Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-11

Computing and compensating suspension and idle-resource losses caused by the employer: idle labour costs, plant standby costs (hired vs owned plant), suspension overheads and suspension profit

Where the employer causes the suspension, the employer bears the costs (GB/T 51262-2017 Article 5.8.3); the contractor may claim, under GB/T 50500-2024 Article 8.11.9, idle costs of mobilised labour, losses of mobilised materials, plant standby costs and other losses, and Article 8.11.10 allows a further profit claim for employer-fault causes (including suspension and failure to resume on time). Computation per T/YJXB 0001-2023: the actual-outlay method first for wages with the rule-based method as fallback, and outlays objectively unnecessary are not counted (5.0.5 / 4.0.5); plant standby costs - hired plant at the hire charges actually incurred, owned plant at the machine-shift quota (5.0.3); suspension overheads = daily overheads (total contract overheads / contract duration) x reasonable ratio x suspension days, neither above normal construction nor zero (5.0.8 / 4.0.8); suspension profit = daily profit x reasonable ratio x suspension days, being loss of expectation interest (5.0.9 / 4.0.9).

Applicable Codes

  • GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.8.3条
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.9条、第8.11.10条
  • T/YJXB 0001-2023《建设工程停工承包人费用计算标准》第5.0.3条、第5.0.5条、第5.0.8条、第5.0.9条
  • 《山东省建设工程施工机械台班费用编制规则》第6.0.1条
  • 湖南省2025版消耗量标准附录

Scope of the question

On suspension caused by the employer (or other non-contractor causes): the cost make-up of the contractor's suspension and idle-resource losses, the computation formulas, and the compensation / depreciation differences between hired and owned plant. Basis: GB/T 51262-2017, GB/T 50500-2024 and T/YJXB 0001-2023.

Core conclusions

1. Cost bearing and assessment rules (GB/T 51262-2017 Code for Construction Cost Expert Assessment, Article 5.8.3) Where the parties dispute suspension claim costs, the appraiser proceeds as follows: 1 Where the contract allocates these costs, assess per the contract. 2 Employer-caused suspension costs are borne by the employer, including protection of completed works, safekeeping of materials and plant delivered to site, plant hire charges, wages of site production workers and management staff, and the contractor's preparations for resumption. 3 Contractor-caused suspension costs are borne by the contractor.

2. Claimable loss items (GB/T 50500-2024, Article 8.11.9) Where stoppage, waiting, reduced efficiency or delay not caused by the contractor causes economic loss, cost increase and / or delay, the contractor may claim. Losses of labour, materials and plant from stoppage, waiting, reduced efficiency and delay include: (1) idle costs of mobilised personnel unable to work; (2) losses of mobilised materials unusable; (3) standby costs of mobilised plant unable to work; (4) other cost losses. Article 8.11.10: for events caused by the employer's fault (including employer-caused delay, suspension, and failure to resume on time after suspension), the contractor may claim profit in addition to the Article 8.11.9 losses. Save as the contract provides otherwise, claims arising from the employer's breach may include profit; losses or delay caused by government authorities extend the time, the economic losses of each party being borne by itself.

3. Idle labour cost method (T/YJXB 0001-2023 Standard for Computing Contractor's Suspension Costs, Article 5.0.5) 1 Actual-outlay method: site production workers' wages per amounts actually paid (preferred); 2 Rule-based method: wages per or by reference to laws, regulations, codes, standards and policy documents (fallback). Counting principle (4.0.5): wages accrue for production workers waiting on site; where wages must be paid through the suspension, the resulting cost increase counts; where objectively and actually unpaid, it does not. Idle costs of machine operators (drivers, signalers) are listed or charged within plant standby costs.

4. Plant standby cost method (T/YJXB 0001-2023 Articles 5.0.3 and 2.0.4) Plant standby cost means the cost of site plant standing idle during suspension (2.0.4) - hire charges may continue on hired plant, and owned plant also accrues standby costs. Basis (5.0.3): (1) hired plant at hire charges actually incurred (actual-outlay); (2) owned plant at the machine-shift quota (rule-based). I.e. hired at actual hire, owned at the machine-shift quota. Quota basis (Shandong plant machine-shift cost compilation rules, Article 6.0.1; Hunan 2025 appendix): standby cost = depreciation + labour + other; Hunan takes the standby machine-shift at its depreciation, the number of standby shifts and operators' idle costs by bilateral certified record; where plant is in fact hired, standby price and count follow the hire contract and site certifications (deducting fuel and power and labour), with operators' idle costs separate. Hired vs owned compensation / depreciation differences: owned plant has no actual hire outlay, so standby follows the machine-shift quota, chiefly depreciation (no overhaul, maintenance or power, since none occur while idle); hired plant bears no asset depreciation, compensation follows rent actually paid, deducting fuel, power and labour not incurred, operators' idle costs separate. The two must not be double counted.

5. Suspension overheads and profit (T/YJXB 0001-2023 Articles 5.0.8, 5.0.9) Suspension overheads = daily overheads x reasonable ratio x suspension days; daily overheads = total contract overheads / contract duration. Overheads span 15 sub-accounts, computed by actual outlay where possible, else by a suitable ratio under the rule-based method. Management is usually not dismissed in suspension: overheads should be neither above normal construction nor zero (4.0.8). Suspension profit = daily profit x reasonable ratio x suspension days; daily profit = total contract profit (or per the profit rate of the local statistical yearbook of construction enterprises) / contract duration. Suspension profit is not money currently paid out by the contractor - it is loss of expectation interest, computed by a suitable ratio under the rule-based method (5.0.9, 4.0.9); FIDIC and the model construction contract both admit reasonable profit on suspension.

Applicability limits

  • Applies to suspension / idle-resource claims caused by the employer's fault (or allocated to the employer by contract); contractor-caused costs are his own; force majeure losses and delay follow GB/T 50500-2024 Articles 8.11.12 to 8.11.14.
  • Contract allocations of these costs govern the assessment.
  • Actual outlay first, rule-based fallback; outlays objectively unnecessary or not incurred are not counted.
  • Claims are limited by the duty to mitigate and foreseeability (Civil Code Articles 591 and 584) and must be notified within the contract period (28 days absent agreement).
  • T/YJXB 0001-2023 is an association standard, binding when invoked by the contract, otherwise a method reference; each reasonable ratio is fixed per case, contract and certifications, not mechanically.

Further reading

  • GB/T 51262-2017 Code for Construction Cost Expert Assessment, Article 5.8.3 (suspension claim costs and assessment).
  • GB/T 50500-2024 China national pricing standard for BOQ: Article 8.11.9 (non-contractor-cause loss claims), 8.11.10 (profit for employer-fault causes), 8.11.12 to 8.11.14 (force majeure).
  • T/YJXB 0001-2023 Standard for Computing Contractor's Suspension Costs: Article 2.0.4 (standby term), 4.0.5 / 4.0.8 / 4.0.9 (cost items), 5.0.3 / 5.0.5 / 5.0.8 / 5.0.9 (methods).
  • Shandong plant machine-shift cost compilation rules, Article 6.0.1 (standby = depreciation + labour + other); Hunan 2025 consumption standard appendix (standby at depreciation; operators' idle costs separate).
  • Evidence requirements per item: see the suspension-claim evidence checklist card; the full menu of suspension cost items: see the non-contractor-cause cost list card.