Determining labour cost in the all-in unit rate: the two-step "norm resource consumption × labour unit price" method and its standard basis
Labour cost in the all-in unit rate is determined in two steps as "norm labour consumption × labour unit price": consumption is taken from the budget quota line item (GB/T 51095-2015 Clause 5.3.9); the unit rate follows the priority "contract agreement -> published price information (government guidance prices) from the cost administration agency -> market price", taking prices of the report compilation period (Clause 7.4.2). Where dayworks has no applicable unit rate, determine it per GB/T 50500-2024 Clause 8.6.3 using tax-exclusive published price information (government guidance prices) or purchase unit prices confirmed by both parties; the railway industry, per TB 10801-2024 Section 3.1, lists labour cost by comprehensive labour unit rate and carries the compilation-period-to-base-period difference as a labour cost differential. The all-in unit rate excludes VAT.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9、8.6.3条
- GB/T 51095-2015 建设工程造价咨询规范 第5.3.9、7.4.2条
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.1节
- TB 10811 铁路基本建设工程设计概(预)算费用定额
- GB/T 50875-2013 工程造价术语标准 第2.2.58条
Topic Positioning
How to determine labour cost in the all-in unit rate: the core formula "labour cost = Σ(norm labour consumption × labour unit price)", the unit rate selection priority, and the dayworks and railway industry basis.
Core Conclusions
(1) Labour cost = Σ(norm labour consumption × labour unit price): consumption is taken from the labour/material/machine element consumptions of the budget quota line item, and the unit price from market prices of the report compilation period (GB/T 51095-2015 Clause 5.3.9). (2) Determine/adjust labour cost by the priority "contract agreement -> published price information (government guidance prices) from the cost administration agency -> market price" (Clause 7.4.2). (3) Dayworks without an applicable unit rate: first follow the source of price information agreed in the contract; absent agreement, use the [tax-exclusive] labour published price information (government guidance prices) issued by the cost administration department and the unit rate analysis details of similar BOQ items; if still unavailable, use the purchase unit price confirmed by both parties (GB/T 50500-2024 Clause 8.6.3). (4) The all-in unit rate contains labour/material/machine costs, management fee, profit, and agreed risk, excluding VAT; under the 2024 edition, statutory levies and fees are apportioned into the labour unit price and the management fee percentage rate.
Applicable Boundaries
Applies to all-in unit rate build-up and review in building and installation works. The railway industry follows TB 10801-2024 Section 3.1: labour cost = Σ(norm resource consumption × comprehensive labour unit rate); the comprehensive labour rate covers wages, allowances and subsidies, auxiliary wages, welfare, labour protection, the five insurances and one fund, and union and vocational education funds, with unit rates per TB 10811, and the compilation-period-to-base-period difference carried as a labour cost differential. Construction-period price adjustment (for fluctuation) follows GB/T 50500-2024 Section 8.7.
Further Reading
GB/T 50500-2024 Clauses 2.0.9 and 8.6.3; GB/T 51095-2015 Clauses 5.3.9 and 7.4.2; TB 10801-2024 Section 3.1 with the companion TB 10811; terminology: GB/T 50875-2013 Clause 2.2.58.