Highway estimate/budget construction-auxiliary fee base: quota direct costs x Table 3.1.6-8 rates (JTG 3830-2018 clause 3.1.6 item 6)
The highway construction-auxiliary fee is charged on the base "quota direct costs of each works class" at the rates of JTG 3830-2018 Table 3.1.6-8. Quota direct costs = quota labor + quota materials + quota construction-plant cost (all at quota base prices, unaffected by compilation-period price movements). Construction-monitoring fees (high-fill/soft-ground settlement monitoring, high-slope stability monitoring, bridge construction monitoring, tunnel monitoring measurement, advance geological forecast) are already inside the construction-auxiliary fee and may not be computed separately. By contrast, the plateau/wind-sand/coastal-region construction addition and traffic-interference addition and the works-transfer fee within the same measures costs use the base "quota labor + quota plant cost" — the bases differ; distinguish when compiling.
Applicable Codes
- JTG 3830—2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.1条、第3.1.6条第6款、Table 3.1.6-8
- JTG/T 3832—2018 · Budget Quota of Highway Engineering 附录四
- JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery
Topic Positioning
This card answers the percentage-rate base question for the "construction-auxiliary fee" under measures costs in highway estimate/budget compilation, and sorts out the base differences among JTG 3830-2018 measures-cost items — for direct use in highway estimate/budget compilation and review.
Core Conclusions
Base: "Measures for compiling estimates and budgets of highway construction projects" (JTG 3830-2018) clause 3.1.6 item 6, verbatim — "The construction-auxiliary fee covers production tools and instruments use fees, inspection and test fees, and works positioning and re-measurement, works handover and site clearing costs. The construction-auxiliary fee is charged on the base of the quota direct costs of each works class at the rates of Table 3.1.6-8."
Meaning of quota direct costs (clause 3.1.1): quota direct costs = quota labor + quota materials + quota construction-plant cost. Each is taken at base prices per Appendix IV "quota labor, material and equipment unit-price table" of the "Highway works budget quota" (JTG/T 3832-2018) and the current "Highway works machinery shift fee quota" (JTG/T 3833) — i.e. quota base-period prices, not moving with compilation-period market prices; this is its essential difference from "direct costs" (at compilation-period prices).
Content of the construction-auxiliary fee (verbatim): (1) production tools and instruments use fee — purchase, amortization and maintenance of production tools, inspection/test instruments and apparatus not belonging to fixed assets, plus allowances to workers for their own tools; (2) inspection and test fee — the contractor's costs of ordinary appraisal and checking of materials, components and works, including materials and chemicals consumed in its own laboratory plus technical-innovation and research-test costs, excluding tests of new structures and new materials and tests demanded by the owner on materials with factory certificates, destructive component tests and other special inspections; (3) works positioning and re-measurement, handover and site clearing costs.
No double charging (verbatim): "Construction-monitoring fees such as high-fill and soft-ground settlement monitoring, high-slope stability monitoring, bridge construction monitoring, tunnel monitoring measurement and advance geological forecast are contained in the construction-auxiliary fee and may not be computed separately." — listing a construction-monitoring item separately in compilation is double pricing.
Measures-cost bases compared (same clause 3.1.6; distinguish when compiling):
- Base quota direct costs: construction-auxiliary fee (Table 3.1.6-8);
- Base quota labor + quota plant cost: plateau-region, wind-sand-region (weighted by route length where the route crosses more than one wind-sand zone) and coastal-region construction addition; traffic-interference addition (only the affected portions; not for new works, closed construction with traffic interruption, or rebuild/widen projects with bypass roads); and the works-transfer fee (Table 3.1.6-9; distance from provincial-capital city for expressway/first-class and standalone major bridges/tunnels, from the prefecture city for second-class and below; interpolable; within 50 km as 50 km).
Form caliber: in estimate/budget Forms 08/09, measures costs are entered with "quota labor + quota plant cost, or quota direct costs" in the base column and the rate in the quantity column.
Applicable Boundaries
- Applies only to highway estimate and budget compilation (including standalone major bridges and tunnels) under JTG 3830-2018; not for railway, building/municipal systems (railway measures costs use the base "base-period labor + base-period plant use" and a different construction-auxiliary caliber).
- Rates must be looked up by works class in Table 3.1.6-8 — this card does not reproduce the rate values; check the current edition for amendments before use.
- The auxiliary-production indirect cost (self-quarried sand/stone etc.) at 3% of quota labor merges into material budget prices and does not appear directly in the estimate (budget); it is a different item from the construction-auxiliary fee — do not confuse.
Further Reading
- JTG 3830-2018 clause 3.1.1 (construction-installation cost composition; quota direct costs defined), clause 3.1.6 (measures-cost definitions and bases), Table 3.1.6-8 (construction-auxiliary rates), Table 3.1.6-9 (works-transfer rates).
- JTG/T 3832-2018 Appendix IV "quota labor, material and equipment unit-price table" (source of quota base prices).
- JTG/T 3833 "Highway works machinery shift fee quota" (source of plant shift base prices).
- Comparison: railway measures costs per TB 10801-2024 clause 3.6 (base: base-period labor + base-period plant use); the winter/rainy-season and works-transfer cards cross-confirm the highway measures-cost base system.