Railway estimate/budget other costs: calculating design fees / design-document review fees / other consulting service fees (TB 10811-2024 Clauses 2.11.5~2.11.7)
Design fee: base = total of Chapters 2~10 of the preliminary-design estimate, rate from Table 2.11.5 (0.60%~1.21% interpolated); preliminary design takes 45%, construction drawings 55%; multiplied by complexity adjustment coefficients (0.85~1.30) and speed surcharge coefficients (1.00~1.22), with specially complex designs charged separately; design-document review fee: base = construction-installation cost, rate interpolated by total investment from the table (0.03%~0.23%) times the complexity coefficient; other consulting service fee = (total of Chapters 1~10 - land acquisition (lease) and demolition compensation) x 0.7%.
Applicable Codes
- TB 10811-2024 第2.11.5~2.11.7条
- TB 10801-2024 第3.11节
Topic Positioning
The bases, rate tables, and coefficient adjustment rules of the three design-related fees under "other costs" of railway estimates (budgets) (TB 10811-2024 Clauses 2.11.5~2.11.7), for looking up rates and verifying charges when compiling or reviewing railway project estimates (budgets).
Core Conclusions
- Design fee: base = total cost of Chapters 2~10 of the preliminary-design estimate, rate from Table 2.11.5 (total 50 million yuan -> 1.21%, 1 billion -> 1.13% ... 20 billion and above -> 0.60%, interpolated); preliminary-design fee 45%, construction-drawing design fee 55%; multiplied by the design complexity adjustment coefficient (new single line 0.85 / double line at 200 km/h and below and rebuilds/expansions 1.00 / double line above 200 km/h and technically especially complex 1.15 / specially complex designs 1.30) and the design-fee supplementary adjustment coefficient (v <= 200: 1.00, 200 < v <= 250: 1.11, 300 <= v <= 350: 1.22); overall design fees, prime-designer coordination fees, and other design fees are charged separately at coefficients not exceeding 5%.
- Specially complex designs (arch bridges with main span >= 300 m, bridges with main span >= 500 m, multi-main-span bridges with single main span >= 300 m, inland water depth >= 25 m with complex geology, sea-crossing bridges >= 3000 m long; extra-large-span mined tunnels of three tracks and above, sea-crossing tunnels) have design fees calculated separately, with the supplementary adjustment coefficient set by the line's design speed.
- Design-document review fee: base = construction-installation cost; rate set by total project investment (10 billion and below 0.23%, 50 billion 0.16%, 200 billion 0.09%, 500 billion 0.06%, 1000 billion and above 0.03%, linearly interpolated), then multiplied by the design complexity adjustment coefficient.
- Other consulting service fee: base = total of Chapters 1~10 of the composite estimate (budget) minus land acquisition (lease) and demolition compensation, rate 0.7%.
Applicable Boundaries
The above rates are reference rates; the fees go into the design estimate (budget), while actual costs are market-determined; applies to railway estimates (budgets) compiled under the 2024 compiling measures. The design-fee base is the preliminary-design estimate caliber, the review-fee base is the construction-installation cost, and the consulting-fee base is the total minus land costs — the three bases differ and must not be mixed.
Further Reading
TB 10811-2024 "Cost quotas for design estimates (budgets) of railway capital construction projects" Clauses 2.11.5~2.11.7 and Table 2.11.5 (design fee rates), Table 2.11.5-9 (features of specially complex designs), Table 2.11.5-10 (design complexity adjustment coefficients), Table 2.11.5-11 (design-fee supplementary adjustment coefficients), Table 2.11.6 (design-document review fee rates); TB 10801-2024 Section 3.11 (other-cost composition and definitions).