Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Highway estimate/budget statutory fees (规费) base: charged on the sum of labor costs of each works class (JTG 3830-2018 clause 3.1.8) and the distinction from quota labor

Per JTG 3830-2018 clause 3.1.8, highway statutory fees comprise five items — pension, unemployment, medical (including maternity), work-injury insurance and housing fund; "each statutory fee is charged on the base of the sum of labor costs of each works class, at standards set by state or local laws, regulations, rules and provisions." That base is the compilation-period labor cost at the works location's composite day rate, not the "quota labor" priced at Appendix IV base prices of JTG/T 3832-2018 (the latter serving only quota direct costs and the bases of measures/enterprise-management/profit fees); the composite day rate already includes the employee-paid pension, unemployment, medical (excluding maternity) and housing fund, while the statutory fee charges the enterprise-paid portion.

Applicable Codes

  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第 3.1.8 条(规费)
  • JTG 3830-2018 第 3.1.2 条(人工费、综合工日单价)
  • JTG 3830-2018 第 3.1.1 条(建安费组成、定额人工费定义)
  • JTG 3830-2018 第 3.1.10 条(税金)
  • JTG/T 3832—2018 · Budget Quota of Highway Engineering 附录四
  • JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery

Topic Positioning

This card answers "on what base are highway statutory fees computed" in estimate/budget compilation: per clause 3.1.8 of JTG 3830-2018 "Measures for compiling estimates and budgets of highway construction projects", statutory fees (five insurances and one fund) are charged on the sum of labor costs of each works class at state or local standards; and it clarifies the difference between that base and "quota labor" (Appendix IV base-price caliber) to prevent wrong fee bases.

Core Conclusions

(1) Composition (clause 3.1.8): statutory fees comprise 1) pension insurance; 2) unemployment insurance; 3) medical insurance (including maternity); 4) work-injury insurance; 5) housing fund. (2) Base (clause 3.1.8 verbatim): "Each statutory fee is charged on the base of the sum of labor costs of each works class, at standards set by state or local laws, regulations, rules and provisions." Rates follow state or works-location (provincial) provisions; in compilation use the rates/standards published (or supplemented) by the provincial transport authority at the works location. (3) Caliber of "labor cost" in the base: the compilation-period labor cost = estimate/budget quota worker-days x the works location's composite day rate (clause 3.1.2; the day rate is set, published and dynamically adjusted by the provincial transport authority, serving only estimate/budget compilation, not actual wage payment). It is not the "quota labor" computed at the worker-day base prices of Appendix IV "quota labor, material and equipment unit-price table" of JTG/T 3832-2018 — quota labor serves only quota direct costs and the bases of other fees (measures, enterprise management, profit); the two must not be confused. (4) Relation to employee-paid portions: the composite day rate adopted by the highway quotas already includes the employee-paid pension, unemployment, medical (excluding maternity) and housing fund; the statutory fee charges the enterprise-paid portion at standards, computed separately on the labor-cost base. (5) Downstream: statutory fees, once inside construction-installation costs, join the tax base: tax = (direct costs + equipment purchase + measures + enterprise management + statutory fees + profit) x the construction VAT rate (formula 3.1.10) — the tax base includes statutory fees.

Applicable Boundaries

  • Applies to highway estimate and budget compilation (JTG 3830-2018); not for railway, building/municipal or other industries.
  • "Sum of labor costs" means the compilation-period labor at the composite day rate, not the Appendix IV base-price quota labor — the two serve different fee chains; mixing them produces wrong amounts.
  • The railway system (TB 10801-2024) has no separate "statutory fees": pension etc. are merged into the composite labor rate, set per TB 10811 "Railway capital construction design estimate (budget) fee quota" — apply the highway and railway systems separately.
  • Statutory-fee rates follow current state or provincial provisions; the rates in the measures' tables are reference only — check each province's companion documents.

Further Reading

  • JTG 3830-2018: section 2.1 basic provisions (labor/material/plant costs from the consumptions of JTG/T 3831 and JTG/T 3832 priced at the location's labor day rate, material budget prices and plant shift prices, with fees charged accordingly); clause 3.1.1 (composition; quota costs defined at base prices); clause 3.1.2 (labor and material calibers); clause 3.1.8 (statutory fees); clause 3.1.10 (tax).
  • Companion quotas: JTG/T 3832-2018 Appendix IV unit-price table (worker-day, material and equipment base prices); JTG/T 3833 machinery shift fee quota (plant shift base prices).
  • Railway comparison: TB 10801-2024 "Measures for compiling design estimates (budgets) of railway capital construction projects" and TB 10811-2024 fee quota.
  • No official .gov.cn URL for the source text; verify via the Ministry of Transport's official publication of JTG 3830-2018.