Selecting quota items for TDF (integral thin-sheet-steel flange) ducts and treating the fabrication part: dedicated items first, borrowing and conversion rules where none exist, the main-material treatment of corner clips and spring clips, and the cost-gap make-up against angle-steel flanges

TDF ducts take the dedicated 'TDF duct fabrication and erection' items first (DB11/T 2382-2024 Table C.7.16, C7-2-87~C7-2-91, per m2, work content already including 'fitting corner clips and spring clips', fabrication and erection in one) - the fabrication part is never borrowed out. Systems without dedicated items run the like flanged-duct items per the volume notes (SJG 111.3-2022 clause 4.1.7 note 8: 'where flange-less connection items are used, no adjustment'), never self-applied experience factors; conversion factors come only from the notes' express text (tapered uniform-supply ducts labour x 2.50, air-curtain ducts labour x 3.00, curved ducts labour and materials x 1.12); true gaps borrow from similar processes with a paper trail or compile supplementary unit-rate build-up schedules for approval. Ducts, valves, diffusers and other main materials list in brackets, never as the base of sundry-material rates.

Applicable Codes

  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第6.7节、App. C Table C.7.16、Table 6.7.27
  • GB 50243-2016 · Code for Acceptance of Construction Quality of Ventilation and Air Conditioning Works 第4.3.1条
  • JGJ/T 141-2017《通风管道技术规程》第3.2.2、3.2.3、4.4.3条
  • DB11/T 1832.15-2022《建筑工程施工工艺规程 第15部分:通风与空调安装工程》第3.5.4条
  • GB/T 50856-2024 · Standard for measurement of general mechanical, electrical, plumbing and fire services App. G Table G.2.1
  • SJG 111.3-2022 · Consumption Standard for Urban Utility Tunnel Works (Volume 3) (Shenzhen) 第4.1.7条

Positioning

Fixing the identity and item selection of TDF ducts (the code term is 'rectangular thin-sheet-steel flange duct') in quota rate build-up: which item the fabrication part takes, whether bite-seam or angle-flange items may be borrowed, how the connectors price, and where the cost gap against angle-steel flanges comes from.

Core conclusions

1. Identity and process

  • Construction: the galvanised sheet is cut and seamed while both ends fold out the flange edge - flange and body are one sheet; corners join with corner clips (angle inserts), the flange face carries sealing gasket strip, and spring clips / set-screw fasteners / slip-on cleats lock it - no independent angle-steel flange sections exist.
  • The codes class it as 'metal flange-less ductwork': GB 50243-2016 clause 4.3.1 item 2 - 'interfaces and accessories of rectangular thin-sheet-steel flange ducts shall be accurate in size, regular in shape and tight; the folded flange edge shall be straight with curvature no more than 5 per mille ... for spring-clip connected ducts the side length should not exceed 1500mm; with due stiffening, not more than 2000mm'; the commentary adds 'thin-sheet-steel flange ducts shall not serve high-pressure ducts'.
  • Process: JGJ/T 141-2017 clause 3.2.3 - 'thin-sheet-steel flanges shall be machine-formed; folded edges or combined flange strips shall be straight, curvature no more than 5 per mille ... spring clips preferably 120mm~150mm long'; clause 4.4.3 - 'elastic inserts, spring clips or bolts shall be evenly spread, tight, spaced no more than 150mm, the outermost fastener no more than 100mm from the duct edge'. DB11/T 1832.15-2022 clause 3.5.4 adds 'spring-clip thickness shall be at least 1mm and not less than the duct body' and bars such ducts from high-pressure service.
  • BOQ side: GB/T 50856-2024 Appendix G Table G.2.1 note 6 - 'duct items include fabrication and erection of supports and hangers'; the item description must state the connection form (TDF / integral flange) - it drives the quota banding and settlement reconciliation.

2. Three item-selection bases

Base A (first choice): dedicated TDF items exist - apply them; fabrication is never borrowed out. DB11/T 2382-2024 Table C.7.16 'galvanised thin-sheet TDF rectangular duct fabrication and erection', banded by longest side, per m2, fabrication and erection in one: C7-2-87 (side up to 320), C7-2-88 (450), C7-2-89 (630), C7-2-90 (1000), C7-2-91 (1500). Work content verbatim: '1) Fabrication: checking plant, loading, program input, ribbing, cutting, seaming rolls, folding, lock seaming, fitting corner clips, assembly, tie-rod internal stiffening, sealant, making hangers; 2) Erection: site haulage, finding levels, expansion bolts, hanging supports, assembly, setting ducts, levelling and truing, gasket strips, spring clips, bolts, tightening, tightness testing.' Edge folding, corner clips and spring clips are all inside - no other duct item is borrowed for fabrication. The bands top out at 1500mm, matching the code's spring-clip limit (no 2000mm stiffened band is set).

