Pricing-form determination and machine-shift rate value for site-owned diesel generator sets: own units by machine-shift (TB/T 10814-2024 power machinery items 9101243/9101253 plus Appendix A base data), leased units by certified rent, standby non-running units by idle cost (depreciation plus labour plus others), and the boundary against permanent-equipment procurement and installation (TB/T 10833-2024 JY-260 to JY-267)

One generator set takes exactly one pricing channel: (1) own units enter the plant and small tools cost as quota machine-shift consumption x machine-shift rate (TB 10801-2024 clause 3.3.2; the rate set under TB/T 10814-2024, its seven components in clause 1.0.4); (2) leased units are certified on actual rent with the lease contract and rental settlement - 'use of leased construction machinery requires agreement between Employer and Contractor' - and idle cost for leased units also follows the actual rental; (3) emergency standby units that never run take no operating machine-shift, only idle cost = depreciation plus labour plus other charges (no overhaul, maintenance or power). Railway diesel generator sets are graded in TB/T 10814-2024 chapter 2 section 2 (power machinery) by capacity with computer codes (300 kW = 9101243, 500 kW = 9101253; fifteen grades from 120 to 1000 kW); depreciation, overhaul, maintenance and erection/dismantling derive from the Appendix A budget prices, residual value rates, total durable machine-shifts and three coefficients; as permanent equipment the set runs equipment procurement plus installation cost (TB/T 10833-2024 volume 12, JY-260 to JY-267), mutually exclusive with the construction-machinery machine-shift rate.

Applicable Codes

  • TB/T 10814-2024 · Quota for Shift Costs of Construction Machinery and Tools of Railway Engineering Ch. 1总则 1.0.3~1.0.5、Ch. 2第二节动力机械(9101231~9101271)、App. A 施工机械基础数据表
  • TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.3节 施工机具使用费(3.3.1~3.3.6)
  • TB 10833-2024《铁路工程预算定额 第十二册 机务车辆机械工程》第一章第七节 柴油发电机组 JY-260~JY-267
  • TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works
  • TB/T 10813-2024 · Base Period Prices of Materials for Railway Engineering
  • JTG/T 3833-2018 · Quota for Shift Costs of Highway Engineering Machinery 九、动力机械(柴油发电机组)
  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.2条
  • T/YJXB 0001-2023《建设工程停工承包人费用计算标准》第5.0.3条
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.9、8.11.10条
  • 湖北省建筑安装工程费用定额(2024);江苏省建设工程施工机具台班费用参考表(2026版)说明第五~十四条;山东省机械台班费用编制规则

Subject positioning

How site-owned diesel generator sets (300 kW, 500 kW and other capacity grades) are priced: fix the pricing form first (own by machine-shift / leased by rent / standby by idle cost), take the fee from the corresponding item of the sector machine-shift rate norms, and draw the boundary against permanent-equipment procurement and installation, mobilisation, generator foundations and fuel tanks.

Core conclusions

1. Three mutually exclusive pricing forms; judgement order: ownership and exit -> actual running -> contract terms

Pricing form Conditions Channel and measurement Basis Common errors
1. Own machinery (machine-shift into plant cost) Company-owned asset; listed in the project execution plan / site set-up; runs with the works quota machine-shift consumption x machine-shift rate -> plant and small tools cost -> into the all-in rate TB 10801-2024 clause 3.3.2 (plant and small tools cost = sum of quota machine-shift consumption x machine-shift rate); clause 3.3.6: the rate set under the machine-shift rate norms charging the machine-shift plant cost and then charging the power output again per kWh
2. Leased generator (rent certified) Not owned; lease contract and settlement exist actual rent (per machine-shift or per month), measured on the rental settlement plus site certification Hubei 2024 fee schedule: leased large machinery priced per the general notes - 'use of leased construction machinery requires agreement between Employer and Contractor'; T/YJXB 0001-2023 clause 5.0.3: 'leased plant on actual rental cost; own plant on the machine-shift norms for idle cost' re-applying the machine-shift rate or re-charging mobilisation when the rent already covers them
3. Emergency standby, not running (no operating machine-shift) On site on stand-by but not generating, or pure standby assurance no operating machine-shift; idle machine-shift cost = depreciation + other charges + labour (no overhaul, maintenance or power); leased units on actual rent Jiangsu machine-shift reference table note 8: 'idle machine-shift cost comprises depreciation, other charges and labour, labour on the count of operators idled by the standstill'; GB/T 50500-2024 clauses 8.11.9-8.11.10 list idle cost of plant on site unable to work as claimable loss charging full machine-shifts for standby as if running; double-claiming a standby duty already covered lump-sum in the contract

