Highway JTG 3830-2018 Table 3.6.1 computation sequence for the cost of works (construction and installation): how the 8 components add up, the 7.42% profit, and the two different tax bases
Per Clause 3.6.1, Table 3.6.1 of JTG 3830-2018 (computation procedure and method for each cost), the cost of works (construction and installation) is built up in this order: direct cost (labour cost + material cost + plant cost) -> permanent equipment procurement cost (Form 05) -> preliminaries and overheads (company and site) (on the sum of norm-based labour cost plus norm-based plant cost, or norm-based direct cost x the prescribed percentage rate) -> statutory levies and fees (on the sum of the labour costs of the various classes of works, at the standards laid down by law) -> profit (7.42% of the sum of norm-based direct cost plus preliminaries plus overheads) -> taxes and duties ((direct cost + permanent equipment procurement cost + preliminaries + overheads + statutory levies and fees + profit) x construction VAT rate, Formula 3.1.10) -> special items (construction site development fee + statutory work safety levy; the levy = cost of works excluding the levy itself x rate, not less than 1.5%); added together the 8 components give the cost of works. Basis note: filling note 5 for Form 03 excludes the permanent equipment procurement cost from the tax base, unlike Formula 3.1.10, which includes it.
Applicable Codes
- JTG 3830-2018 公路工程建设项目概算预算编制办法
- JTG/T 3832—2018 公路工程预算定额
- JTG/T 3833 公路工程机械台班费用定额
Topic Positioning
This card answers how the cost of works (construction and installation) is built up item by item in the cost computation table of the highway 2018 pricing system — the summation order and the bases to which percentage rates are applied under Table 3.6.1 (Clause 3.6.1, JTG 3830-2018, Administrative Compilation Rules for Estimates and Budgets of Highway Works), and the difference in the tax base between the itemized Form 03 and the clause formula.
Core Conclusions
Composition (Clause 3.1.1, in substance, 8 items): the cost of works (construction and installation) comprises direct cost, permanent equipment procurement cost, preliminaries, overheads (company and site), statutory levies and fees, profit, taxes and duties, and special items, i.e.: cost of works = direct cost + permanent equipment procurement cost + preliminaries + overheads + statutory levies and fees + profit + taxes and duties + special items.
Item-by-item computation and summation order (Table 3.6.1 basis): (1) Direct cost (Clause 3.1.2) = labour cost + material cost + plant cost. Labour cost = norm labour-days x all-in daily labour rate (issued by the provincial transport authority); material cost = norm material consumption x norm-based material price for estimating, where the norm-based material price for estimating = (material price at source + freight and handling charges) x (1 + off-site transport wastage rate) x (1 + purchasing and custody charges rate) - recovery value of packaging; plant cost = norm machine-shift consumption x plant rate per machine-shift. (2) Permanent equipment procurement cost: per the equipment cost computation form (Form 05). (3) Preliminaries and overheads (company and site) (filling notes for Form 03): computed on the sum of the norm-based labour cost and the norm-based plant cost of the corresponding items, or on the norm-based direct cost x the prescribed percentage rate. (4) Statutory levies and fees (Clause 3.1.8, in substance): each statutory levy and fee is computed on the sum of the labour costs of the various classes of works, at the standards laid down by state or local laws, regulations, rules and codes. (5) Profit (Clause 3.1.9, in substance): computed at 7.42% of the sum of the norm-based direct cost plus preliminaries plus overheads. (6) Taxes and duties (Formula 3.1.10, in substance): taxes and duties = (direct cost + permanent equipment procurement cost + preliminaries + overheads + statutory levies and fees + profit) x construction VAT rate. (7) Special items (Clause 3.1.11) = construction site development fee + statutory work safety levy: the construction site development fee is computed by the progressive (banded) method on the site-fee base (= norm-based cost of works minus special items) at the rates in Table 3.1.11; the statutory work safety levy = cost of works (excluding the levy itself) x work safety levy rate, taken at not less than 1.5%.
Two key pricing bases (Clause 3.1.1): (1) Separation of net price and VAT: except for the special items, all components are computed under the rule of separation of net price and VAT, i.e. every cost is computed at prices (or percentage rates) excluding deductible input VAT. (2) Norm basis: norm-based cost of works (construction and installation) = norm-based direct cost + 40% of the norm-based permanent equipment procurement cost + preliminaries + overheads + statutory levies and fees + profit + taxes and duties + special items; norm-based direct cost = norm-based labour cost + norm-based material cost + norm-based plant cost (all taken at the base prices in Appendix IV of the Highway Works Budget Quota Manual, JTG/T 3832-2018, and the current Highway Engineering Plant Rate Norms per Machine-Shift, JTG/T 3833). This basis is used for summary tables and for the bases to which percentage rates are applied; it is distinct from the actual cost of works computed at prices of the compilation period, and the two must not be mixed.
Caution on the tax base: filling note 5 for Form 03 (Cost of Works Computation Form) reads taxes and duties = (direct cost + preliminaries + overheads + statutory levies and fees + profit) x rate — excluding the permanent equipment procurement cost; whereas the summary formula in Clause 3.1.10 includes it. In the itemized form the permanent equipment procurement cost is a separate line; when summarized into the general table the clause formula governs the tax computation, so the summary basis of the software used should be checked at compilation.
One-line summary of the summation logic: first compute the direct cost (labour + material + plant); roll up preliminaries and overheads on the norm-based labour cost plus norm-based plant cost (or the norm-based direct cost); roll up statutory levies and fees on the labour cost; roll up profit (7.42%) on (norm-based direct cost + preliminaries + overheads); roll up taxes and duties on (direct cost + permanent equipment procurement cost + preliminaries + overheads + statutory levies and fees + profit); finally add the special items; adding the 8 components gives the cost of works (construction and installation).
Applicable Boundaries
- Applies to the compilation of estimates and budgets for highway construction projects (the JTG 3830-2018 pricing system); Table 3.6.1 is the computation sequence common to both the estimate and the budget stage.
- Not applicable to other sectors: railways follow the 16-step accumulation sequence in Table 2.6.2 of TB 10801-2024, and building and municipal works follow the GB/T 50500 BOQ-based pricing system — the composition and the bases to which percentage rates are applied differ by sector and must not be mixed.
- The difference in tax base between the itemized Form 03 and the clause summary formula is a reporting-basis matter and must be reconciled on the summary basis, so as to avoid omitting the permanent equipment procurement cost from the tax base or double-counting tax.
- The 7.42% profit is the rate prescribed by JTG 3830-2018; the 1.5% work safety levy is a floor rate, not a fixed value; the construction site development fee is computed progressively at the rates in Table 3.1.11.
Further Reading
- JTG 3830-2018: Clause 3.6.1, Table 3.6.1 (computation procedure and method for each cost); Clause 3.1.1 (composition of the cost of works, separation of net price and VAT, norm basis); Clause 3.1.2 (direct cost); Clauses 3.1.8-3.1.10 (statutory levies and fees, profit, taxes and duties); Clause 3.1.11 (special items, with the Table 3.1.11 rates for the construction site development fee); Appendix A, Table A.0.2-7 (Form 03, Cost of Works Computation Form) and its filling notes.
- Companion quota manuals: Highway Works Budget Quota Manual (JTG/T 3832-2018), Appendix IV (table of norm unit prices for labour, materials and equipment); the current Highway Engineering Plant Rate Norms per Machine-Shift (JTG/T 3833).