railway estimates and budgets (China Railway system)
- 01
Railway general estimate (budget) chapter table, Chapters 1-11: chapter order, section numbers and detailed cost contents per chapter (TB 10801-2024 Appendix A)
Per Appendix A 'General estimate (budget) chapter table' of TB 10801-202…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法:第 2.5 节、第 2.3.3 条、第 3.8 节、第 3.11 条、App. A Table A.0.1、App. B Table B.0.152026-09-25 - 02
Railway 2024 quota system equipment purchase cost: composition and booking — equipment price + equipment freight and handling charges, rate standards, and the nature boundary against installation works cost (TB 10801-2024 Section 3.10 / TB 10811-2024 Section 2.10)
Equipment purchase cost = equipment price + equipment freight and handli…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction ProjectsTB 10811-2024 · Fee schedule for design estimates and budgets of capital railway worksGB/T 50531-2009 · Standard for Classification of Equipment and Materials for Construction Cost Pricing2026-09-25 - 03
Railway work safety fee (mandatory health, safety and environmental (HSE) provisions): calculation rate, non-competitive nature, and earmarked-fund management rules
The railway work safety fee is accrued at 3.0% of the construction and i…
TB 10811-2024 铁路基本建设工程设计概(预)算费用定额TB 10801-2024 铁路基本建设工程设计概(预)算编制办法交通运输部令2017年第25号 公路水运工程安全生产监督管理办法2026-09-25 - 04
Railway 2024 design estimate (budget) VAT listing scheme: rate steps, taxable base and the tax-exclusive caliber (TB 10801/TB 10811-2024)
Under the railway 2024 estimate (budget) system, VAT is listed as a pric…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction ProjectsTB 10811-2024 · Fee schedule for design estimates and budgets of capital railway worksTB/T 10813-2024 · Base Period Prices of Materials for Railway Engineering2026-09-25 - 05
Railway estimate (budget) price adjustment rules: the labour/materials/plant three-line adjustment method and its place in the item-estimate procedure (TB 10801-2024 section 4.1, Table 2.6.2)
TB 10801-2024 clause 4.1.1: price adjustment means the reasonable adjust…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第4.1节、第3.2节、第3.14节、第2.6节及Table 2.6.2TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway worksTB/T 10813-2024 · Base Period Prices of Materials for Railway Engineering2026-09-25 - 06
Railway estimate/budget preliminaries and on-costs (indirect costs): composition, calculation base, and percentage rates (TB 10801-2024 Clauses 3.6/3.9; TB 10811-2024 Table 2.9.1)
Preliminaries (7 items: winter (cold-weather) and rainy-season construct…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.6、3.6、3.9条TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.9节Table 2.9.12026-09-25 - 07
Railway 2024 estimates and budgets: dividing the cost scope between labour cost and on-costs - attribution to production workers (all-in labour cost) vs management personnel (overheads) (TB 10801-2024 clauses 3.1/3.9)
Labour cost means the various costs incurred for the production workers…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction ProjectsTB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works2026-09-25 - 08
Booking construction plant mobilization in railway 2024 preliminary estimates: merged into on-costs (indirect costs) within overheads (company and site) (contractor entry/exit and site-transfer costs), no overlap with plant entry/exit cost or heavy temporary works
The TB 10801-2024 preliminary estimate (budget) system has no stand-alon…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法(第 2.6、3.3、3.8、3.9 节)TB 10811-2024 铁路基本建设工程设计概(预)算费用定额(间接费费率Table 2.9.1、大临Table 2.8.2~2.8.4)TB/T 10814-2024 铁路工程施工机具台班费用定额(Ch. 3专用施工机械)2026-09-25 - 09
Railway basic contingency: scope of use and drawdown discipline — definition of unforeseeable factors, distinction from price-difference contingency, approval procedures (TB 10801-2024 clause 3.13 etc.)
Railway 2024 quota system (TB 10801/10811-2024) basic contingency: (1) r…
TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.13节TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.5节、第3.13节铁建〔1990〕191号《铁路基本建设管理暂行办法》第33条2026-09-25 - 10
Railway estimate/budget other costs: calculating design fees / design-document review fees / other consulting service fees (TB 10811-2024 Clauses 2.11.5~2.11.7)
Design fee: base = total of Chapters 2~10 of the preliminary-design esti…
TB 10811-2024 第2.11.5~2.11.7条TB 10801-2024 第3.11节2026-09-25 - 11
Railway 2024 quota all-in labour rate: composition, the seven base-period classes, and compilation-period labour cost price adjustment (TB 10811-2024 Table 2.1.1; TB 10801-2024 Sections 3.1/4.1)
The comprehensive labor rate comprises basic wages, allowances and subsi…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction ProjectsTB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works2026-09-25 - 12
Calculation rules for railway material transport costs (out-of-price freight and miscellaneous charges) and secondary haulage (TB 10801/10811/10821)
Out-of-price freight and miscellaneous charges = sum(freight + loading/u…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法TB 10811-2024 铁路基本建设工程设计概(预)算费用定额TB/T 10821-2024 铁路工程基本定额2026-09-25 - 13
Charging channels for protection personnel and protection facilities on existing (business) lines (business-line construction cooperation fee + work-safety fee + formal-works chapters)
Railway estimates (budgets) have no separate "protection fee" item: oper…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法TB 10811-2024 铁路基本建设工程设计概(预)算费用定额2026-09-25 - 14
Composition and booking of "other costs" in railway estimates (budgets) (TB 10801-2024 Clause 3.11; Chapter 11 other costs)
Other costs are "static-investment costs payable from capital constructi…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法(第 2.5 节、2.6 节、3.11 条)TB 10811-2024 铁路基本建设工程设计概(预)算费用定额2026-09-25 - 15
Railway estimate compilation scope and unit division: the total/comprehensive/single-item three-level system (TB 10801-2024 Sections 2.2, 2.3)
Per TB 10801-2024 Sections 2.2-2.3: total estimates divide scope by 7 pr…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects2026-09-25 - 16
Relationship between railway estimates and budgets and the over-estimate red line: construction-drawing budgets (investment verification) must not exceed approved preliminary-design estimates (TB 10801-2024; MOR Decree No. 26; GB/T 51095-2015; State Council Decree No. 712)
The two railway cost documents are successive links of one investment-co…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法TB 10811-2024 铁路基本建设工程设计概(预)算费用定额铁道部令第26号 铁路建设工程勘察设计管理办法2026-09-25