Occurred / not-occurred tests (worth writing into the record wording): (1) listed in the project execution plan and accepted on mobilisation (mobilisation acceptance sheet); (2) actually generating (running records, output, machine-shift sign-off); (3) on site but not running - idle cost or actual rent; (4) where the contract lists standby power as a contractor assurance duty (continuous pours, tunnel ventilation, fire standby), it is covered lump-sum and no separate machine-shift is taken; (5) not mobilised and not in the plan - 'for tenderers' own consideration' - is not payable.

2. The seven components of the machine-shift rate (original wording)

TB/T 10814-2024 clause 1.0.4: 'the construction machinery machine-shift rate is the full cost of one machine in normal operation over one work shift (8 h). It comprises seven charges: depreciation, overhaul, maintenance, erection and dismantling, labour, power and other charges.'

  1. Depreciation = budget price x (1 - residual value rate) / total durable machine-shifts; residual rates '4% for machinery up to 1,000,000 yuan inclusive, 3% above, 2% for transport machinery, 5% for tunnelling machinery', all in Appendix A.
  2. Overhaul (the traditional overhaul / major-repair item - never listed twice) = budget price x overhaul coefficient / total durable machine-shifts.
  3. Maintenance = overhaul x maintenance coefficient (the coefficient being all maintenance cost as a share of all overhaul cost, Appendix A).
  4. Erection and dismantling = budget price x erection/dismantling coefficient / total durable machine-shifts; three classes: not listed for machines needing no erection or self-moving or fixed; simple erection needing cranes or transporters included in this volume's rates; complex erection not included here, charged separately.
  5. Labour = headcount x all-in labour rate (operators carried here, not in the works quotas).
  6. Power = sum of fuel, water and power consumption x unit prices.
  7. Other charges = annual vehicle and vessel tax + compulsory insurance + vehicle inspection + special-equipment periodic examination, divided by (250 annual working days x annual utilisation). Clause 1.0.3 base period: 2020 price level excluding deductible input VAT; labour 149.18 yuan/workday, water 0.55 yuan/t, power 0.47 yuan/kWh, petrol 6.55 yuan/kg, diesel 5.67 yuan/kg, gas 1.95 yuan/m3. Instruments and meters carry only four components: depreciation, maintenance, verification and power (clause 1.0.5).

3. Capacity grades and value items for diesel generator sets

TB/T 10814-2024 chapter 2 (general construction machinery), section 2 (power machinery) lists 15 diesel generator grades: up to 120, 160, 200, 250, 300, 350, 370, 400, 450, 500, 560, 600, 700, 800 and 1000 kW; Appendix A gives budget prices, residual rates, power, total durable machine-shifts (2700) and the overhaul, maintenance and erection/dismantling coefficients. Key grades (yuan per machine-shift, excluding labour, power and other charges):

Code Specification Budget price (yuan) Residual (%) Overhaul coef. Maint. coef. Erect/dism. coef. Depreciation Overhaul Maintenance Erection
9101231 up to 120 kW 73100 4 0.3811 3.43 0.8208 25.99 10.32 35.39 22.22
9101235 up to 200 kW 141800 4 0.3812 2.47 0.5289 50.42 20.02 49.45 27.78
9101243 up to 300 kW 227800 4 0.3812 2.33 0.3951 81.00 32.16 74.94 33.33
9101253 up to 500 kW 352400 4 0.3812 2.29 0.3405 125.30 49.75 113.94 44.44
9101257 up to 600 kW 541500 4 0.3812 2.23 0.3324 192.53 76.45 170.49 66.66
9101265 up to 800 kW 764900 4 0.3812 2.20 0.3138 271.96 107.99 237.58 88.90
9101271 up to 1000 kW 1010000 3 0.3812 2.21 0.3120 362.85 142.60 315.14 116.71

'Up to' grades include the stated value; the 1000 kW grade takes 3% residual because its budget price exceeds 1,000,000 yuan. Check by recomputation (300 kW): depreciation = 227800 x (1 - 0.04) / 2700 = 80.996, about 81.00; overhaul = 227800 x 0.3812 / 2700 = 32.162, about 32.16; maintenance = 32.16 x 2.33 = 74.93 (the norm takes 74.94, a rounding difference); erection = 227800 x 0.3951 / 2700 = 33.34, about 33.33. The four fixed charges total 221.43 yuan per machine-shift. 500 kW: depreciation 125.30, overhaul 49.75, maintenance 113.93 (norm 113.94), erection 44.44, total 333.43 yuan. The full machine-shift rate = these fixed charges + labour + power (diesel consumption x the 5.67 yuan/kg base-period price) + other charges.

