Whether the contractor may suspend the works when the employer pays progress payments late, and the scope of compensation for suspension losses: the statutory right to suspend exists only for the advance payment and the statutory safety provisions, late progress payment generates only a claim; the model contract text's 28-day procedural suspension right; suspension and idle-time losses enjoy no priority right to payment out of the works price

For a simple late progress payment, neither the law nor the pricing standard gives the contractor an 'automatic right to suspend': GB/T 50500-2024, Clause 9.4.12, says only that 'where the employer does not pay the progress payments as agreed in the contract or pays late, the contractor may claim from the employer under Clause 8.11.9 of this standard', whereas for the advance payment (Clause 9.2.4) and the statutory safety provisions (Clause 9.3.3), if still unpaid after being urged, 'the contractor has the right to suspend the works'. With contractual basis, suspension is possible: under GF-2017-0201, where the employer pays late and fails to correct after written notice, and still does not correct within 28 days after receiving the notice, the contractor may suspend the works 'in the affected parts' and notify the supervising engineer; where suspension lasts 28 full days and defeats the contract purpose, the contract may be terminated, and the employer must pay the 7 categories of sums within 28 days after termination. Compensation is in principle claimable: Civil Code Articles 803 and 804 plus GB/T 50500-2024 Clause 8.11.9 (idle labour, material losses, idle plant, etc.) and Clause 8.11.10 (profit may additionally be claimed for employer-responsible causes), but suspension and idle-time losses enjoy no priority right to payment out of the works price (Fa Shi [2026] No. 12, Article 17, paragraph 2).

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.3、8.11.9、8.11.10、9.2.4、9.3.3、9.4.11、9.4.12条
  • GF-2017-0201《建设工程施工合同(示范文本)》第12.4款、第16.1款
  • 《中华人民共和国民法典》第526、527、563、564、577、584、591、803、804、807条
  • 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十七条、第二十三条
  • 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第二十六条、第二十七条、第四十一条
  • 《保障中小企业款项支付条例》(国务院令第802号,2025修订)第九条、第十五条、第十七条
  • https://www.gov.cn/zhengce/202504/content_7021701.htm
  • http://zjt.shandong.gov.cn/art/2026/7/24/art_102884_10354808.html?xxgkhide=1

Topic positioning

This card answers two questions - 'when the employer withholds progress payments, can the contractor suspend the works, and can it claim the losses' - by separating three distinct things: the statutory suspension right, the contractually agreed suspension right, and the right to compensation for losses; and it draws the line between the advance payment, the statutory safety provisions and the progress payment as regards suspension rights.

Core conclusions

I. Statutory suspension right: none for late progress payment; only for the advance payment and the statutory safety provisions

  • Progress payment: Clause 9.4.12 of GB/T 50500-2024, the national standard for BOQ pricing of construction works, provides only that 'where the employer does not pay the progress payments as agreed in the contract or pays late, the contractor may claim from the employer under Clause 8.11.9 of this standard.' A claim only, no right to suspend. Clause 9.4.11 of the same standard: where the parties dispute the measured and priced results of some BOQ items, the employer shall issue the progress payment certificate and pay the progress payment on the basis of the measurement and pricing results of the undisputed portions (the undisputed portions are paid first).
  • Advance payment: Clause 9.2.4: 'Where the employer does not pay the advance payment at the time agreed in the contract, the contractor may urge the employer to prepay; where the employer still fails to prepay as required within the agreed time after being urged, the contractor has the right to suspend the works, claim from the employer under Clause 8.11.9, paragraph 6, of this standard, and the employer shall bear the liability for breach.'
  • Statutory safety provisions: Clause 9.3.3: 'Where the employer fails to pay the statutory safety provisions at the time agreed in the contract, the contractor may urge the employer to pay; where the employer still fails to pay within the agreed time after being urged, the contractor has the right to suspend the works and the employer shall bear the liability for breach. Where a safety accident occurs because the employer failed to pay the statutory safety provisions on time, the employer shall bear the corresponding responsibility.'
  • Conclusion: without contractual basis, a self-initiated full suspension over late progress payment is at the contractor's own breach risk and may attract a counterclaim for delay liquidated damages; the right path is urging + claim + preservation of claim rights, not walking off the job.

