Railway estimate/budget special construction additional fees: windy-sand / plateau / primeval-forest region construction additional fees (TB 10801-2024 / TB 10811-2024)

Windy-sand region additional fee: base = compilation-period labor cost + construction machinery cost of outdoor construction-installation works in the windy-sand section, rate 2.2%; plateau regions (elevation >= 2000 m): quota work-days x compilation-period composite wage price x work-day increase + quota machinery-shift quantities x compilation-period shift price x machinery-shift increase, graded by elevation (2000~3000 m 8%/19% up to > 5000 m 40%/85%); primeval-forest regions: only new/second-line subgrade earthwork, charged as (quota work-days x composite wage price + quota machinery-shift quantities x shift price) x 25%.

Applicable Codes

  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额

Topic Positioning

The bases to which percentage rates are applied, rates, and algorithms for the three natural-condition items under 'special construction additional fees' in the railway estimate (budget) cost system — windy-sand region, plateau region, and primeval-forest region construction additional fees. Defined in TB 10801-2024 Clauses 3.7.2~3.7.4; rates and increase magnitudes follow TB 10811-2024 Clauses 2.7.1~2.7.3. The train-interference and business-line blockade items are on a companion card.

Core Conclusions

  1. Windy-sand region construction additional fee: applies to outdoor construction and installation works in the windy season of non-fixed desert/Gobi regions with a monthly (or 30-consecutive-day) average wind force of class 4 or above (average wind speed >= 5.5 m/s). Base = estimate preparation period labour cost plus estimate preparation period plant and small tools cost for outdoor works in the windy-sand section, with a rate of 2.2%. For high-wind months (average wind speed >= 5.5 m/s and hourly extreme wind speed >= 13.9 m/s accumulating to 85 hours or more), separate analysis and inclusion based on survey data is allowed.
  2. Plateau region construction additional fee: charged for construction at elevations >= 2000 m; algorithm = quota work-days × estimate preparation period composite labour rate × work-day quota increase + quota plant machine-shift quantities × estimate preparation period plant rate per machine-shift × plant machine-shift quota increase. Grades: 2000~3000 m 8%/19%, 3000~4000 m 15%/32%, 4000~4500 m 23%/50%, 4500~5000 m 27%/57%, above 5000 m 40%/85% (work-day/plant machine-shift).
  3. Primeval-forest region construction additional fee: limited to subgrade earthwork of new or second-line railways; algorithm = (subgrade earthwork quota work-days × estimate preparation period composite labour rate + quota plant machine-shift quantities × estimate preparation period plant rate per machine-shift) × 25%.

Applicable Boundaries

Where a plateau section spans two or more elevation grades, weight-average by the length proportion of each grade; tunnels constructed via auxiliary adits are graded by the auxiliary adit's highest elevation; in-tunnel works of tunnels over 4 km in length step up one grade, but tunnels designed with oxygen supply/enrichment do not; heavy temporary works are graded by design elevation. The windy-sand rate covers only outdoor works of the corresponding windy-sand section; the primeval-forest rate covers only subgrade earthwork. Each is charged separately per actual applicable conditions and shall not be double-counted.

Further Reading

TB 10801-2024 'Measures for compiling design estimates (budgets) of railway capital construction projects' Clauses 3.7.2~3.7.4; TB 10811-2024 'Cost quotas for design estimates (budgets) of railway capital construction projects' Clauses 2.7.1~2.7.3 and Table 2.7.2 (plateau construction quota increases).

Keywords

  • 特殊施工增加费
  • 风沙地区施工增加费
  • 高原地区施工增加费
  • 原始森林地区施工增加费
  • 高原地区施工定额增加幅度
  • TB 10801
  • TB 10811