Highway JTG 3830-2018 plateau-region construction addition: from 2000 m elevation, base quota labor + quota plant cost, stepped rates in Table 3.1.6-4

Per clause 3.1.6 item 4 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects", the plateau-region construction addition is charged from 2000 m elevation (inclusive) upward: the extra cost of reduced labor and plant efficiency in regions above 2000 m due to climate and air pressure; charged on the base of quota labor + quota construction-plant cost of each works class at Table 3.1.6-4 rates (first step 2000-2500 m: earthwork 13.295%, rockwork 13.711%, pavement 14.572%, structures 13.364%; then every 500 m to above 5000 m). Where a route crosses two or more elevation zones, compute separately or derive an average addition rate by quantity proportion, then compute the whole-line fee.

Applicable Codes

  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.1.6 条第 4 款、Table 3.1.6-4

Topic Positioning

The rules for charging the "plateau-region construction addition" in the highway 2018 norm system (JTG 3830-2018): threshold elevation, definition, the base to which percentage rates are applied, rate-table structure and treatment across elevation zones — a component of the special-region construction addition within preliminaries.

Core Conclusions

Under clause 3.1.6, item 4 of the Administrative Compilation Rules for Estimates and Budgets of Highway Works (JTG 3830-2018):

  1. Threshold elevation: the plateau-region construction addition is the extra cost incurred in works above 2000 m elevation, where climate and air pressure lower labour and plant efficiency. It is charged from 2000 m (inclusive) — the first step of the rate table is 2000-2500 m; below 2000 m the fee does not apply.

  2. Base to which percentage rates are applied: the sum of the norm-based labour cost and the norm-based construction plant cost of each class of works, taken at the rates of Table 3.1.6-4 "Plateau-region construction addition rate table" (note: not the full cost, and taken at norm prices).

  3. Rate-table structure (Table 3.1.6-4): 7 elevation steps — 2000-2500 m, 2501-3000 m, 3001-3500 m, 3501-4000 m, 4001-4500 m, 4501-5000 m and above 5000 m, one step per 500 m; rows by class of works (earthwork, rockwork, haulage, pavement, Structures I/II/III, technically complex bridges, steel and steel structures, etc.). Sample rates for the first step (2000-2500 m): earthwork 13.295%, rockwork 13.711%, pavement 14.572%, Structure I 13.364%; rates rise steeply with elevation, the earthwork rate reaching 91.853% in the above-5000 m step.

  4. Across elevation zones: where a route passes through two or more different elevation zones, the plateau-region construction addition shall be computed separately for each, or an average addition rate obtained in proportion to quantities and used to compute the addition for the whole line.

  5. Where the fee belongs: the special-region construction addition comprises three items — plateau-region, wind-sand-region and coastal-region construction additions (clause 3.1.6, item 4); the plateau fee is one of them, and all fall under preliminaries.

Applicable Boundaries

  • Applies to estimate and budget compilation for highway works construction projects (JTG 3830-2018 pricing system); below 2000 m the fee does not arise.
  • The base is the sum of "norm-based labour cost + norm-based construction plant cost", taken at the rate for the relevant class of works; the rate is read from Table 3.1.6-4 with no interpolation, applying the step of the elevation zone concerned.
  • Where a route crosses several elevation zones, a single blanket rate may not be used; compute separately or derive an average addition rate in proportion to quantities.
  • This card follows the highway system basis; the railway system (TB 10801-2024) also starts at 2000 m elevation but uses a different method (railway: norm-based worker-days x composite labour rate per worker-day x worker-day increase percentage + norm-based machine-shift quantities x plant rate per machine-shift x machine-shift increase percentage), and the two bases must not be mixed.

Further Reading

  • See clause 3.1.6 (preliminaries) item 4 of JTG 3830-2018 Administrative Compilation Rules for Estimates and Budgets of Highway Works, and Table 3.1.6-4 "Plateau-region construction addition rate table"; item 4 also sets out the wind-sand-region and coastal-region construction additions, and the same clause contains the rainy-season construction addition (Table 3.1.6-2), night-work construction addition (Table 3.1.6-3), auxiliary works allowance (Table 3.1.6-8) and works-transfer fee (Table 3.1.6-9), among other preliminaries rules.
  • For comparison with the railway system, see the railway special construction addition cards (wind-sand / plateau / primitive forest, TB 10801-2024 / TB 10811-2024).
  • The overall composition of the cost of works (construction and installation) for highway works and the base for each charge are set out in the card "Highway 2018 norm system: composition of the cost of works (construction and installation) (JTG 3830-2018, section 3.1)".