Start and end dates for calculating standby rent and standby costs of standing construction plant (hired or owned): to which date they run absent a demobilisation site record, the presumption of the due demobilisation date, and the boundary set by the duty to mitigate

Absence of a demobilisation site record does not defeat the standby-cost claim; it only changes the mode of proof (T/YJXB 0001-2023, Art. 3.0.3: a site record governs where one exists; otherwise the standard applies). Standby rent claimable against the employer runs to the earlier of the 'actual demobilisation date' and the 'due demobilisation date': the due date = suspension date + about 30 days + a reasonable removal period (Art. 4.0.12 takes 'a fairly long suspension, generally more than 30 days' as the yardstick for when demobilisation should occur); where the employer instructs in writing that plant remain on site or demobilisation is objectively impossible, the boundary is the date the instruction ends or the actual demobilisation date; any overstay beyond that is enlarged loss under Article 591 of the Civil Code, borne by the contractor itself. Towards the lessor, rent runs under the hire contract until the plant is actually returned.

Applicable Codes

  • 《中华人民共和国民法典》第五百八十四条
  • 《中华人民共和国民法典》第五百九十条
  • 《中华人民共和国民法典》第五百九十一条
  • 《中华人民共和国民法典》第八百零四条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第8.11.9条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第8.11.10条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第8.11.12条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第8.11.13条
  • T/YJXB 0001-2023 建设工程停工承包人费用计算标准 第3.0.3条、第3.0.9条、第4.0.3条、第4.0.12条、第5.0.3条、第6.0.3条
  • GF-2017-0201 建设工程施工合同(示范文本)第7.8.6项、第7.8.8项
  • 法释〔2020〕25号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)第二十条
  • 法释〔2026〕12号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)第十七条、第二十三条(自2026年6月30日起施行)
  • https://www.mohurd.gov.cn/gongkai/fdzdgknr/zgzygwywj/art/2022/art_402_769104.html
  • https://jst.sc.gov.cn/scjst/c101448/2026/8/19/50906a8da925400883bfd8793b15b357.shtml
  • http://zfcj.gz.gov.cn/zjdt/zjxw/content/post_11007841.html
  • http://zjt.gxzf.gov.cn/zfxxgk/fdzdgknr/fgwj/xzgfxwj/t19536323.shtml

Topic scope

Where construction plant on site has stood idle but no demobilisation site record (return of hired plant) has been certified, to which date do standby rent or standby costs run in time: the start date, the end date, how the due demobilisation date is presumed, and how the duty to mitigate splits the claimable period from the unclaimable period. It applies to contractors claiming suspension and idle-time losses against the employer, and equally to distinguishing the contractor's payment obligations towards the plant lessor.

Core conclusions

1. Absence of a site record does not defeat the claim; it only changes the mode of proof. T/YJXB 0001-2023, Art. 3.0.3: 'Where the suspension costs listed in this standard are covered by a site record, the site record governs; where there is no site record, this standard may be applied.' Fa Shi [2020] No. 25, Article 20: 'Where the parties dispute the quantities of the works, they shall be ascertained on the basis of site records and other written documents formed during construction. Where the contractor can prove that the employer consented to its construction but cannot produce site records to prove the quantities, the actual quantities may be ascertained on the basis of other evidence provided by the parties.' So, when the demobilisation record is missing, substitute proof is available: supervisor logs, minutes of site meetings, correspondence, plant entry and exit acceptance sheets, rental settlement statements, photographic and video material.

2. The calculation period runs from the start date to the end date, and the end date is the earlier of the two candidate dates.

Billable days = end date - start date + 1 (calendar days) Claimable standby rent = daily rent x billable days End date = min(actual demobilisation date, due demobilisation date); where the employer has instructed in writing that the plant stay on site or demobilisation is objectively impossible, end date = actual demobilisation date (or the date the instruction ends) Due demobilisation date = suspension date + 30 days + reasonable removal period (as agreed where the contract so provides; absent agreement, the period actually needed to dismantle and haul the plant out, usually 7-15 days, subject to proof) Daily rent = monthly rent / days of that month, or the daily rate agreed in the hire contract

3. The '30 days' is a reasonableness yardstick of the industry standard, not a statutory uniform period. It comes from T/YJXB 0001-2023, Art. 4.0.12: 'Where during suspension the contractor demobilises to avoid enlargement of the loss, the demobilisation costs of the suspension shall be allowed. Where the suspension lasts fairly long (generally more than 30 days) and the contractor withdraws personnel, equipment and plant to avoid enlargement of the loss, the corresponding demobilisation costs are not included in the price of the works and shall be allowed.' So 30 days serves as a reference mark that 'the suspension has become long and the contractor ought to consider demobilising'; the final test is the contract agreement and the reasonableness of the individual case.

