Railway 2024 quota norms: erection/dismantling and commissioning of large plant (special line items GY-1~GY-5) versus plant rate per machine-shift and plant entry/exit cost — boundary rules: erection/commissioning must be booked separately, entry/exit must not, and the three never overlap
Under the railway 2024 quota norms (TB/T 10825-2024, TB/T 10814-2024, TB 10801-2024, effective 2025-01-01), for large plant such as track-laying machines and rail-welding trains: (1) erection/dismantling and commissioning must be booked separately via the special line items GY-1~GY-5 of "Section 1: erection/dismantling and commissioning of large plant", Chapter 1 of the track works quota manual, measured per "occurrence", listed independently (composite preliminary estimate/budget chapter table, Chapter 1 track laying, (9)); (2) plant entry/exit cost is not booked separately — contractor entry/exit and site-transfer costs are already inside the on-costs (indirect costs) item of overheads (company and site) (base (base-period labour cost + base-period plant and small tools cost) x on-cost percentage rate), and must not appear as a separate line; (3) no overlap with plant rates per machine-shift — decision rule: where the erection/dismantling column of the shift-cost norms (TB/T 10814-2024) reads "book separately" or "—" (long-rail flash-butt welding line 9114095 "book separately"; welding trains 9114091/9114092 etc. "—"), the cost is landed via the GY line items, booked separately without duplication; where the column carries a specific amount (e.g., long-rail flat wagon 9114081, 5.21 yuan/machine-shift), it is already amortized in the plant rate per machine-shift and the GY line items must not be applied. For the single-sleeper-method track-laying machine, erection/dismantling and commissioning is compiled on a combined basis of 60% major dismantling and 40% minor dismantling of the machine set, with no adjustment for the actual dismantling mode when the line item is applied.
Applicable Codes
- TB/T 10825-2024 铁路工程预算定额 Vol. 4 轨道工程 Ch. 1第一节 大型机械安拆与调试(GY-1~GY-5)
- TB/T 10814-2024 铁路工程施工机具台班费用定额 Ch. 3第三节 轨道工程机械
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.3.4条
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额(间接费费率)
Topic Positioning
This card addresses the cost boundaries and booking rules among "erection/dismantling and commissioning cost", "plant entry/exit cost", and "plant rate per machine-shift" for large plant such as track-laying machines and rail-welding trains under the railway 2024 quota norms (TB/T 10825-2024 "Railway works budget quota manual, Volume 4: track works", TB/T 10814-2024 "Railway construction plant shift-cost norms", TB 10801-2024 "Measures for compiling design preliminary estimates (budgets) of railway capital construction projects"), answering three questions: must erection/commissioning be booked separately, must entry/exit be booked separately, and is there overlap with the plant rate per machine-shift.
Core Conclusions
- Erection/dismantling and commissioning: must be booked separately via the Chapter 1 special line items. TB/T 10825-2024 Chapter 1 Section 1 "erection/dismantling and commissioning of large plant" provides 5 special line items, with work content "erect, commission, (trial run), dismantle after completion", measured per "occurrence" (the number of occurrences is determined by the project execution plan (construction methodology and site organization) — normally once per track-laying base / per contract section), listed independently under "(9) erection/dismantling and commissioning of large plant" of Chapter 1 track laying in the composite preliminary estimate (budget) chapter table, not merged into the track-km line items:
- GY-1 long-rail flash-butt welding line erection/dismantling and commissioning, base price 115,413.61 yuan/occurrence (labour cost 65,401.28, material cost 27,734.35, plant cost 22,277.98);
- GY-2 single-sleeper-method long-rail track-laying machine erection/dismantling and commissioning, 81,018.39 yuan/occurrence;
- GY-3 ballastless-track laying machine erection/dismantling and commissioning, 13,881.91 yuan/occurrence;
- GY-4 rail-panel track-laying machine erection/dismantling and commissioning, 103,817.85 yuan/occurrence;
- GY-5 rail-panel assembling machine erection/dismantling and commissioning, 29,310.37 yuan/occurrence. Volume note 4: the single-sleeper-method track-laying machine erection/dismantling and commissioning quota is compiled on a combined basis of 60% major dismantling of the machine set (separating the main and auxiliary machine bodies from bogies, brake links, mechanical connections, etc.) and 40% minor dismantling, with no adjustment for the actual dismantling mode when the line item is applied.
