base to which percentage rates are applied
- 01
Fee boundary for material price adjustment: the price difference carries VAT only, with no management fee or profit; the eight cost categories under Clause 8.7.6 are not adjusted (GB/T 50500-2024)
Per GB/T 50500-2024 Clause 3.3.5 item 4, price differences of labor, mat…
GB/T 50500-2024 第3.3.5条(物价变化合同价格调整)GB/T 50500-2024 第8.7.6条(不应因物价变化调整的费用)GB/T 50500-2024 第7.3.1条(措施项目不予计量调整)2026-10-25 - 02
Computation procedure and cost make-up of item-wise estimates (budgets) for railway works of construction and installation, including the equipment item-wise procedure - TB 10801-2024 Section 2.6 Tables 2.6.2 and 2.6.3
Per TB 10801-2024 Article 2.6.2 Table 2.6.2, the item-wise estimate (bud…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第2.6节(Table 2.6.2、Table 2.6.3)TB 10811-2024 铁路基本建设工程设计概(预)算费用定额2026-10-11 - 03
Highway JTG 3830-2018 Table 3.6.1 computation sequence for the cost of works (construction and installation): how the 8 components add up, the 7.42% profit, and the two different tax bases
Per Clause 3.6.1, Table 3.6.1 of JTG 3830-2018 (computation procedure an…
JTG 3830-2018 公路工程建设项目概算预算编制办法JTG/T 3832—2018 公路工程预算定额JTG/T 3833 公路工程机械台班费用定额2026-09-25 - 04
Whether purchased materials enter the bases to which percentage rates are applied for preliminaries and overheads (company and site) in highway preliminary estimates (budgets): the ministry JTG 3830-2018 base system and local exclusion rules (Qinghai DB63/T 2011-2022, Beijing DB11/T 1509-2018)
The ministry JTG 3830-2018 does not itemize exclusions of purchased mate…
JTG 3830-2018 公路工程建设项目概算预算编制办法DB63/T 2011-2022 公路养护工程预算编制指南DB11/T 1509-2018 公路工程设计导则2026-09-25 - 05
Highway 2018 quota norms system: composition of the cost of works (construction and installation) — 8 cost items, separation of net price and VAT, and bases to which percentage rates are applied (JTG 3830-2018 section 3.1)
Per JTG 3830-2018 clause 3.1.1, highway cost of works (construction and…
JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1节JTG/T 3832-2018 · Budget Quota of Highway Engineering 附录四JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery2026-09-25 - 06
Railway construction-installation single-item estimate calculation program (TB 10801-2024 Table 2.6.2): 16-step accumulation and percentage-rate base rules — labor + machinery in the base; materials / out-of-price freight / price differences / fill material out; VAT separately listed
The single-item estimate for cost of works (construction and installatio…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第2.6节(图2.6.1、Table 2.6.2、Table 2.6.3)、第3.4节、第3.12条TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works2026-09-25