Booking construction plant mobilization in railway 2024 preliminary estimates: merged into on-costs (indirect costs) within overheads (company and site) (contractor entry/exit and site-transfer costs), no overlap with plant entry/exit cost or heavy temporary works
The TB 10801-2024 preliminary estimate (budget) system has no stand-alone 'construction plant mobilization' account: the account is 'contractor entry/exit and site-transfer costs', item 9 of overheads (company and site) within on-costs (indirect costs) (Clause 3.9.2), booked in package via on-costs = (base-period labour cost + base-period plant and small tools cost) x on-costs percentage rate (percentage rate selected by works class per TB 10811), with no separate line. The three channels — plant entry/exit cost (ordinary plant erection/removal already inside plant rates per machine-shift; large special plant per 'book separately' quota line items), heavy temporary works cost (construction and removal of facilities) — are distinct and non-overlapping; the entry/exit and site-transfer costs of special plant such as shield machines and TBMs are expressly outside overheads (company and site) and go to special quota line items (e.g., TB/T 10824-2024 shield-machine frame lifting and commissioning SY-419~422).
Applicable Codes
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法(第 2.6、3.3、3.8、3.9 节)
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额(间接费费率Table 2.9.1、大临Table 2.8.2~2.8.4)
- TB/T 10814-2024 铁路工程施工机具台班费用定额(Ch. 3专用施工机械)
- TB/T 10824-2024 铁路工程预算定额 Vol. 3 隧道工程(Ch. 3盾构法隧道 SY-419~422)
Topic Positioning
How 'construction plant mobilization' is booked in the railway 2024 preliminary estimate (budget) system (TB 10801-2024 + TB 10811-2024): renamed 'contractor entry/exit and site-transfer costs' and merged into on-costs (indirect costs), within overheads (company and site), at package percentage rates, and how the boundaries among it, plant entry/exit cost, and heavy temporary works cost are drawn to prevent double counting.
Core Conclusions
1. Account attribution: no stand-alone 'construction plant mobilization'. Neither the cost-composition diagram (Fig. 2.6.1) nor the composite preliminary estimate (budget) chapter table of TB 10801-2024 carries such an account. The 2024 account is 'contractor entry/exit and site-transfer costs', item 9 of overheads (company and site) within on-costs (indirect costs) (Clause 3.9.2 item 9): 'the costs of the contractor's round-trip relocation of personnel, plant, and equipment from base to the works location, or from one project to another, as required by the construction task, and the costs of round-trip transfers of the construction crew within one project as the works progress, and of workers travelling to and from site. Includes: dispatch travel expenses of assigned staff, wages during dispatch, carriage of construction plant, tools, appliances, recyclable materials, and other construction equipment; and during crew transfers, staff wages, travel, transport, and transfer allowances; and the boat/bus fares, en-route board and lodging subsidies, and luggage carriage for workers travelling to and from site.' Excludes the entry/exit and site-transfer costs of special plant such as shield machines and TBM tunnelling machines.
2. Booking: packaged with on-costs (indirect costs) at a percentage rate. Clause 3.9.3: on-costs = (base-period labour cost + base-period plant and small tools cost) x on-costs percentage rate; the percentage rate is selected by works class (16 classes, no regional dimension) per Table 2.9.1 of TB 10811. In the computation schedule for building-works item preliminary estimates (Table 2.6.2) this is serial 15 'on-costs = [(1)+(3)] x on-costs percentage rate' and serial 16 'item preliminary estimate (budget) value = (14)+(15)'. Mobilization is not a separate line and must not be added again.
