Deciding when large plant mobilisation and erection charges are priced separately, and the cost make-up (with quota item codes, trip counts and haul-distance rules)
Large-plant mobilisation and erection charges follow a three-type test: plant needing no erection, self-moving or fixed in position is uncounted; light plant with simple erection but needing cranes and transport to move is spread into the machine-shift rate (erection charge = budget price x erection coefficient / total durable machine-shifts); heavy plant with complex erection and crane / transport moves (tower cranes, builder's hoists, shields) is itemised per machine per trip and computed separately. The same sum must not be counted both in the machine-shift rate and as preliminaries; tower crane and builder's hoist bases and ground improvement are charged separately. Codes: building 011601, structures 070304, landscape 050404, urban rail per GB/T 50861-2024 Appendix M M.2.4.
Applicable Codes
- GB/T 50500-2024 App. E Table E.3.4
- GB/T 50854-2024 App. R Table R.1.1(code 011601)
- GB 50860-2013 App. C Table C.4(code 070304)
- GB/T 50858-2024 App. D Table D.4.1(code 050404)
- GB/T 50861-2024 App. M M.2.4
- TB/T 10814-2024 第1.0.4条
- 山东省建设工程施工机械台班费用编制规则 4.4
- 江苏省建设工程施工机具台班费用参考表(2026版)
- 湖南省2025消耗量标准附录
- 陕西省新编消耗量定额 八、大型机械设备进出场及安拆
Scope of the question
The two pricing routes of large-plant mobilisation and erection charges and the rule separate pricing versus included-in-machine-shift, with the cost make-up, typical plant classes, trip counts, haul distances and BOQ / quota codes. For pricing preliminaries, compiling machine-shift costs and settlement review.
Core conclusions
1. Two routes (never mixed)
- Machine-shift route: the machine-shift rate = depreciation + overhaul + maintenance + erection and dismantling + labour + power + other (7 items), per 8-hour shift, per TB/T 10814-2024 Railway Plant Machine-Shift Cost Norms, Article 1.0.4.
- BOQ / preliminaries route: the make-up of large-plant mobilisation and erection charges follows GB/T 50500-2024 Table E.3.4 - note 1: where the same plant's mobilisation prices differ, itemise separately; note 2: manufacturer special requirements may be noted.
2. Make-up (five parts)
- Erection / dismantling: labour, materials, plant and trial runs for one erection and dismantling on site (one-off, excluding ground improvement).
- Transport (off-site haul / mobilisation): transport, loading and unloading, auxiliary materials and return legs from the car park to site or between sites.
- Auxiliary installations: depreciation, erection and removal of the plant's auxiliary installations (TB/T 10814-2024 Article 1.0.4 item 4).
- Bases, pedestals, anchor blocks, travel tracks, sleepers, road boxes: their depreciation, erection and removal enter the erection charge (including road boxes reinforcing travel routes of large crawler and truck-mounted cranes).
- Fixed-device erection: a cost constituent parallel to plant erection and plant haulage in the BOQ basis (GB/T 50500-2024 Table E.3.4; building works GB/T 50854-2024 Table R.1.1 item 011601 work content).
Bases itemised separately: erection is one-off per erection and dismantling, excluding tower crane and builder's hoist bases and ground improvement - fixed bases follow the works consumption standard items (concrete, formwork, rebar), removal charged separately. Base scope per local rules: Shandong - fixed bases up to 10 m3 of concrete; Shaanxi - up to 60 m3, beyond per actual concrete, formwork and rebar under Chapter 5. Tower crane bases and track erection: tracks taken straight, curved multiplied by 1.15; piling excluded, charged separately.
3. The separate-pricing test (three types)
- Not counted: plant needing no erection, self-moving or positionally fixed - no erection charge or off-site haul; self-propelled plant not needing erection and able to drive (except crawler types) - scrapers, graders, tyred loaders, horizontal transport - attracts no transfer cost between unit works or blocks on site.
- Into the machine-shift rate: light plant, simple to erect but needing cranes and transport to move - its erection and haul enter the rate; erection charge = budget price x erection coefficient / total durable machine-shifts.
- Computed separately: heavy plant, complex to erect and needing cranes and transport - erection and haul itemised; plant moved on auxiliary installations - depreciation, erection and removal of those installations (tracks, sleepers) computed separately. Formula: erection + off-site haul = (one-off erection and haul x average annual erection count) / annual working machine-shifts; one-off erection covers labour, materials, plant, statutory inspection fees and trial runs for one erection and dismantling; one-off haul covers transport, loading, auxiliary materials and the return leg.