4. Companion costs and the permanent-equipment boundary

  1. Mobilisation and erection: per the three classes of clause 1.0.4(4) - not listed, spread into the rate by coefficient, or listed separately (large machinery mobilisation as separate items per movement). Generator foundations, fuel tanks and their bases, temporary distribution boxes and cables, plant rooms and noise control are not among the seven components - charge them under preliminaries or the corresponding work items. Where the rent already covers mobilisation, erection and attendance, neither the machine-shift rate nor mobilisation may be charged again.
  2. As permanent equipment (tunnel or station fixed power plants): runs equipment procurement plus installation cost - railway installation quota TB/T 10833-2024 Volume 12 Locomotive and Rolling Stock Machinery Works, chapter 1 general equipment installation, section 7 diesel generator sets, JY-260 to JY-267 for up to 30, 50, 80, 120, 200, 300, 400 and 500 kW, work content 'unpacking and inspection, external cleaning, setting anchor bolts and shims, installing, aligning, levelling, fixing, grouting, finishing and curing, installing the diesel engine, controls and accessories, commissioning'. No construction-machinery machine-shift applies; conversely, temporary site generators must not borrow this installation quota as plant cost.
  3. Sector bases never mix: highway works convert self-generated power into an electricity price (JTG 3830-2018 clause 3.1.2: A the price per kWh, K the set's machine-shift rate, N total power) - a material/power channel, distinct from machine-shift plant cost, and the two must not double; the highway machine-shift norms (JTG/T 3833-2018, section 9 power machinery, e.g. code 8017010) and the local reference tables (Jiangsu, Shandong) each have their own grades and base-period labour - one generator must never take rates across sectors or regions.

Applicability boundaries

  • The data are the railway TB/T 10814-2024 base-period level (2020 prices, excluding deductible input VAT); the gap to the working-date level is carried as the plant price differential under TB 10801-2024 clause 3.3.3 - never use base-period rates as current prices.
  • The norm rates assume normal operation and depreciation over total durable machine-shifts for own machinery and do not set market rental prices (the local reference tables state they apply to own machinery, not to market rents); rents follow contract and market.
  • Idle cost applies only to stand-by non-running units; units that generated take operating machine-shifts and no idle cost. Where standby power is a contractor lump-sum duty, no separate charge.
  • 'Overhaul' is the current name of the traditional major-repair item - never listed twice; maintenance and erection are already inside the rate - listing them again is double counting.
  • Sector and regional systems are mutually exclusive: railway estimates use railway quotas, highway uses highway quotas, local building works use local tables; 'up to' grades include the value; where a model does not match a grade, consumption must not be changed - take the nearest grade or convert as prescribed.

Further reading

  • TB/T 10814-2024 Machine-Shift Rate Norms for Railway Works Construction Machinery and Instruments: chapter 1, 1.0.3 to 1.0.5 (base-period prices; rate components and formulas); chapter 2 section 2 power machinery (diesel generator codes 9101231 to 9101271); Appendix A base data (budget prices, residual rates, power, total durable machine-shifts, coefficients); Appendices B and C.
  • TB 10801-2024 Compilation Rules for Railway Capital Construction Design Estimates and Budgets, section 3.3 (3.3.1 to 3.3.6).
  • TB/T 10833-2024 Railway Works Budget Quota, Volume 12 Locomotive and Rolling Stock Machinery Works, chapter 1 section 7 (JY-260 to JY-267).
  • TB 10811-2024 railway fee norms; TB/T 10813-2024 base-period material prices (labour, water, power and fuel base prices).
  • JTG/T 3833-2018 Highway Machinery Machine-Shift Rate Norms, section 9; JTG 3830-2018 clause 3.1.2 (self-generation price formula).
  • Local and association rules: Jiangsu reference table (notes 5 to 14: idle cost, rents not covered, instruments' four components); Shandong compilation rules (maintenance = overhaul x K; three classes of erection and off-site haulage); Hubei 2024 fee schedule (leased machinery; market prices into all-in rates); T/YJXB 0001-2023 clause 5.0.3; GB/T 50500-2024 clauses 8.11.9 and 8.11.10 (idle-cost claims).