Contractor cash-flow risk control when progress-payment review runs overdue: deemed approval of measurements, payment of undisputed portions, and four-layer defense (GB/T 50500-2024)

Review deadlines are not bottomless: absent contractual deadlines, GB/T 50500-2024 Article 7.1.5 establishes "overdue silence = measurement accepted," Article 9.4.11 "undisputed portions paid first," and Article 9.1.7 payment no less than 80% of cumulative completed work value; overdue non-payment supports claims under 9.4.12, and in extreme cases priority-of-payment under Civil Code Article 807 (exercisable within 18 months) and the Regulation on Payment to SMEs. Defense deploys across four layers: contract clauses - process management - legal remedies - self-rescue financing.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • 中华人民共和国民法典 第807条
  • 法释〔2020〕25号 第35~41条
  • 保障中小企业款项支付条例
  • DB11/T 382-2017 建设工程监理规程

Topic Positioning

Compliance conclusions for "how the contractor controls cash-flow risk when progress-payment review drags on": three baseline rules of the interim payment stage in GB/T 50500-2024 (deemed approval of measurements, pay undisputed portions first, payment proportion floor) + remedies like Civil Code priority of payment + a four-layer playbook from ex ante to ex post.

Core Conclusions

Review deadlines are not bottomless: where the contract sets them, they govern; absent agreement, per GB/T 50500-2024: (1) Article 7.1.5 "deemed approval"—if the owner fails to provide reconciliation results within the agreed time, the contractor's measurement may be deemed accepted as the pricing basis; (2) Article 9.4.11 "pay undisputed first"—where only some BOQ items are disputed, a payment certificate must be issued and paid for the undisputed portion; no wholesale freeze; (3) Article 9.1.7 "payment floor"—payment no less than 80% of cumulative completed work value, and safety-measure prepayments must not be recovered from progress payments; (4) Article 9.4.12—overdue non-payment supports claims under Article 8.11.9. Remedy floor: Civil Code Article 807—after demand, agreement to offset by price or request auction with priority of payment (exercisable within 18 months from the due date per Fa Shi [2020] No. 25); the Regulation on Payment to SMEs caps payment at 60 days for government/public-procurement, with overdue interest at the agreed rate or 0.05% per day. Four-layer defense: contract clauses (fixed review deadline + deemed approval + payment >= 80% + undisputed-first + overdue interest); process management (complete measurement dossiers in one submission, ledger trails, written demands on due dates, proactive splitting of disputes, pre-reconciliation with the supervisor); legal remedies (demand -> suspend and claim -> terminate/priority of payment; suspension must be preceded by written demand to avoid counterclaims); self-rescue (advance-funding estimates and financing contingency).

Applicable Boundaries

(1) "Deemed approval" presupposes the contractor's complete written measurement submission and serves only as the pricing basis—not deemed acceptance of the works; (2) where the owner's failure to notify on time prevents the contractor attending on-site verification, the verification result is void; where the contractor fails to attend after notice, it is deemed to accept (Article 9.4.10); (3) priority of payment has an 18-month exclusion period—interest, penalties, and damages are not prioritized; (4) suspension requires prior written demand + contract basis, or counterclaim risk; (5) explicit contract terms prevail—the standard articles are mostly floors for when terms are missing.

Further Reading

GB/T 50500-2024, Articles 7.1.5, 9.1.7, 9.4.10-9.4.12 (interim payment and measurement reconciliation), claims procedure per 8.11.9, advance recovery per 9.2.6 and 9.3.2; Civil Code Article 807; Fa Shi [2020] No. 25 Articles 35-41 (priority scope and 18-month period); Regulation on Payment to SMEs; DB11/T 382-2017 Supervision Regulation, Article 5.3.6 (supervisor's procedure for signing payment certificates).