4. The duty to mitigate is the legal basis of the end date. T/YJXB 0001-2023, Art. 3.0.9: 'After the works are suspended, the contractor shall take measures to reduce or prevent enlargement of the loss... Where the suspension is not caused by the contractor, the contractor is obliged to avoid enlargement of the loss; where the contractor fails to take measures so that the loss is enlarged, it shall bear the enlarged loss and may not claim the enlarged loss from the other party.' Its superior law is Article 591 of the Civil Code: 'Where one party breaches, the other party shall take appropriate measures to prevent enlargement of the loss; where it fails to take appropriate measures so that the loss is enlarged, it may not claim damages for the enlarged part. Reasonable expenses incurred by the party in preventing enlargement of the loss shall be borne by the breaching party.' The latter sentence is also the basis for allowing demobilisation costs: a reasonable demobilisation is not money wasted, and the costs are borne by the party in breach.

5. Basis of the claim and characterisation of the cost. Article 804 of the Civil Code: 'Where for reasons attributable to the employer the works are suspended part-way or slowed down, the employer shall take measures to remedy or reduce the loss and compensate the contractor for the losses and actual expenses thereby caused, including suspension, idle time, re-handling, relocation of plant and machinery, and accumulation of materials and components.' GB/T 50500-2024, Art. 8.11.9, lists 'losses of labour, materials, plant and machinery, and water and electricity consumption caused by suspension, waiting, reduced efficiency, extension of the period and the like' among claimable events not caused by the contractor, and states that the losses include 'standby costs of construction plant already on site that cannot be put to work'; Art. 8.11.10 adds profit to the claimable heads where the cause lies with the employer's responsibility (including suspension of the works and failure to resume on time after suspension). The amount of compensation is capped by the foreseeability rule of Article 584 of the Civil Code: '...the damages shall be equivalent to the loss caused by the breach, including the benefits obtainable after performance of the contract; but they shall not exceed the loss that the breaching party foresaw or should have foreseen at the time of concluding the contract as likely to be caused by the breach.'

6. Comparison of start and end scenarios

Start scenario Start date Runs to (end) Key basis
Written suspension order, attributable to the employer Suspension date stated in the order; if unstated, the actual stand-down date The earlier of the resumption notice date and the actual demobilisation date Civil Code Art. 804; GB/T 50500-2024 Art. 8.11.9
No written order but attributable to the employer Actual idle date (proved by supervisor logs, meeting minutes, correspondence) Actual demobilisation date Fa Shi [2020] No. 25 Art. 20; T/YJXB 0001-2023 Art. 6.0.3
Long suspension, no prospect of resumption Suspension date Suspension date + about 30 days + reasonable removal period T/YJXB 0001-2023 Art. 3.0.9, Art. 4.0.12; Civil Code Art. 591
Employer instructs in writing that plant stay on site pending resumption Suspension date Date the instruction ends or resumption date Civil Code Art. 804; GF-2017-0201 item 7.8.6
Contract terminated, or the work cancelled by variation Date termination takes effect / date of the variation instruction Termination or variation date + reasonable removal period Civil Code Art. 591; T/YJXB 0001-2023 Art. 4.0.12
Standby machine-shifts or rent already certified by a site record Date stated in the record Date stated in the record T/YJXB 0001-2023 Art. 3.0.3
Suspension caused by the contractor No start point accrues - GF-2017-0201 item 7.8.2
Force majeure - No standby cost accrues GB/T 50500-2024 Art. 8.11.12 para 2 (stand-down losses of plant borne by the contractor)
Suspension or control required by a government authority - Each side bears its own losses; period extended GB/T 50500-2024 Art. 8.11.13

7. Points of proof (evidence chain without a demobilisation record): T/YJXB 0001-2023, Art. 6.0.3, requires 'plant entry and exit acceptance sheets for the suspension period, hire contracts, schedules of construction plant, the project execution plan, notarial certificates, rental settlement statements, reconciliation statements, electronic records and other supporting materials'; and 'during suspension, where hired construction plant continues to incur rent, the construction enterprise must provide corresponding evidence of the rental loss during the suspension. For owned plant, evidence must show how the contractor's own plant was deployed on site.' Evidence of the reasonableness of mitigation should also be strengthened (for instance, letters showing the lessor refused early termination of the hire, records of acceptance of return formalities, and an explanation that the plant genuinely had no further use on this project), to support the point that 'failure to demobilise was not passive inaction'.

