Publication and dynamic adjustment of the labour workday rate (all-in daily labour rate) under the 2018 highway quota system: set and published by the provincial transport authority (JTG 3830-2018, Clause 3.1.2)

Per Clause 3.1.2, item 1 of JTG 3830-2018, labour cost in highway estimates (budgets) = labour workdays from the estimate/budget quota norms x the all-in daily labour rate; "the labour workday rate is set and published by the provincial transport authority and dynamically adjusted in due course", serving only as a basis for compiling estimates and budgets, not as a basis for the wages actually paid by contractors. The all-in daily labour rate is not differentiated by trade and already includes the individual's pension, unemployment and medical (excluding maternity) insurance contributions and housing fund; it differs from the labour market price in the working-hour basis (8 h/day, 7 h for tunnels, 6 h for diving), the enterprise's four insurances and one fund, and winter/rainy/night allowances — the two must not be mixed. It must also be distinguished from the "norm-based labour cost" computed at the base prices in Appendix IV of JTG/T 3832-2018 (used for the norm-based direct cost and for the bases to which percentage rates are applied).

Applicable Codes

  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.2条、第2.1.1条、第3.1.1条、第3.1.8条
  • JTG/T 3832—2018 · Budget Quota of Highway Engineering 附录四'定额人工、材料、设备单价表'
  • JTG/T 3833 · Quota for Shift Costs of Highway Engineering Machinery
  • 交通运输部公告第86号(2018年发布,2019-05-01起施行)

Topic Positioning

This card answers, under the 2018 highway quota system (JTG 3830-2018): "who sets and publishes the labour workday rate (all-in daily labour rate), how it is adjusted, what it includes, and how it differs from the labour market price" — foundational knowledge for taking labour rates in highway estimates (budgets) and distinguishing the different pricing bases.

Core Conclusions

(1) Publisher and basis (Clause 3.1.2, item 1, verbatim): "The labour cost standard is determined by comprehensive analysis of the wage statistics of highway projects in the region and of the highway construction labour market, so as to determine the labour workday rate. The labour workday rate is set and published by the provincial transport authority and dynamically adjusted in due course. The labour workday rate serves only as a basis for compiling estimates and budgets, not as a basis for the wages actually paid by contractors." (2) Method: labour cost = labour workdays from the estimate/budget quota norms x the all-in daily labour rate. (3) Adjustment mechanism: the administrative compilation rules only provide for "dynamic adjustment in due course" — no fixed cycle; each province issues its own adjustment documents according to local wage statistics and labour market changes (in practice mostly annually or as required); estimates (budgets) compute labour, material and plant costs at the labour workday rate for the project location at the time of compilation (Clause 2.1.1). (4) Scope of the all-in daily labour rate (notes to Clause 3.1.2): (1) no trade differentiation — all highway construction labour (e.g. labourers, concrete workers, steel fixers, carpenters, riggers, post-tensioning workers, tunnel face excavation workers, traffic engineering installers, plant operators) uses the same all-in daily labour rate; (2) it already includes the old-age, unemployment and medical insurance contributions (maternity insurance excluded) and the housing fund payable by the individual, while the "four insurances and one fund" (social insurance contributions and housing fund) payable by the enterprise is calculated separately when compiling estimates (budgets); (3) it differs from the labour market price for highway construction — the all-in daily labour rate is normally based on 8 working hours per day, 7 hours for tunnels and 6 hours for divers, and winter, rainy and night working allowances, site relocation, heating subsidy, staple-food subsidy and home-visit travel expenses are calculated separately, whereas market labour prices generally include the above items and use a different working-hour basis. (5) Distinction from "norm-based labour cost": norm-based labour cost is computed at the base labour workday rates set out in Appendix IV "unit price table of norm labour, materials and equipment" of the Highway Works Budget Quota Manual (JTG/T 3832-2018) (norm labour consumption x base price), and is used for the norm-based direct cost and for the bases to which percentage rates are applied for preliminaries, overheads (company and site) and profit — it is locked to the quota norms and does not fluctuate with the provincially published rates; only the compilation-period labour cost (the labour cost within direct cost and the base for statutory levies and fees) uses the provincially published all-in daily labour rate. The two bases serve different pricing chains, appear separately in the budget schedules, and are not interchangeable.

Applicable Boundaries

  • Applies to the compilation of estimates and budgets for highway construction projects (JTG 3830-2018); not applicable to railways (TB 10801-2024, where the composite labour rate follows TB 10811), building/municipal works (GB/T 50500 — pricing on a bill of quantities basis) or other sectors.
  • The all-in daily labour rate "serves only as a basis for compiling estimates and budgets, not as a basis for the wages actually paid by contractors" — it must not be used to judge actual wage levels, nor may wages be reimbursed on an actual-cost basis against payrolls.
  • Specific rate values vary by province and date of publication; when compiling a highway budget for a province, the rate in the latest document published by that province's transport authority must be used; this card gives no rate figures for any province.
  • Risk of mixing bases: the base for statutory levies and fees and the labour cost within direct cost use the all-in daily labour rate (compilation-period labour cost); the norm-based direct cost and the bases for preliminaries / overheads (company and site) / profit use the Appendix IV base prices (norm-based labour cost) — mixing them produces incorrect amounts.

Further Reading

  • JTG 3830-2018, Administrative Compilation Rules for Estimates and Budgets of Highway Construction Projects, Clause 3.1.2 (labour and material cost bases, including the three notes on the all-in daily labour rate), Clause 2.1.1 (labour, material and plant costs computed at the labour workday rate for the project location at the time of compilation), Clause 3.1.1 (definitions of norm-based labour cost / norm-based direct cost / norm-based cost of works (construction and installation) computed at base prices), Clause 3.1.8 (statutory levies and fees based on the sum of labour costs of all classes of works).
  • Companion quota manuals: Highway Works Budget Quota Manual (JTG/T 3832-2018), Appendix IV "unit price table of norm labour, materials and equipment" (base labour workday rate, material base prices, equipment base prices); Highway Works Plant Rate per Machine-Shift Norms (JTG/T 3833); Highway Works Preliminary Estimate Quota (JTG/T 3831).
  • The 2018 highway quota set was issued by the Ministry of Transport under Announcement No. 86 and took effect on 1 May 2019.
  • Related bases compared: all-in daily labour rate vs norm-based labour cost vs labour market price — see the cards on the base for statutory levies and fees and on norm-based labour cost / actual wages; there is no .gov.cn official source URL in this evidence — the original text can be verified through the official channel by which the Ministry of Transport issued JTG 3830-2018.