II. The contractually agreed suspension right (GF-2017-0201, model construction contract text)

  • Suspension: item 16.1.1, final paragraph: 'Where the employer commits a breach other than item (7) of this clause, the contractor may notify the employer and require it to take effective measures to correct the breach. Where the employer still fails to correct the breach within 28 days after receiving the contractor's notice, the contractor has the right to suspend the works in the affected parts and notify the supervising engineer.' This is suspension of 'the affected parts', not a full stop, and is conditioned on written notice plus a 28-day waiting period.
  • Termination: item 16.1.3: 'Where, after the contractor has suspended the works under item 16.1.1 (events of employer breach) for 28 full days, the employer still fails to correct its breach and this makes it impossible to achieve the purpose of the contract ... the contractor has the right to terminate the contract, and the employer shall bear the costs thereby increased and pay the contractor a reasonable profit.'
  • Payment after termination: item 16.1.4 requires the employer, within 28 days after termination of the contract, to pay (1) the price of the work completed before termination; (2) the price of materials, engineering equipment and other items already ordered and paid for; (3) the sums for evacuating the site and dismissing personnel; (4) the liquidated damages payable before termination; (5) other sums payable; (6) the retention money to be returned; (7) the losses caused by the termination; and to release the performance security.
  • Progress payment procedural nodes (item 12.4.4 of the same text): the supervising engineer completes the review within 7 days of receiving the progress payment application and the accompanying documents and forwards them to the employer; the employer completes the approval and issues the progress payment certificate within 7 days of receipt; failure to approve within the time and to raise objections is deemed issuance of the certificate; payment is completed within 14 days after the certificate (including interim certificates) is issued; late payment bears liquidated damages at the benchmark rate of the People's Bank of China for similar loans of the same period.
  • Events of employer breach (item 16.1.1) include 'failure to pay the contract price as agreed for reasons attributable to the employer', 'suspension of the works caused by the employer's breach of the contract', and 'the employer failing, without justified reason, to issue resumption instructions within the agreed period so that the contractor cannot resume the works'.

III. The right to compensation and its scope

  • Civil Code Article 803: 'Where the employer fails to provide the raw materials, equipment, site, funds or technical data at the agreed time and according to the agreed requirements, the contractor may extend the construction period and claim compensation for the losses from suspension of the works and idle time.' (Unpaid works payments fall under 'funds' not provided as agreed.)
  • Civil Code Article 804: 'Where the works are stopped or slowed down midway for reasons attributable to the employer, the employer shall take measures to remedy or reduce the loss, and compensate the contractor for the losses and actual expenses thereby caused, including suspension of the works, idle time, re-handling, relocation of machinery and equipment, and the accumulation of materials and components.'
  • Scope under the pricing standard, GB/T 50500-2024, Clause 8.11.9: where an event not attributable to the contractor causes economic loss, increased costs and/or delay, the following may be claimed: (i) cost losses of labour, materials, plant, water and electricity from suspension, waiting, reduced efficiency or extended duration; (ii) the increase or decrease in direct costs from price changes caused by adjustment of the contract duration (except where adjusted under Clause 8.7.4); (iii) the necessary measure costs of suspension, resumption and maintenance of the site; (iv) the direct costs of rework, demolition and modification and repair, and the direct losses of scrapped or damaged materials; (v) additionally incurred inspection and testing costs; (vi) losses caused by non-payment of the contract price as agreed; (vii) the effects of suspension, interruption or stopping caused by cultural relics and historic sites; (viii) other losses the contractor can prove, and VAT; (ix) reasonable extension of the duration. Suspension losses specifically include: (1) idle labour costs of personnel already on site who cannot work; (2) the losses of materials already on site that cannot be put to use; (3) the idle plant costs of construction equipment already on site that cannot work; (4) other cost losses.
  • Profit: Clause 8.11.10 provides that for causes attributable to the employer (including 'delay, suspension of the works, or failure to resume on time after suspension, caused by the employer', 'the employer's late provision of the construction drawings or the construction site', 'failure to approve in good time as agreed, or interference with the normal construction sequence'), besides claiming the losses under Clause 8.11.9, profit may also be claimed; 'unless otherwise provided in the contract, claims for the works caused by causes of the employer's breach of contract may include profit'. Where the cause lies with a government authority, the duration is extended accordingly and each party bears its own economic loss.
  • Compensation boundary: the damages shall be equivalent to the losses caused by the breach (including the benefits obtainable after performance of the contract), but may not exceed the losses which the breaching party foresaw or ought to have foreseen at the time of contracting (Civil Code Article 584); the injured party shall take proper measures to prevent the enlargement of the loss, and may not claim the enlarged part it failed to prevent, the reasonable costs of prevention being borne by the breaching party (Article 591); a party that fails to perform, or performs inconsistently with the agreement, shall bear liability for breach by continued performance, remedial measures or compensation (Article 577).
  • Defences and termination: where performance is sequential and the party due to perform first (e.g. to pay as agreed or provide the site) fails to perform, the contractor performing later may reject its corresponding demand for performance (Article 526); with conclusive evidence that the employer's business condition has seriously deteriorated, that it transfers assets or evades funds, or that it has lost commercial credit or a circumstance showing loss of capacity to perform, performance may be suspended - suspending without conclusive evidence attracts liability for breach (Article 527); where a party delays performance of a principal debt and still fails to perform within a reasonable period after being urged, or the breach makes it impossible to achieve the purpose of the contract, the contract may be terminated (Article 563, paragraph 1, items (iii) and (iv)); the right to terminate extinguishes if not exercised within one year from the date of knowing, or ought to have known, the grounds for termination, or within a reasonable period after being urged (Article 564).
  • Exclusion from the priority right: Fa Shi [2026] No. 12, Article 17, paragraph 2: 'Where the contractor claims to enjoy the priority right to payment out of the construction works price for the losses from suspension of the works and idle time caused by the employer, the people's court will not support it.' The debt for idle-time losses is established and can be sued for, but enjoys no priority in order over mortgages and other debts; the Interpretation takes effect on 30 June 2026 and applies to newly accepted first-instance cases (Article 23).
  • Overdue interest: as agreed; absent agreement, interest runs at the rate for similar loans of the same period or the loan prime rate of the same period (Fa Shi [2020] No. 25, Article 26); interest runs from the date the works price fell due; where no payment time is agreed: the date of actual delivery, or, if not delivered, the date of submitting the final account documents, or, if neither delivered nor settled, the date of filing suit (Article 27). A contractor whose counterparty is a government agency, public institution or large enterprise and which qualifies as an SME may also claim overdue interest under the Regulation on Ensuring Payment to SMEs (the agreed rate not lower than the 1-year LPR at the time of contracting; absent agreement, a daily rate of 0.05%).