Boundaries of application

  1. Two accounts must not be mixed: towards the lessor, rent is paid under the hire contract until the plant is actually returned (privity of contract; in principle rent continues until return); against the employer, compensation is subject to the triple limits of necessity, reasonableness and foreseeability (Civil Code Art. 584) and the duty to mitigate (Art. 591), and the portion beyond a reasonable overstay period is the contractor's own. Minimum or fixed hire periods agreed in the hire contract cannot be converted directly into the scope of compensation by the employer.
  2. Attribution first: where the suspension is caused by the contractor, by force majeure or by control of a government authority, plant standby losses may in principle not be claimed against the employer (GB/T 50500-2024 Art. 8.11.12 para 2, Art. 8.11.13; Civil Code Art. 590 on exemption for force majeure and the duties of timely notice and of proof within a reasonable period).
  3. Contract agreement prevails over the 30-day reference value: where the particular conditions stipulate a standby period, a demobilisation deadline or a standard for plant standby costs, the agreement governs; the '30 days + reasonable removal period' operates as a reasonableness presumption only where there is no agreement or the agreement is unclear, and must be proved in light of the scale of the suspension and the prospect of resumption; it should not be applied mechanically.
  4. Pricing bases differ: hired plant is priced on the rental cost actually incurred (contract daily rates, settlement statements); owned plant is priced on standby cost under the plant rate norms per machine-shift (T/YJXB 0001-2023, Art. 5.0.3); rental cost and machine-shift standby cost must not both be claimed for the same item of plant.
  5. No priority right of payment: Fa Shi [2026] No. 12, Article 17, paragraph 2: 'Where the contractor claims to enjoy a priority right of payment out of the price of the construction works for losses such as suspension and idle time caused by the employer, the people's court shall not support the claim.' The debt is claimable but enjoys no priority; under Article 23, the Interpretation takes effect on 30 June 2026 and applies to first-instance construction contract dispute cases newly accepted after that date, earlier-accepted cases following the old rules.

Further reading

  • Civil Code, Article 584 (foreseeability rule), Article 590 (exemption for force majeure and duty of notice), Article 591 (duty to mitigate and bearing of mitigation costs), Article 804 (scope of compensation where the employer suspends or slows the works part-way, and the phrase 'actual expenses').
  • GB/T 50500-2024, national pricing standard for bills of quantities, Art. 8.11.9 (list of claimable events not caused by the contractor and composition of plant standby costs), Art. 8.11.10 (profit additionally claimable where the cause lies with the employer's responsibility), Art. 8.11.12 (sharing of force majeure losses), Art. 8.11.13 (exceptional events such as suspension ordered by government authorities).
  • T/YJXB 0001-2023, Standard for Calculating the Contractor's Costs upon Suspension of Construction Works, Art. 3.0.3 (site record prevails), Art. 3.0.9 (duty to mitigate), Art. 4.0.3 (standby cost of retained plant), Art. 4.0.12 (demobilisation costs and the 30-day yardstick), Art. 5.0.3 (actual-expenditure method / rule-standard method), Art. 6.0.3 (list of evidentiary materials).
  • GF-2017-0201, model construction contract, item 7.8.6 (notice to resume after suspension exceeding 56 days, price adjustment or termination rights after 84 days), item 7.8.8 (both parties shall take necessary measures during suspension to prevent enlargement of loss).
  • Fa Shi [2020] No. 25, Article 20 (ascertaining actual quantities by other evidence absent site records); Fa Shi [2026] No. 12, Articles 17 and 23 (no priority right of payment for suspension and idle-time losses; cut-off of application).
  • Publicly released documents of local housing and construction authorities may serve as local reference, e.g. the Ministry of Housing and Urban-Rural Development page https://www.mohurd.gov.cn/gongkai/fdzdgknr/zgzygwywj/art/2022/art_402_769104.html , the Sichuan Provincial Department of Housing and Construction https://jst.sc.gov.cn/scjst/c101448/2026/8/19/50906a8da925400883bfd8793b15b357.shtml , the Guangzhou Municipal Housing and Construction Bureau http://zfcj.gz.gov.cn/zjdt/zjxw/content/post_11007841.html , and the Guangxi Department of Housing and Construction http://zjt.gxzf.gov.cn/zfxxgk/fdzdgknr/fgwj/xzgfxwj/t19536323.shtml .

Keywords

  • 施工机具停滞费
  • 机械停置费
  • 退场签证
  • 减损义务
  • 民法典第591条
  • 停滞费计算期间
  • 设备租金
  • 停工索赔