Typical classes (urban rail): 1 non-self-propelled or hard to move - bored piling rigs for retaining structures and substructure, non-crawler diaphragm-wall cutters, gantry cranes, tower cranes, bridging machines, track-laying machines; 2 self-propelled but barred from city roads - crawler dozers, excavators, loaders, scrapers, cranes, rollers, crawler cutters; 3 shield entry / exit transport - loading the shield, its frames and appurtenances, off-site haul and partial member handling; shield (TBM) site lifting and unwinding itemised per GB/T 50861-2024 Appendix C. Tower cranes, builder's hoists: machine-shift costs per machine-day, covering routine maintenance, wall-tie and use charges, with operators, power and sundry materials in the standard; third-party testing after erection charged separately; self-climbing crane erection follows tower height (below). Hired plant: the machine-shift make-up already covers both owned and hired modes; compute per the make-up and notes save as otherwise agreed; where hire includes mobilisation / erection, avoid double counting.
4. Trip counts and haul distances
- Base haul: off-site haul per the quota base distance - Shandong within 30 km; Hunan within 25 km. Tolls for roads, bridges and tunnels charged separately per transport rules; escort and over-limit costs charged separately.
- Trips: one mobilisation (and return) plus one erection and dismantling per work location; transfers between unit works or blocks needing dismantling - erection per actual count, transfer haul at 75% of off-site haul; self-propelled heavy plant without dismantling attracts no transfer cost.
- Return legs: Shandong includes the return; Shaanxi includes one round trip with the return at 25% of the single-leg freight, and includes booms, buckets, attachments, sleepers and rails.
- Height: self-climbing crane erection follows tower height - Shandong set at 45 m, +10% per extra 10 m of tower height (eaves within 300 m), remainders rounding up to 10 m; Shaanxi at 45 m, eaves up to 200 m, same stepping.
- Self-propelled extra-large plant not listed (truck-mounted drilling rigs, tyred loaders, self-propelled scrapers, truck-mounted cranes): mobilisation at 0.5 machine-shifts of the plant itself.
- Unlisted items: some extra-large plant's one-off mobilisation and erection may be certified by both parties at actual cost.
5.Codes by discipline
- Building and decoration: GB/T 50854-2024 Appendix R Table R.1.1 (011601);
- Structures: GB 50860-2013 Appendix C Table C.4 (070304);
- Landscape: GB/T 50858-2024 Appendix D Table D.4.1 (050404);
- Urban rail: GB/T 50861-2024 Appendix M M.2.4;
- Summary: GB/T 50500-2024 Appendix E Table E.3.4.
Applicability limits
- One route only per sum: counted in the machine-shift rate, not re-listed as preliminaries; itemised, not spread into the rate.
- Base haul distances, base-volume limits, height coefficients and return-leg ratios differ by province (Shandong 30 km / 10 m3; Hunan 25 km / 0.5 shifts; Shaanxi 25% return / 60 m3) - follow the current local pricing basis and machine-shift norms; no cross-region borrowing.
- Machine-shift cost items exclude deductible input VAT; sundry works machine-shift costs follow certifications, not this make-up.
- This card is a general pricing rule without specific rates or project data; item numbers follow the current local basis.
Further reading
- GB/T 50500-2024 Appendix E Table E.3.4; GB/T 50854-2024 Appendix R Table R.1.1 (011601); GB 50860-2013 Appendix C Table C.4 (070304); GB/T 50858-2024 Appendix D Table D.4.1 (050404); GB/T 50861-2024 Appendix M M.2.4.
- TB/T 10814-2024 Railway Plant Machine-Shift Cost Norms, Article 1.0.4 (7-item rate make-up, three erection treatments, residual rates).
- Provincial rules: Shandong machine-shift cost compilation rules 4.4.1-4.4.3 and Appendix C (separately computed charges, tower crane bases, 45 m / 30 km rules); Jiangsu machine-shift reference tables (2026) notes (mobilisation defined, once per location, 75% on-site transfer, tower crane haul and erection consumptions); Hunan 2025 appendix (25 km base, 0.5-shift conversion, fixed bases separate, 50 m tower coefficient); Shaanxi new quota section 8 large-plant mobilisation and erection (round trip with 25% return, 60 m3 bases, 45 m / 200 m height).
Keywords
- 大型机械设备进出场及安拆
- 进出场费
- 安拆费
- 单独计算
- 场外运费
- preliminary items
- plant rate per machine-shift
- 定额子目编码