Base B: no dedicated items - run the like (flanged) duct items per the volume notes; notes over experience. SJG 111.3-2022 clause 4.1.7 note 8 verbatim: 'The duct fabrication and erection items list flanged connection only; where flange-less connection items are used, no adjustment.' - i.e. the like-size flanged items apply with no factor; note 3: 'the thin-sheet duct items include bends, tees, reducers and square-to-rounds with their flanges, stiffening frames and hangers (flanges / frames versus hangers at a 7:3 share), excluding floor-standing spans supports' - none of that re-charges on borrowing. Note: some regions list 'TDF ducts' and 'thin-sheet flange ducts (combined flange strips)' as two classes - the two never intermix.

Base C: angle-flange items x conversion factors - never a routine practice. Conversion runs only 'where the notes say so'. DB11/T 2382-2024 clause 6.7.28 gives three express factors: 'tapered uniform-supply ducts take the duct items at average diameter or longest side with labour x 2.50; air-curtain ducts take rectangular items at average longest side with labour x 3.00; curved ducts take the duct items with labour and materials x 1.12.' Beyond such text, self-chosen factors folding angle-flange items into TDF are unsupported conversions; on true gaps, borrow from the similar process with a paper trail or compile a supplementary schedule for the quota authority's approval.

3. Splitting 'fabrication only': the ratio basis

DB11/T 2382-2024 Table 6.7.27 duct labour / material / plant ratios: galvanised TDF rectangular ducts - labour fabrication 40% / erection 60%, materials 70% / 30%, plant 95% / 5%; stainless ducts - labour 72% / 28%, materials 95% / 5%, plant 95% / 5%. Listing 'fabrication' alone splits on these ratios - far better grounded than experience factors.

4. Corner clips and spring clips: main-material treatment

Clause 6.7.3 verbatim: 'Main materials of the ventilation works - ducts, valves, diffusers etc. - enter consumption in bracketed form and never form the base of sundry material rates.' So duct main materials (galvanised sheet and the clip, spring-clip and gasket connectors supplied with the duct) list as braced (unpriced) materials: the item carries quantity only, prices computed separately into main-material cost, never the base of the item's 2% sundry-material rate. Sheet consumption is 1.18 m2 per m2 of duct (seaming and folding waste included), equal across bands; timber pads on hangers are inside the hanger work content but 'pad consumption computes separately' (work content item 2).

5. The cost gap against angle-flange ducts (steel content and labour)

  • Steel: TDF drops the independent angle-steel flange and its fabrication; steel falls to 'hangers plus tie-rod stiffening'. Beijing TDF items run 1.5~3 kg/m2 of sections: up to 450 - angles and channels about 3.1 kg/m2; up to 1000 - channel 16 at 1.5287 kg/m2, flats 0.29, angles 0.60 (some material-table names and units are misaligned - e.g. angles marked 'piece'; verify against the original tables). Like-size angle-flange ducts need independent flanges with cutting, pairing, welding and drilling (riveted fold no less than 6mm; flange bolt holes interchangeable) - markedly more steel and labour.
  • Labour: all-in labour II runs 0.465 workdays/m2 at 320, 0.340 at 450, 0.306 at 630, 0.267 at 1000, 0.299 at 1500 (non-monotonic - machine forming versus hoisting difficulty).
  • Plant: 400A plasma cutters, folders and seamers about 0.0167~0.0361 machine-shifts per band; 'other plant' at 3%.
  • The price of it: clip and spring-clip connectors (main materials apart) and flange stiffening (sides 1500~2000mm need tie rods / steel straps).

Applicable boundaries

  • Rectangular galvanised TDF ducts only; never high-pressure ducts (GB 50243-2016 clause 4.3.1 commentary; DB11/T 1832.15-2022 clause 3.5.4); spring-clip sides preferably up to 1500mm, 2000mm stiffened.
  • Match items by longest side; never band upwards; duct quantities by developed area on design internal dimensions, no deduction for inspection, measuring or supply / return openings (clauses 6.7.29-6.7.30).
  • Duct items exclude derusting and painting (separate items; SJG 111.3-2022 clause 4.1.7 note 1); the three factors serve only their listed cases - no analogy.
  • This card holds no full consumption of the like angle-flange items: the gap is compositional and qualitative, not a substitute for actual rate comparison; cross-region use checks the local volume's notes and items first.
  • Erection above 6m runs the height allowance of clause 6.1.2; foundation pours follow the building volume and grouting the mechanical-equipment volume (clauses 6.7.1-6.7.2).

Further reading

  • DB11/T 2382-2024 clause set 6.7 (ventilation and air-conditioning) with Appendix C Table C.7.16 items C7-2-87~C7-2-91 and Table 6.7.27 ratios.
  • GB 50243-2016 clause 4.3.1 and commentary; JGJ/T 141-2017 clauses 3.2.2, 3.2.3, 4.4.3; DB11/T 1832.15-2022 clause 3.5.4.
  • GB/T 50856-2024 Appendix G Table G.2.1 duct notes; SJG 111.3-2022 clause 4.1.7 notes (flange-less unadjusted; 7:3 share; factor 2.50).

Keywords

  • 共板法兰
  • TDF
  • 薄钢板法兰风管
  • 无法兰连接
  • 风管制作安装子目
  • 角码弹簧夹
  • 表C.7.16
  • 定额换算系数