No overlap with the plant rate per machine-shift: per TB 10801-2024 Clause 3.3.4, the plant rate per machine-shift comprises seven components — depreciation, overhaul, maintenance, erection and dismantling, labour, power, and other costs. Check Chapter 3 Section 3 track works plant of TB/T 10814-2024 (9114 series): the erection/dismantling column for the long-rail flash-butt welding line (9114095) is marked "book separately" — the plant rate per machine-shift excludes this cost, and it is landed precisely by GY-1; the fixed rail-welding train (9114092), mobile rail-welding train-set (9114091), long-rail thermit-welding set (9114093), and long-rail gas-pressure-welding set (9114094) show "—" in the erection/dismantling column — likewise not amortized into the plant rate per machine-shift. Counter-example: the long-rail flat wagon (9114081) erection/dismantling 5.21 yuan/machine-shift — already amortized in the plant rate per machine-shift, and Chapter 1 of the track works quota manual has no corresponding erection/dismantling line item — the two correspond one-to-one. Decision rule: where the erection/dismantling column of the shift-cost norms reads "book separately" or "—" -> book the GY erection/dismantling and commissioning line item separately, no duplication; where the column carries a specific amount -> the cost is already included in the plant rate per machine-shift, and the erection/dismantling line item must not be applied.
Plant entry/exit cost: not booked separately. The railway preliminary estimate (budget) system has no stand-alone account for "large plant and machinery entry/exit and erection/dismantling cost" as in building BOQ-based pricing (GB/T 50500 series); contractor entry/exit and site-transfer costs are an item of overheads (company and site) within the on-costs (indirect costs) (including the carriage of construction plant, small tools, appliances, recyclable materials, and other construction equipment), booked as a package via on-costs = (base-period labour cost + base-period plant and small tools cost) x on-cost percentage rate (the percentage rate is selected by works class per TB 10811), and must not appear as a separate line — the inbound relocation of track-laying machines and rail-welding trains falls here. The only exception is the entry/exit and site transfer of special plant such as shield machines and TBM boring machines, which goes to special quota line items. Also distinguish: the construction of the track-laying base or rail-welding base site itself is a heavy temporary works cost (temporary yards) — a separate line that does not overlap with entry/exit cost or erection/dismantling cost.
Applicable Boundaries
- Applies only to the railway 2024 quota norms (effective 1 January 2025, replacing TZJ 1001-2017 and other older versions); the calibres of the old system do not carry over.
- GY line items are measured per "occurrence"; the number of occurrences has no uniform quota standard — it is determined by the project execution plan (construction methodology and site organization).
- For plant whose erection/dismantling column in the shift-cost norms already carries a specific amount (e.g., long-rail flat wagon 5.21 yuan/machine-shift), applying a GY line item as well is strictly prohibited, as that would be double charging.
- The erection/dismantling and commissioning quota covers only on-site erection, commissioning, trial run, and dismantling — it does not cover the cost of establishing a rail-welding base (the yard long-rail welding quota likewise excludes base establishment cost).
- These rules do not apply to the building/municipal BOQ-based pricing system (GB/T 50500 series, which lists entry/exit and erection/dismantling cost as a separate account).
Further Reading
- TB/T 10825-2024 "Railway works budget quota manual, Volume 4: track works", Chapter 1 track laying, Section 1 erection/dismantling and commissioning of large plant (GY-1~GY-5) and volume notes (in particular: note 4 on the single-sleeper-method track-laying machine 60% major / 40% minor dismantling calibre; notes 1 to 3 on rail-material pairing and closure-gap rail sawing and drilling booked separately; note 13 on the yard welding of long rails in 100 m fixed lengths).
- TB/T 10814-2024 "Railway construction plant shift-cost norms", Chapter 3 Section 3 track works plant (computer codes 9114 series — in particular check the three markings of the erection/dismantling column: "book separately" / "—" / amount).
- TB 10801-2024 "Measures for compiling design preliminary estimates (budgets) of railway capital construction projects", Section 3.3 plant and small tools cost (Clause 3.3.4 seven components of the plant rate per machine-shift; Clause 3.3.6 plant rates per machine-shift determined per TB 10811), Appendix A composite preliminary estimate (budget) chapter table "(9) erection/dismantling and commissioning of large plant".
- For the detailed calibre on plant entry/exit cost (mobilization of construction plant) being merged into on-costs, see the knowledge card "Booking construction plant mobilization in railway 2024 preliminary estimates"; for the general (non-railway) classification rules on erection/dismantling cost and entry/exit cost, see the knowledge card "Calculation rules for plant standby cost, entry/exit cost, and erection/dismantling cost" — the two systems can be compared.
Keywords
- 大型机械安拆与调试
- 铺轨机
- 焊轨机组
- GY-1
- GY-5
- plant rate per machine-shift
- 安装拆卸费
- 另计
- 机械进出场费
- 轨道工程定额
- TB/T 10825
- TB/T 10814