Calculation of plant standby costs when the works stand suspended for reasons attributable to the employer: standby cost = standby rate per machine-shift x number of standby machine-shifts, the cost components of the standby machine-shift rate, whether overheads and profit are taken, and the difference in compensation scope between contractor-owned plant (priced on machine-shift rate norms) and hired plant (priced on hire charges)
Plant standby cost = sum of (standby rate per machine-shift x number of standby machine-shifts); the number of standby machine-shifts is fixed as 'idle plant units x days of suspension x machine-shift conversion factor per day (an 8h working day = 1 machine-shift per unit per day)'. Under T/YJXB 0001-2023 Clause 5.0.3: hired plant is priced on the hire charges actually incurred during the suspension, and contractor-owned plant on the machine-shift rate norms. The standby rate per machine-shift is built up from depreciation + labour cost + other charges (the Shandong and Jiangsu scope); the Hunan scope takes machine-shift depreciation only, with idle operator and banksman costs calculated separately per certified site records; repair, maintenance and power charges are excluded. The standby rate carries no uplift for overheads or profit; where the employer is liable, profit may be claimed separately under GB/T 50500-2024 Clause 8.11.10 (listed alone under the suspension-profit rule, not duplicated inside the machine-shift rate).
Applicable Codes
- T/YJXB 0001-2023 建设工程停工承包人费用计算标准 第1.0.2、5.0.3、5.0.8、5.0.9、6.0.3条
- GB/T 50500-2024 建设工程工程量清单计价标准 第8.11.3、8.11.9、8.11.10条
- GB 50500-2013 建设工程工程量清单计价规范 第9.13.2、9.13.3、9.13.4、9.13.6条、第9.14节及第9.14.2、9.14.3条(已被 GB/T 50500-2024 替代)
- GF-2017-0201 建设工程施工合同(示范文本)第19.1、19.2、19.5款
- 山东省建设工程施工机械台班费用编制规则 第6.0.1、6.0.2条
- 江苏省建设工程施工机具台班费用编制参考表(2026版)说明八、九
- 湖南省2025消耗量标准附录(机械台班)说明九、十
- TB/T 10814-2024 铁路工程施工机具台班费用定额 第1.0.4条
- DBJ41/T 208-2018 建设工程监理工作标准 第7.1.4、9.2.4条
Topic positioning
When the works are suspended for reasons attributable to the employer (or otherwise not to the contractor), this card covers the calculation model for on-site plant standby costs (machine-shift standby costs), the cost components of the standby machine-shift rate, the treatment of overheads and profit, the differences and evidentiary requirements between the two compensation routes for contractor-owned and hired plant, and the linkage with site records and the claims procedure.
Core conclusions
I. Calculation model Plant standby cost = sum over i of (standby rate per machine-shift_i x number of standby machine-shifts_i) Number of standby machine-shifts_i = idle plant units_i x days of suspension x machine-shift conversion factor per day
| Variable | Definition | Basis of value |
|---|---|---|
| Standby rate per machine-shift_i | The chargeable cost of one machine-shift (8h) of that plant model in the standing state | Contractor-owned plant: taken from the machine-shift rate norms of the same period; hired plant: the rate under the hire contract (or the hire actually incurred) |
| Idle plant units_i | Units of that model retained on site for the works during the suspension and not yet demobilised | Evidenced by mobilisation and demobilisation acceptance sheets, the plant list, site instruction records and the supervising engineer's diary; units demobilised early or retained unnecessarily are excluded (duty to mitigate) |
| Days of suspension | From the suspension order (or the actual stoppage) to resumption, in calendar days | Locked by the suspension order, the resumption order and the supervising engineer's diary; agreed terms prevail where the contract provides otherwise |
| Machine-shift conversion factor per day | Usually 1 machine-shift per unit per day (an 8h working day); part days converted at actual standby hours / 8 | TB/T 10814-2024 Clause 1.0.4: the plant rate per machine-shift means all charges incurred by one item of construction plant in normal operation over one working shift (8h) |
The cause of the standstill must lie outside the plant itself. Shandong rule 6.0.1, source wording: 'construction plant standby cost means the cost incurred during a period in which construction plant stands idle for reasons not attributable to the plant itself.'