3. No overlap with plant entry/exit cost — two plant families. (1) Ordinary construction plant: the plant rate per machine-shift comprises 7 parts — depreciation, overhaul, maintenance, erection and dismantling, labour, power, and others (Clause 3.3.4); on-site erection/dismantling is already inside the plant rate per machine-shift, enters plant and small tools cost via quota machine-shift consumption, and entry/exit or erection/removal must not be added again. (2) Large special plant (bridge erectors, shields, TBMs, etc.): in TB/T 10814-2024 'Railway construction plant and small tools machine-shift cost quota norms', the 'erection and dismantling' column of large special plant such as bridge erectors is marked 'book separately' — booked by special quota line items; and Clause 3.9.2 item 9 expressly excludes shield/TBM entry/exit and site transfer from overheads (company and site) — those go to special quota line items, e.g., 'shield-machine frame lifting and commissioning' SY-419~422 (50 t to 110 t and above, unit: section) in Section 5 'auxiliary measures', Chapter 3 'shield tunnels' of TB/T 10824-2024 'Railway works budget quota manual (China Railway), Volume 3: tunnel works'. Special-plant entry/exit costs and overheads (company and site) are complementary, not overlapping.
4. No overlap with heavy temporary works cost. Heavy temporary works cost (Section 3.8) is the 'construction and removal/restoration' cost of temporary structures (10 classes: temporary rail sidings, motor-haul roads, girder-haul roads, temporary water supply, temporary power lines, centralized power/transformer stations, temporary communication base stations, temporary yards, tunnel sewage plants, ferry crossings, wharves, floating bridges, suspension bridges, footbridges, and underpasses), sized by the project execution plan (construction methodology and site organization) and computed through the item preliminary estimate (budget) schedule by applying quota items; mobilization is the crew-and-plant relocation cost — different natures, no overlap. Boundary note: within heavy temporary works, the 'TBM or shield assembly yard' (Clause 3.8.3 item 8) covers only site earthworks, ground treatment, hardened production areas, and gantry-crane tracks (>=10 t and >=100 m) — not the shield machine's own lifting and commissioning (which goes to special quota line items).
5. Heavy and minor temporary works do not overlap. When heavy temporary works are computed through the item preliminary estimate (budget) schedule, preliminaries are booked at the like permanent-works percentage rate x 0.45, excluding minor temporary works cost — minor temporary works cost is already inside the preliminaries of permanent works (Section 3.6 = (base-period labour cost + base-period plant and small tools cost) x preliminaries percentage rate).
Applicable Boundaries
- Applies only to railway design preliminary estimates (budgets) (TB 10801-2024/TB 10811-2024 system).
- Building/municipal BOQ-based pricing (GB/T 50500 series) has a stand-alone 'large plant and equipment entry/exit and erection/removal' item — a different caliber; do not cross-apply.
- The on-costs base is 'base-period labour cost + base-period plant and small tools cost', excluding materials and excluding price differences.
- Do not list a 'construction plant mobilization/removal' line by old habit — the 2024 edition merged it into on-costs (indirect costs); only special-plant (shield/TBM) entry/exit and site transfer needs special quota line items.
Further Reading
- TB 10801-2024: Section 2.6 'cost composition and item preliminary estimate (budget) computation schedule' (Fig. 2.6.1, Table 2.6.2), Section 3.3 'plant and small tools cost' (Clause 3.3.4 plant rate per machine-shift composition), Section 3.8 'heavy temporary works and transitional works cost' (3.8.1-3.8.7), Section 3.9 'on-costs (indirect costs)' (Clause 3.9.2 item 9; Clause 3.9.3 formula).
- TB 10811-2024: on-costs percentage rate table (Section 2.9, Table 2.9.1, 16 works classes); heavy temporary works Tables 2.8.2-2.8.4.
- TB/T 10814-2024 'Railway construction plant and small tools machine-shift cost quota norms', Chapter 3 'special construction plant', Section 1 bridge works plant (bridge-erector erection/dismantling 'book separately').
- TB/T 10824-2024 'Railway works budget quota manual (China Railway), Volume 3: tunnel works', Chapter 3 shield tunnels, Section 5 auxiliary measures (shield-machine frame lifting and commissioning SY-419~422).
Keywords
- 施工机构调遣费
- 施工单位进退场及工地转移费
- on-costs (indirect costs)
- overheads (company and site)
- 施工机械进出场费
- 大型临时设施费
- railway estimates and budgets (China Railway system)
- TB 10801