Preparing supplementary quota items (supplementary unit-rate build-up schedules): trigger conditions, consumption measurement, base price composition, industry approval, and distinction from supplementary BOQ items

Where the budget quota norms do not cover a work item and no similar sub-item can be applied, prepare a supplementary unit-rate build-up schedule per the compilation principles and methods of the budget quota norms (supplementation is the last resort — prefer adjusted application of existing quotas or similar quota items first; the power industry requires approval by the quota administration; railway supplementary unit-price analyses are copied to the industry standards administration, and passenger station buildings etc. may adopt provincial local quota norms instead). Labour consumption = basic labour + extra-haulage labour + auxiliary labour + labour margin, measured by work-study recording / time measurement; materials = net quantity × (1 + wastage rate), turnover materials by amortized quantity; base price = labour cost + material cost + machinery cost, with management fee, profit, statutory levies and fees, and taxes added for the all-in unit rate. A missing BOQ item is a listing-level matter: supplementary item codes use the standard code + B + three digits (e.g., from 07B001) and are filed with the provincial administration.

Applicable Codes

  • GB/T 51095-2015 建设工程造价咨询规范
  • DL/T 5468-2013 输变电工程施工图预算编制导则
  • DL/T 5591-2021 配电网工程建设预算编制导则
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
  • DB11/T 2382-2024 建设工程施工消耗量标准
  • GB 50860-2013 构筑物工程工程量计算规范
  • GB/T 50875-2013 工程造价术语标准

Topic Positioning

The complete workflow for preparing a supplementary quota item (supplementary unit-rate build-up schedule) where the budget quota norms do not cover a work item: trigger conditions and priority, compilation principles, measurement of labour/material/machinery consumption, base price and all-in unit rate composition, industry approval procedures, and the distinction from supplementary BOQ items.

Core Conclusions

① Trigger and priority: prepare a supplementary unit-rate build-up schedule only where the budget quota norms do not cover the item (GB/T 51095-2015 Clause 5.3.12). Supplementation is the last resort — first apply existing quotas adjusted for technical-condition differences, then apply similar-process quotas (the power industry prefers power quotas → other industry or local quotas, DL/T 5591-2021 Clause 4.1.10), compile from construction-drawing based budgets (pre-tender estimates) / settlement data of similar works, and only where no data exist compile per the works' specific technical conditions — in all cases per the quota compilation administration provisions and subject to approval by the industry quota administration (DL/T 5468-2013 Clause 4.1.4). ② Compilation principles: follow the budget quota norms' principles and methods (normal construction conditions, reasonable project execution plan (construction methodology and site organization)); item division, work content, and units of measurement consistent with the same volume; deliverable is the supplementary unit-rate build-up schedule (GB/T 51095-2015 Appendix C, Table C.0.11). ③ Labour consumption = basic labour + extra-haulage labour + auxiliary labour + labour margin, on the 8-hour workday, collected on site by work-study recording / time measurement, finalized after gross-error identification, adjustment coefficients, and random-error treatment (DB11/T 2382-2024 Clause 3.2). ④ Material consumption: main/auxiliary materials = net quantity × (1 + wastage rate), wastage covering transport, processing, operation, and storage losses (DB11/T 2382-2024 Clause 3.3); turnover materials by amortized quantity; incidental materials as a percentage of material cost. ⑤ Base price = labour cost + material cost + machinery cost; the all-in unit rate additionally includes management fee, profit, statutory levies and fees, and taxes (GB/T 51095-2015 Clause 5.3.9).

Applicable Boundaries

Applies to consumption measurement of conventional-process items not covered by the budget / preliminary estimate quota norms; where existing quotas can be applied with adjustment, do not supplement (adjust and apply first); consumption must be supported by field measurement or reliable data — experience-based guesses are not acceptable. Railway specifics: passenger station buildings, station complexes, canopies, and footbridges may adopt the provincial local quota norms of the works location, with labour/material/machinery prices and norms for on-costs and expenses adopted in matching sets (TB 10801-2024 Clause 2.4.2); railway supplementary unit-price analyses are copied to the industry standards administration (Clause 2.4.3). Note the distinction: a missing BOQ item is a listing-level matter — supplementary items are coded as standard code + B + three digits (structures from 07B001, no duplicate codes), with name, item description (work item specification), unit of measurement, method of measurement, and work content attached, filed with the provincial or industry cost administration (GB 50860-2013 Clause 4.1.3) — not the same thing as a supplementary quota item at the rate build-up level.

Further Reading

See GB/T 51095-2015 Clauses 5.3.12, 5.3.9 and Appendix C Table C.0.11; GB/T 50875-2013 Section 2.3 (labour/material consumption definitions); DL/T 5468-2013 Clauses 4.1.4, 4.1.12; DL/T 5591-2021 Clause 4.1.10; DB11/T 2382-2024 Clauses 3.2, 3.3; TB 10801-2024 Section 2.4; GB 50860-2013 Clause 4.1.3.