Determining labour consumption in quota norms: composition, time-study methods and data-processing flow
Labour consumption in quota norms = basic labour + auxiliary labour + excess-haul labour (on-site small handling) + labour margin allowance (GB/T 50875-2013 simplifies this to basic labour + other labour; railway TB/T 10821-2024 uses basic + auxiliary + on-site small handling, without a separate margin allowance). It is determined on site by the realistic-work-record analysis method / chronometry, then processed through gross-error rejection -> adjustment coefficients -> random-error treatment -> computation of basic work time per unit product -> addition of other work times, converted at 8 hours per workday, and expressed as composite labour classes I/II/III.
Applicable Codes
- GB/T 50875-2013 工程造价术语标准
- GB/T 50851-2013 建设工程人工材料设备机械数据标准
- DB11/T 2382-2024 建设工程施工消耗量标准
- TB/T 10821-2024 铁路工程基本定额
- T/CSCS 035-2023 膜结构工程消耗量标准
Topic Positioning
This card explains "how labour consumption in quota norms is determined": labour composition, determination methods (realistic-work-record analysis / chronometry), the data-processing flow and the workday basis — for understanding, computing and reviewing labour consumption in quota norms.
Core Conclusions
- Composition: basic + auxiliary + excess-haul (on-site small handling) + margin allowance. GB/T 50875-2013 simplifies this to "basic + other"; railway TB/T 10821-2024 uses basic + auxiliary + on-site small handling (within 50 m; for factory-produced itemized works, within the temporary site station), without a separate margin allowance.
- Determination: field observation by the realistic-work-record analysis method and chronometry; beforehand collect drawings, the project execution plan (construction methodology and site organization), construction methods, schemes, plant matching, trade-skill grade ratios, and geological/hydrological/climatic conditions; data are organized at three levels — measurement item, method, and work item.
- Processing: classified summary -> gross-error rejection (incl. chronometric observation-count checks) -> level-assessment adjustment coefficients -> random-error treatment -> basic work time per unit product -> add other work times to obtain the consumption.
- Bases: 8 hours per workday; expressed as composite labour classes I, II and III according to trade and the unskilled/skilled/highly-skilled ratio; the unit labour-time norm includes basic, auxiliary, preparation-and-ending, unavoidable-interruption and rest time.
Applicable Boundaries
Applies to budget, preliminary estimate and construction quota norms and to enterprise consumption databases; the bases differ across standards. Excludes labour unit prices and material/plant consumption; actual on-site labour (overtime, idle time, rework) is not the labour consumption in quota norms.
Further Reading
GB/T 50875-2013 section 2.3; GB/T 50851-2013 clause 2.0.4; DB11/T 2382-2024 section 3.2; TB/T 10821-2024 general notes; T/CSCS 035-2023.