II. Normative basis of the calculation method (source wording) T/YJXB 0001-2023 'Standard for calculation of contractor costs upon suspension of construction works', Clause 5.0.3, source wording: 'The standby cost of construction plant may be calculated by the following methods. Actual-expenditure method: calculated on the plant hire charges actually paid during the suspension. Rule-based method: the standby cost of construction plant during the suspension is calculated on, or by reference to, the machine-shift rate norms of the same period. Standby cost of construction plant: hired plant on the hire charges actually incurred; contractor-owned plant on the machine-shift rate norms.' Scope of application (Clause 1.0.2, source wording): 'This standard applies to pricing activities where the works are suspended mid-course for reasons not attributable to the contractor, causing increases in the contractor's costs and the loss of reasonable profit.'
III. Cost components of the standby machine-shift rate (per the rule documents of the provincial quota stations, source wording)
- 'Compilation rules for machine-shift rates of Shandong construction plant', Clause 6.0.1: 'construction plant standby cost = depreciation + labour cost + other charges'; Clause 6.0.2: 'construction plant hire charges are determined by each region and sector by reference to the hire market and in light of its own actual conditions.'
- 'Jiangsu reference tables of machine-shift rates for construction plant and tools' (2026 edition), note 8: 'the plant standby machine-shift rate is composed of the depreciation, other charges and labour cost of the plant, the labour cost being calculated on the idle operator-hours on the machine caused by the plant standing idle on site.'
- 'Hunan 2025 consumption standard appendix (plant machine-shifts)', note 10: 'the plant standby machine-shift cost is calculated on the machine-shift depreciation; the number of plant standby machine-shifts and the idle cost of operating and directing personnel during the standby period are calculated per site records certified by both parties; where hired plant is actually in use, its standby machine-shift rate and number are calculated by the parties per the hire contract and the site records (deducting fuel and power charges and labour), with personnel idle costs counted separately; the cost of plant fittings during the standby period is calculated per the certified site records.'
- Excluded items: repair charge, maintenance charge and power charge (no repairs are done and no fuel or power is consumed during the standby). Maintenance must not be double-counted - TB/T 10814-2024 Clause 1.0.4 states that the machine-shift maintenance charge already includes 'the maintenance cost of the plant during the standby period'.
- Machine-shift depreciation (the core item for contractor-owned plant) = budget price x (1 - residual value rate) / total durable machine-shifts (TB/T 10814-2024 Clause 1.0.4); the residual value rate is taken at 4% up to 1 million yuan (inclusive) and 3% above, 2% for hauling plant and 5% for tunnelling plant.
IV. Overheads and profit
- The standby machine-shift rate itself carries no uplift for overheads or profit - the provincial quota stations limit the standby rate components to depreciation, labour cost and other charges (Hunan narrower still: machine-shift depreciation only).
- Yet, as claim value, the standby cost supports a separate claim for profit where the employer is liable: GB/T 50500-2024 Clause 8.11.10 provides that where an event arises from causes attributable to the employer (including 'delay caused by the employer, suspension of the works, or failure to resume on time after suspension'), the contractor, beyond claiming its losses under Clause 8.11.9, 'may also claim profit'; economic losses caused by government authorities are borne by the parties respectively, the time for completion being extended accordingly.
- Profit is listed separately under the suspension-profit rule and is not duplicated inside the standby machine-shift rate: T/YJXB 0001-2023 Clause 5.0.9: 'calculated as a reasonable proportion of average daily profit multiplied by the days of suspension. Average daily profit is the total contract profit, or the total profit calculated at the profit rate of the statistical annual report of construction enterprises published by the statistics authority at the place of the works, divided by the contract duration.' Clause 5.0.8 applies the same method to suspension overheads (average daily overheads = total contract overheads / contract duration).
