Determining plant and small tools cost within the all-in unit rate: consumption × plant rate per machine-shift, 7-item/4-item composition of the plant rate per machine-shift, and adjustment for price differentials
Plant and small tools cost = construction machinery usage cost + construction instrument and meter usage cost, both determined as machine-shift consumption under quota norms (prescribed resource consumption standards) × plant rate per machine-shift (GB/T 51095-2015 Clause 5.3.9; TB 10801-2024 Section 3.3). The plant rate per machine-shift for construction machinery has 7 items = depreciation + overhaul + maintenance + assembly and disassembly + labour + power + other costs; the plant rate per machine-shift for instrument and meter has 4 items = depreciation + maintenance + verification + power; both are computed on an 8-hour working shift. Where machine-shift cost quota norms exist, take the price per the quota norms (railway TB/T 10814-2024, base-period price excluding deductible input value added tax (VAT)); the difference between base period and compilation period is listed as an adjustment for price differentials of plant and small tools cost. When fuel and power prices fluctuate beyond the agreed risk band (no-adjustment tolerance, e.g. ±5%; where not agreed, 5%), price adjustment (for fluctuation) applies; the price difference carries VAT only, with no management fee or profit (GB/T 50500-2024 Clauses 8.7.2, 3.3.5).
Applicable Codes
- TB/T 10814-2024 · Quota for Shift Costs of Construction Machinery and Tools of Railway Engineering 第1.0.1~1.0.6条及App. A/B/C
- TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.3节、第4.1.2条
- TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.3节
- TB/T 10813-2024 · Base Period Prices of Materials for Railway Engineering
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.9、3.3.5、8.7.2、8.7.6条
- GB/T 51095-2015 · Code for construction cost consultation 第5.3.9条
- 《山东省建设工程施工机械台班费用编制规则》4.0~4.7、5.0
- 湖北省建筑安装工程费用定额(2024)施工机具使用费条
- 江苏省建设工程施工机具台班费用参考表
Topic Positioning
How plant and small tools cost within the all-in unit rate is determined: calculation formulas, composition of the plant rate per machine-shift, price-taking sources, and adjustment for price differentials, covering both the building BOQ-based pricing and railway estimates and budgets (China Railway system) calibers.
Core Conclusions
Plant and small tools cost = construction machinery usage cost + construction instrument and meter usage cost, both determined as consumption × unit price: machinery usage cost = Σ (machine-shift consumption under quota norms (prescribed resource consumption standards) × plant rate per machine-shift) (GB/T 51095-2015 Clause 5.3.9; TB 10801-2024 Clause 3.3.2). Two calibers of plant rate per machine-shift: (1) the construction machinery rate per machine-shift has 7 items = depreciation + overhaul + maintenance + assembly and disassembly + labour + power + other costs; (2) the construction instrument and meter rate per machine-shift has 4 items = depreciation + maintenance + verification + power; both are computed on an 8-hour working shift (TB 10801-2024 Clauses 3.3.4–3.3.5). Machine-operator labour cost covers only dedicated operators not itemized in the work quota norms; where already included in the quota norms, it is not counted again. Price taking: where machine-shift cost quota norms exist, follow them (railway TB/T 10814-2024, 2020 price level, excluding deductible input value added tax (VAT)); for machinery lacking quota norm items, compile supplementary machine-shift cost quota norms (TB 10811-2024 Clause 2.3.1); the base-period and compilation-period plant rates per machine-shift are computed respectively with the labour, fuel, and water/electricity prices of the corresponding periods, and the difference is listed as an adjustment for price differentials of plant and small tools cost (Clause 2.3.2). Price adjustment (for fluctuation): for labour, material, and fuel/power items the contract allows to adjust, when fluctuation exceeds the agreed risk band (no-adjustment tolerance, e.g. ±5%; where not agreed, 5%), adjust by index-based (formula) adjustment or adjustment based on published price information; the price difference carries VAT only, with no management fee or profit (GB/T 50500-2024 Clauses 8.7.2, 3.3.5).
Applicable Boundaries
Applies to BOQ-based pricing rate build-up and railway estimates and budgets (China Railway system) compilation; neither caliber includes VAT; the railway plant rate per machine-shift excludes deductible input VAT, and compilation-period prices are determined by the design organization through survey and analysis. Rented machinery may be priced by rental fee. Fuel and power price adjustment (for fluctuation) is limited to items the contract allows to adjust; no adjustment if the agreed risk band (no-adjustment tolerance, e.g. ±5%) is not exceeded.
Further Reading
GB/T 50500-2024 Clause 2.0.9 (all-in unit rate definition), Clause 3.3.5 (price difference carries VAT only), Clause 8.7.2 (adjustment beyond 5%); GB/T 51095-2015 Clause 5.3.9; railway TB 10801-2024 Section 3.3, TB 10811-2024 Section 2.3, TB/T 10814-2024 Clause 1.0.4.