labour consumption
- 01
Composition and determination of the work content of quota sub-items / BOQ items: main processes + auxiliary content included by default, under "unlisted not separately counted, auxiliary must be included, processes not split"
The work content of a quota sub-item = the listed main construction proc…
GB/T 50860-2024 构筑物工程工程量计算标准GB/T 50857-2024 市政工程工程量计算标准GB 50860-2013 构筑物工程工程量计算规范2026-09-25 - 02
Preparing supplementary quota items (supplementary unit-rate build-up schedules): trigger conditions, consumption measurement, base price composition, industry approval, and distinction from supplementary BOQ items
Where the budget quota norms do not cover a work item and no similar sub…
GB/T 51095-2015 建设工程造价咨询规范DL/T 5468-2013 输变电工程施工图预算编制导则DL/T 5591-2021 配电网工程建设预算编制导则2026-09-25 - 03
Determining labour consumption in quota norms: composition, time-study methods and data-processing flow
Labour consumption in quota norms = basic labour + auxiliary labour + ex…
GB/T 50875-2013 工程造价术语标准GB/T 50851-2013 建设工程人工材料设备机械数据标准DB11/T 2382-2024 建设工程施工消耗量标准2026-09-25