IV. The claim procedure (if the procedure is missed, the substance may fail) Under GB/T 50500-2024, Clause 8.11.3, where the contract fixes no time limit: submit a written notice of claim for the works within 28 days of the claim event (stating the cause and the claim intent) -> submit a written claim report within 28 days of the notice (cause, the contract clauses relied on, the costs and/or days of extension claimed, the supporting records and the cost computation sheets) -> claims involving both costs and duration shall be raised together -> for events of continuing effect, submit continuing notices of intent at the agreed intervals (absent agreement, no more than 28 days) or at reasonable intervals, listing the cumulative costs/days -> submit the final claim report within 28 days after the event ends. Late submission means that, 'except as otherwise agreed in the contract and otherwise provided by laws and regulations, the relevant claim for the works may be deemed waived'; where the claiming party submits the report as agreed and the other party fails to reply within the agreed time, 'the relevant claim for the works demanded by the claiming party may be deemed approved'. The 'notice - 28-day correction period' of GF-2017-0201 and the '28-day notice + 28-day report' of the pricing standard are two parallel clocks; in practice the same event should satisfy both: a written notice to the employer to correct the breach, and a contemporaneous notice of claim.

Applicability boundaries

  • The conclusion 'no automatic suspension right' concerns late progress payments; for the advance payment and the statutory safety provisions, the standard expressly authorises suspension after urgence without payment.
  • Where the contract (particular conditions) separately provides a suspension right, or excludes the final paragraph of item 16.1.1 of the model text, the agreement prevails; GB/T 50500-2024 is a recommended standard and binds only once incorporated by the contract.
  • Suspension must be confined to 'the affected parts' and be reasonable as mitigation: unnecessary large-scale suspension, or failure to take the necessary protection and caretaking measures during suspension, forfeits compensation for the enlarged losses (Civil Code Article 591).
  • Suspension and idle-time losses are ordinary debts without priority; the principal of the works price may still claim priority payment from the proceeds of the discounting or auction of the works under Civil Code Article 807 (exercise period at most 18 months, running from the date the employer ought to pay the works price).
  • For force majeure, or suspension required by a government authority, loss sharing and extension of time follow GB/T 50500-2024, Clauses 8.11.12-8.11.14, and the contract's force majeure clause; the claim scope for the employer's breach cannot be applied by analogy.

Further reading

  • GB/T 50500-2024, national BOQ pricing standard: Clause 9.2.4 (advance payment), Clause 9.3.3 (statutory safety provisions), Clauses 9.4.11-9.4.12 (progress payment checking and late payment claims), Clause 8.11.3 (claim procedure), Clause 8.11.9 (loss claim scope), Clause 8.11.10 (profit claim events).
  • GF-2017-0201, model construction contract text: Clause 12.4 (progress payment), Clause 16.1 (employer breach: events, liability, termination, post-termination payment), Clause 19 (claims).
  • Civil Code Articles 526, 527, 563, 564, 577, 584, 591, 803, 804, 807.
  • Fa Shi [2026] No. 12 (SPC Interpretation on Construction Contract Disputes (II)), Articles 17 and 23; Fa Shi [2020] No. 25, Articles 26, 27 and 41.
  • Regulation on Ensuring Payment to SMEs (State Council Decree No. 802, 2025 revision): Article 9 (30 days, 60 at most; 60 days for large enterprises), Article 15 (undisputed portions paid first), Article 17 (overdue interest); State Council policy document library: https://www.gov.cn/zhengce/202504/content_7021701.htm ; example of a local implementing document: http://zjt.shandong.gov.cn/art/2026/7/24/art_102884_10354808.html?xxgkhide=1