V. Compensation scope: contractor-owned plant versus hired plant
| Item | Contractor-owned plant (rule-based method) | Hired plant (actual-expenditure method) |
|---|---|---|
| Pricing basis | Standby machine-shift rate from the machine-shift rate norms of the same period (depreciation + labour cost + other charges) | Hire actually paid during the suspension (hire contract rate x units x days) |
| Depreciation | Amortised as machine-shift depreciation - the principal compensation item for owned plant | Not counted separately (the hire already returns the owner's capital cost) |
| Deductions | No hire outlay, nothing deducted | Hunan scope: deduct fuel and power charges and labour; personnel idle cost counted separately |
| Evidence | Must show the deployment of owned plant on site (list, mobilisation and demobilisation acceptance sheets) | Must show that hire remained payable during the suspension (hire contract, hire settlement sheets, statements) |
| Double counting | The two routes are mutually exclusive; one and the same machine may not be priced both on the machine-shift norms and on hire | Same |
Jiangsu 2026 reference tables, note 9, add an important boundary: 'these reference tables compile rates for contractor-owned plant amortised over its total durable machine-shifts; they do not apply to determining the market hire prices of plant.'
VI. Linkage with site records and the claims procedure
- Site records first: employer-caused stoppage belongs to the fourth category of recordable events in the commentary to GB 50500-2013 Section 9.14 - 'where the employer fails to provide the site, materials or equipment as agreed in the contract, or cuts water or power, causing the contractor to stop work, the contractor must promptly seek record certification from the employer so that the claim costs can be calculated.'
- Time limit of the record (GB 50500-2013 Clause 9.14.2, source wording): 'the contractor shall submit the site record report to the employer within 7 days after receiving the employer's instruction, and the employer shall verify the report content within 48 hours after receiving it and either confirm it or raise comments for revision. Where the employer neither confirms nor raises revision comments within 48 hours after receiving the contractor's site record report, the report shall be deemed approved by the employer.'
- Content of the record (Clause 9.14.3): where dayworks rates exist, the record shall state the quantities of labour, materials, permanent equipment and construction plant machine-shifts needed for the work; where no dayworks rate exists, it shall also state the rates.
- Claims procedure (contractor to employer): GB 50500-2013 Clause 9.13.2 - a Notice of Claim within 28 days of knowing or being expected to know of the claim event, 'a contractor that fails to issue the Notice of Claim in time loses the right to claim'; a formal claim notice within 28 days of issue; continuing notices for continuing effect; a final claim notice within 28 days of the end of the effect. Clause 9.13.3 - the employer responds within 28 days of receipt, 'if the employer fails to respond within the time limit, the contractor's claim is deemed approved'; accepted claims are added to the contract price and paid with the current progress payment. Clause 9.13.4 remedies: extension of time, payment of additional costs actually incurred, payment of reasonable anticipated profit, liquidated damages per the contract (one or several of these). Clause 9.13.6 - after the final account is settled no claim may be raised for any event that arose before it.
- Model-contract wording (GF-2017-0201 Clauses 19.1 / 19.2): within 28 days of the Notice of Claim the contractor submits the formal claim report to the supervising engineer; for continuing effect, further notices at reasonable intervals stating the cumulative additional payment and/or days of extension; the final claim report within 28 days of the end of the effect. The supervising engineer completes its review and forwards it to the employer within 14 days of receipt; the employer issues a signed claim determination within 28 days; a response not made in time is deemed approval of the claim.
- Linkage to the current edition: GB 50500-2013 has been replaced by GB/T 50500-2024, the standard for BOQ pricing of construction works; the corresponding 2024 clauses are Clause 8.11.3 (notice within 28 days, claim report within 28 days, late response 'may be handled as agreed in the contract' - the strength of the time bar is left to the contract), Clause 8.11.9 (plant standby costs from suspension, waiting, loss of efficiency or extension of time are recoverable losses) and Clause 8.11.10 (a profit claim where the employer is liable). Contracts citing the 2013 edition follow its clauses; otherwise the current standard applies.
