Whether purchased materials enter the bases to which percentage rates are applied for preliminaries and overheads (company and site) in highway preliminary estimates (budgets): the ministry JTG 3830-2018 base system and local exclusion rules (Qinghai DB63/T 2011-2022, Beijing DB11/T 1509-2018)
The ministry JTG 3830-2018 does not itemize exclusions of purchased materials; it distinguishes through base rules: preliminaries items based on "norm-based labour cost + norm-based plant and small tools cost" (winter/rainy/night/plateau/sand-storm/coastal/traffic-interference construction additions, site transfer fee) naturally contain no material cost; the auxiliary works allowance and overheads (company and site) based on "norm-based direct cost" (= norm-based labour cost + norm-based material cost + norm-based plant and small tools cost, all at JTG/T 3832-2018 appendix IV base prices) include purchased materials at quota base prices. Express exclusions are local: Qinghai DB63/T 2011-2022 clause 6.1.1.2 excludes purchased subgrade maintenance fill, greening nursery stock, commercial cement concrete, commercial asphalt mixes and stabilized-soil mixes, purchased concrete units, and permanent equipment procurement cost from the bases for preliminaries and overheads (company and site); Beijing DB11/T 1509-2018 clause 13.3.2.3 sets the purchased finished-material percentage rate uniformly at 0 (no comprehensive rate) and the paving/installation quota percentage rate at 10 for structures (general). Note clause 3.1.2 ("commercial cement concrete, asphalt mixes and stabilized-soil mixes carry no purchasing and custody charges; purchased units, finished and semi-finished products at 0.42%") is a purchasing and custody rule, not a fee-base rule.
Applicable Codes
- JTG 3830-2018 公路工程建设项目概算预算编制办法
- DB63/T 2011-2022 公路养护工程预算编制指南
- DB11/T 1509-2018 公路工程设计导则
- JTG/T 3832-2018 公路工程预算定额
- JTG/T 3833 公路工程机械台班费用定额
Topic Positioning
This card answers "which purchased materials do not enter the bases to which percentage rates are applied for preliminaries and overheads (company and site) in highway preliminary estimate (budget) compilation": first clarifies the ministry JTG 3830-2018 base system (when material costs naturally drop out, when they enter at base prices), then gives local standards with express exclusion lists (Qinghai DB63/T 2011-2022, Beijing DB11/T 1509-2018), and disentangles the easily confused purchasing and custody exemption clause.
Core Conclusions
1. Ministry JTG 3830-2018 caliber: no itemized exclusions; separation by base rules.
- Norm-based direct cost definition (clause 3.1.1): "the sum of norm-based labour cost, norm-based material cost and norm-based plant and small tools cost, computed as quantities x the base prices in appendix IV of the current Highway Works Estimate Quota (JTG/T 3831) or Budget Quota (JTG/T 3832-2018)". Norm-based material cost = quota material consumption x appendix IV material base prices.
- Preliminaries items based on "norm-based labour cost + norm-based plant and small tools cost": winter, rainy, night, plateau, sand-storm, coastal and traffic-interference construction additions, site transfer fee (table 3.1.6-9) — all material costs (purchased included) naturally excluded.
- Items based on "norm-based direct cost of each works class": auxiliary works allowance (table 3.1.6-8 percentage rates) and the five overheads (company and site) items (basic fee, staple-food transport subsidy, home-visit travel, heating subsidy, financial charges, tables 3.1.7-1 to 3.1.7-5) — purchased materials enter at quota base prices; the ministry text excludes no purchased-material class. 2. Local express exclusion rules (apply per project location). (a) Qinghai DB63/T 2011-2022 "Guide for compiling highway maintenance budgets" clause 6.1.1.2: "purchased subgrade maintenance fill, greening nursery stock, commercial cement concrete, commercial asphalt mixes and all stabilized-soil mixes, purchased concrete units, and permanent equipment procurement cost do not serve as the base to which percentage rates are applied for preliminaries and overheads (company and site)" — seven purchased classes excluded. (b) Beijing DB11/T 1509-2018 "Highway engineering design guideline" clause 13.3.2: "13.3.2.1 Common purchased finished materials include commercial concrete (asphalt and cement), lime-flyash-gravel mixes, small finished units (kerbs, pavement bricks, lawn bricks, large square bricks etc.) and purchased pipes." "13.3.2.3 The purchased finished-material percentage rate is uniformly 0, taking no comprehensive rate; the paving and installation quota percentage rate is uniformly 10, charged for structures (general)." Clause 13.3.2.2 adds that purchased finished-material published price information (government guidance prices) already includes transport (no separate charge) and prices are VAT-exclusive. 3. Easily confused point. JTG 3830-2018 clause 3.1.2 ("commercial cement concrete, asphalt mixes and stabilized-soil mixes carry no purchasing and custody charges; purchased units, finished and semi-finished products at 0.42%") is a norm-based material price for estimating composition rule, not a preliminaries/overheads fee-base rule — do not mix.
Applicable Boundaries
- The ministry JTG 3830-2018 base system applies to highway new-build and rebuild/expansion preliminary estimates (budgets) nationwide; Qinghai DB63/T 2011-2022 is Qinghai's highway maintenance caliber, Beijing DB11/T 1509-2018 Beijing's design-stage caliber — local standards apply per project location, and where used together with the ministry administrative compilation rules the project's governing caliber prevails.
- Not applicable to railways (TB 10801-2024 preliminaries/on-costs (indirect costs) on base-period labour cost + base-period plant and small tools cost), building/municipal (GB/T 50500 BOQ-based pricing caliber) or other industries.
- This card excludes the numeric percentage-rate tables 3.1.6-8/9 and 3.1.7-1~5; actual percentage rates must be read from the standards; "purchased finished-material percentage rate 0, paving/installation 10" is Beijing's local band, not portable.
Further Reading
- MOT "Measures for compiling estimates and budgets of highway construction projects" (JTG 3830-2018) section 3.1: 3.1.1 norm-based direct cost / norm-based construction-installation cost definitions; 3.1.2 material cost and purchasing and custody charges; 3.1.6 preliminaries; 3.1.7 overheads (company and site); 3.1.8 statutory levies and fees (on the sum of labour costs); 3.1.9 profit (7.42% of norm-based direct cost + preliminaries + overheads); 3.1.10 taxes and duties (VAT under the current standard); 3.1.11 special fees (site construction, statutory work safety levy (earmarked funds)).
- Qinghai DB63/T 2011-2022 clause 6.1.1 general provisions; Beijing DB11/T 1509-2018 clause 13.3.2 purchased finished materials.
- Companion quota norms: JTG/T 3832-2018 appendix IV "unit price tables of quota labour, materials, equipment"; JTG/T 3833 "Plant rate norms per machine-shift of highway works".
Keywords
- 外购材料
- preliminaries
- overheads (company and site)
- base to which percentage rates are applied
- norm-based direct cost
- JTG 3830-2018
- DB63/T 2011-2022
- DB11/T 1509-2018
- 外购成品材料
- 综合费率