Composition of labor cost (quota labor cost) in the highway 2018 system: three classes of wage-type costs and the comprehensive shift-price caliber (JTG 3830-2018 Clause 3.1.2)
Per Clause 3.1.2 of JTG 3830-2018, highway estimate (budget) labor cost has three classes of wage-type costs: (1) time-rate or piece-rate wages; (2) allowances and subsidies (mobility allowance, special-region allowance, high-temperature/cold temporary allowance, work-at-height allowance, etc.); (3) wages paid under special circumstances (sickness, work injury, maternity, family-planning leave, marriage/bereavement leave, personal leave, home-visit leave, regular leave, suspended-work study, performance of state or social duties, at a proportion of the time/piece rate). Labor cost = quota labor shifts x comprehensive shift price (set, published, and dynamically adjusted by the provincial transport authority; not differentiated by trade; already including the individual's pension, unemployment, and medical insurance (excluding maternity) and housing fund), used only as the estimate/budget basis, not as an actual-wage basis; must be distinguished from the "quota labor cost" (percentage-rate base caliber) computed at the JTG/T 3832-2018 Appendix IV base prices.
Applicable Codes
- JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.2条
- JTG 3820-2018 · Measure for Compilation of Investment Estimates of Highway Construction Projects
- JTG/T 3832-2018 · Budget Quota of Highway Engineering 附录四
- JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery
Topic Positioning
This card covers the composition and pricing basis of "labour cost (norm-based labour cost)" under Clause 3.1.2 of JTG 3830-2018, the administrative compilation rules for estimates and budgets of highway works construction projects, within the 2018 highway quota system: the three classes of wage-related costs, the nature of the all-in daily labour rate, and the distinction between "norm-based labour cost (base-price basis)" and "labour cost (compilation-period all-in daily labour rate basis)".
Core Conclusions
Per Clause 3.1.2 of JTG 3830-2018, labour cost means the costs of the production workers directly engaged in construction and installation works as listed in the estimate and budget quotas; its wage-related costs fall into three classes:
- Time-rate or piece-rate wages: remuneration paid to individuals at the time-rate standard according to working time, or at piece rates for work done.
- Allowances and subsidies: allowances paid to individuals to compensate for special or extra labour consumption and for other special reasons, as well as price subsidies paid to keep wage levels unaffected by price movements — e.g., mobility allowance for construction, allowance for construction in special regions, temporary allowance for high-temperature (low-temperature) operations, work-at-height allowance.
- Wages paid under special circumstances: wages paid at a certain proportion of the time-rate or piece-rate standard, in accordance with state laws, regulations and policies, for sickness, work injury, maternity leave, family-planning leave, marriage or bereavement leave, personal leave, home-visit leave, regular leave, study during work stoppage, or performance of state or social duties.
Pricing rules:
- Labour cost is calculated as the number of quota labour workdays in the estimate and budget quotas multiplied by the all-in daily labour rate; the labour cost standard is determined through comprehensive analysis of wage statistics for highway works construction projects in the region and of the highway construction labour market; the daily labour rate is formulated and published by the provincial transport authority and adjusted dynamically in due course. The daily labour rate serves only as the basis for compiling estimates and budgets, not as the basis for wages actually paid by construction contractors.
- Labour in the highway estimate (budget) quotas is priced at a single all-in daily labour rate without distinguishing trades: all labour used in highway works construction (general labourers, concrete workers, steel fixers, carpenters, counterweight workers, stressing workers, tunnel-face excavation workers, traffic engineering installers, plant operators, etc.) takes the same all-in daily labour rate.
- The all-in daily labour rate already includes the old-age, unemployment and medical insurance contributions (excluding maternity insurance) and the housing provident fund paid by the individual; working time is taken as 8 h outside tunnels, 7 h in tunnels and 6 h for diving work, which differs from the actual working hours of the highway construction labour market.
- The all-in daily labour rate differs from the market price of construction labour on highway projects.
Basis distinction (easily confused in budgeting):
- "Norm-based labour cost" (basis to which percentage rates are applied) = norm-based labour consumption x base daily labour rate, calculated according to the base prices in Appendix IV "Table of unit prices of norm-based labour, materials and equipment" of the "Highway Works Budget Quota Manual" JTG/T 3832-2018 and the current "Plant Rate Norms per Machine-Shift for Highway Works" JTG/T 3833; norm-based direct cost = norm-based labour cost + norm-based material cost + norm-based construction plant cost, and is the basis to which percentage rates are applied for preliminaries, overheads (company and site), site transfer fee and other charges.
- "Labour cost" (compilation-period pricing basis) = number of quota labour workdays x all-in daily labour rate (provincially published), used for estimate and budget pricing and for charges calculated on the basis of labour cost, such as statutory fees.
- The two differ in rate source and in use, and must not be mixed in compilation.
Applicable Boundaries
- Applies to the compilation of estimates and budgets for highway works construction projects (JTG 3830-2018); the same basis applies at the feasibility-stage cost estimate stage (JTG 3820-2018).
- The daily labour rate is a provincially published regional price that varies from province to province; the rate published by the provincial transport authority of the project location prevails. This card does not address any specific rate values.
- The daily labour rate serves only as the basis for compiling estimates and budgets and does not apply to wages actually paid by construction contractors, labour subcontract final accounts or other pricing of actual labour use.
- The three-class composition of wage-related costs is a general rule, applicable to all types of highway works compiled under the 2018 quota system (JTG/T 3831 estimate quota, JTG/T 3832 budget quota, JTG/T 3833 plant rate norms per machine-shift).
Further Reading
- See JTG 3830-2018: Clause 3.1.1 (composition of the cost of works (construction and installation), definition of norm-based direct cost) and Clause 3.1.2 (labour cost and material cost notes).
- Norm-based labour, material and equipment unit prices: Appendix IV "Table of unit prices of norm-based labour, materials and equipment" of the "Highway Works Budget Quota Manual" JTG/T 3832-2018; base plant shift prices: JTG/T 3833.
- Feasibility-stage cost estimate basis: JTG 3820-2018.
- Related basis analysis: statutory fees are calculated on the base of "the sum of labour costs of all types of works" (Clause 3.1.8, at the compilation-period all-in daily labour rate), whereas norm-based direct cost, preliminaries and overheads (company and site) are calculated on the base of "norm-based labour cost" — see the statutory-fee base and cost-composition cards in this card's reference chain.