VII. Evidentiary requirements T/YJXB 0001-2023 Clause 6.0.3: the documents for calculating the standby cost of construction plant include 'mobilisation and demobilisation acceptance sheets of on-site plant during the suspension, hire contracts, the plant list, the project execution plan, notarial certificates, hire settlement sheets, statements, electronic records and other supporting documents'; 'during the suspension, where hired construction plant continues to attract hire, the contractor must produce corresponding evidence of the hire loss during the suspension; for contractor-owned plant, evidence of its deployment on the construction site is required.' On the supervision side (DBJ41/T 208-2018): Clause 7.1.4 requires the project supervision office to record and collect the original records of site records and cost claims together with the cause, the duration and the site conditions of the stoppage; Clause 9.2.4 requires that on suspension events the supervision diary truthfully record the numbers and state of site personnel, plant and materials, by text, charts or audio-visual means - the primary evidence for fixing 'idle plant units x days of suspension'.
Boundaries of applicability
- Applies to pricing and claims for plant standby costs arising from suspension or stand-down for reasons not attributable to the contractor (the employer in particular); stoppages caused by the contractor itself, or plant breakdown, fall outside the standby-cost scope.
- Where the contract stipulates a standby-cost calculation method, the stipulation prevails; where certified site records exist they govern, and only in their absence do the methods of the association standard T/YJXB 0001-2023 apply (the standard binds once cited in the contract, and otherwise serves as a methodological reference).
- Provincial quota stations differ on the standby machine-shift rate components (whether labour cost is included, or depreciation only, and whether fuel, power and labour are deducted); pricing and claims must follow the current machine-shift rate norms and notes at the place of the works - no cross-province borrowing.
- The Jiangsu machine-shift rate reference tables apply only to compiling rates for contractor-owned plant amortised over total durable machine-shifts; they cannot directly determine market plant hire prices.
- GB 50500-2013 is withdrawn (current: GB/T 50500-2024); the 2013 clauses carry meaning only for contracts citing that edition.
- 'Reasonable proportion' and the 'machine-shift conversion factor per day' must be fixed case by case from the contract and the certified records; 1 must not be applied mechanically.
Further reading
- T/YJXB 0001-2023 'Standard for calculation of contractor costs upon suspension of construction works': Clause 1.0.2 (scope), 5.0.3 (standby-cost methods), 5.0.8 (suspension overheads), 5.0.9 (suspension profit), 6.0.3 (documents required).
- 'Compilation rules for machine-shift rates of Shandong construction plant': Clause 6.0.1 (definition and components of the standby cost), 6.0.2 (hire charges set regionally by reference to the market).
- 'Jiangsu reference tables of machine-shift rates for construction plant and tools' (May 2026): note 8 (standby rate components), note 9 (own plant only; not for market hire prices).
- 'Hunan 2025 consumption standard appendix (plant machine-shifts)': note 9 (basis of repair and maintenance charges), note 10 (standby on depreciation; numbers per certified record; hired plant deducts power and labour).
- TB/T 10814-2024 'Railway works plant rate norms per machine-shift for construction plant and tools': Clause 1.0.4 (seven rate components, 8h shift, depreciation formula, residual value rates, maintenance inclusive of standby upkeep).
- GB/T 50500-2024, standard for BOQ pricing of construction works: Clause 8.11.3 (claims procedure and 28 days), 8.11.9 (recoverable losses including plant standby costs), 8.11.10 (profit where the employer is liable).
- GB 50500-2013, code for BOQ pricing of construction works: Clauses 9.13.2-9.13.6 (claims procedure, remedies, time limits), Section 9.14 with Clauses 9.14.2 and 9.14.3 (recordable events, the 7-day / 48-hour limits, stating machine-shift quantities and rates).
- GF-2017-0201 model construction contract: Clause 19.1 (Notice of Claim and claim report), 19.2 (engineer's 14-day review, employer's 28-day response), 19.5 (time limit for claims).
- DBJ41/T 208-2018 'Standard for construction supervision work': Clause 7.1.4 (recording and collecting cost-control documents), 9.2.4 (supervision diary records of personnel, plant and material numbers and state on suspension).
Keywords
- 机械停滞费
- 停滞台班费
- 停滞台班单价
- 停滞台班数
- 施工机具停滞费
- 自有机械与租赁机械
- T/YJXB 0001-2023
- 现场签证与索赔程序