Quantity take-off (measurement) and pricing rules for pipeline supports/hangers and seismic braces (GB/T 50856-2024 listing + GB 50981-2014 installation)
The fabrication, installation, and painting of ordinary pipeline supports, hangers, and base channel steel are already included in the work content of pipeline installation items (GB/T 50856-2024 Clause 3.0.10) and are generally not listed separately; where there are special design requirements they are listed under Appendix N (031301) — prefabricated supports per set, supports/hangers and base channel steel per kg. Seismic braces must be listed separately under the prefabricated-support item code, counted per set, with installation quantities per GB 50981-2014 Chapter 8: transverse braces at both ends of each horizontal straight pipe segment and at least one longitudinal, transverse braces within 0.6 m at bends, spacing l = l0·αEk·k (half for renovation works).
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准
- GB 50981-2014 建筑机电工程抗震设计规范
- DB22/T 5138-2023 建筑机电管线工程抗震支吊架技术标准
- TB/T 10832-2024 铁路工程预算定额 Vol. 11
- DB11T 2382-2024 建设工程施工消耗量标准
Topic Positioning
The quantity take-off (measurement) and pricing rules for supports, hangers, and seismic braces of pipelines (water supply and drainage, heating, gas, etc.): when they merge into the all-in unit rate for pipeline installation and when they are listed separately, plus the installation rules and spacing formula of seismic braces.
Core Conclusions
Ordinary supports and hangers: per GB/T 50856-2024 Standard for Measurement of General Installation Works Quantities Clause 3.0.10, the work content of equipment, pipeline, and accessory installation items includes the fabrication, installation, and painting of supports, hangers, and base channel steel — generally not listed separately, the cost being contained in the all-in unit rate for pipeline installation; never double counting. Where there are special design requirements, list separately under Appendix N (code 031301): prefabricated supports counted per "set" (per the design quantities), supports/hangers and base channel steel per kg (mass computed per design dimensions); anti-corrosion painting is listed under Appendix M. Seismic braces: per Appendix N "seismic braces are listed under the prefabricated-support item codes", counted per set per the design quantities, and must not be merged into pipeline installation costs. Installation rules (GB 50981-2014 Chapter 8, mandatory provisions): each horizontal straight pipe segment has transverse seismic supports at both ends and at least one longitudinal, added in sequence beyond the maximum design spacing; within 0.6 m of bends, a transverse brace is provided (a diagonal acting directly on the pipeline may count as a longitudinal support on the other side). Spacing is calculated as l = l0·αEk·k, where l0 is the maximum spacing per Table 8.2.3, half for renovation works; αEk is the combined horizontal seismic force coefficient (taken as 1.0 when less than 1.0); k is the diagonal-angle adjustment coefficient (vertical/horizontal ratio 1.0 → 1.00, ≤1.5 → 1.67, ≤2.0 → 2.33). Pricing is per set; the main material, prefabricated seismic braces, includes anchors and undercut anchors.
Applicable Boundaries
Applies to building water supply/drainage/heating/gas pipeline works listed per GB/T 50856-2024 and seismically designed per GB 50981-2014; Jilin and other provinces execute DB22/T 5138-2023 with installation rules consistent with the national standard. The number of seismic braces depends on the seismic design documents (layout drawings) — obtain the design layout before pricing; specific consumption items and labour coefficients follow the current local quota of the project, with slight regional differences.
Further Reading
GB/T 50856-2024 Clause 3.0.10, Appendix N Tables N.1.1 and N.2.3 (seismic braces listed as prefabricated supports); GB 50981-2014 Code for Seismic Design of Building MEP Engineering, Clauses 8.2.3, 8.3.1, 8.3.3, 8.3.6; Jilin DB22/T 5138-2023 Technical Standard for Seismic Supports and Hangers of Building MEP Pipelines, Section 5.7; railway TB/T 10832-2024 Volume 11 Water Supply and Drainage Works pipeline support fabrication and installation quota (ordinary/cushion/spring supports listed separately); Beijing DB11T 2382-2024 prefabricated seismic support installation quota (transverse-longitudinal supports execute transverse items with labour coefficients).
Keywords
- 抗震支架
- 抗震支吊架
- 管道支架
- 吊架
- 成品支架
- GB 50981
- GB/T 50856
- 侧向抗震支架
- 纵向抗震支架
Related Cards
Cited By
- ←
Quota conventions for pipe supports and hangers (general supports, sliding/guiding/anchoring seats) calculated separately by design mass in kg: fabrication and installation items set apart, timber-padded and spring types merged in, outdoor above-ground structural-steel supports switched to the static equipment and process metal structures volume, sources of support spacing values (GB 50242-2002, DB11/T 1832.14-2022), and the double-counting boundary against the bill convention (GB/T 50856-2024 clause 3.0.10, supports already included)
Pipe-laying items exclude supports; supports are calculated separately by design mass in kg: Beijing DB11/T 2382-2024 appendix C sets C10-4-1 'fabrication, general pipe support' and C10-4-2 'installation, general pipe support' (both per 100 kg; the fabrication item carries 105 kg of section steel per 100 kg) - fabrication and installation must be applied as separate items; timber-padded and spring supports run the same items, with anti-corrosion timber pads and spring vibration isolators as main materials added; indoor supports and supports inside outdoor pipe trenches run the piping-volume support items, while above-ground structural-steel supports for outdoor pipes switch to appendix C.3, the static equipment and process metal structures volume (the most frequent mis-application on overhead works); support counts follow the maximum spacings of GB 50242-2002 table 3.3.8 and the anchor-support spacings and free-end lengths of DB11/T 1832.14-2022 tables 2.0.19-1 and 2.0.19-2, then weigh group by group off the standard drawings; under the bill convention (GB/T 50856-2024 clause 3.0.10) the work content already includes support fabrication, installation and painting - no separate bill item without a special design requirement.
- ←
BOQ classification under GB/T 50856-2024 of power cable earthing, handover tests and insulation checking: termination earthing included in the termination installation itself, cables (wires) used as earth conductors billed under cable installation / conduits and wiring, stand-alone lightning protection and earthing installations under 030410, tests under 030416 (electrical adjustment and testing), with the billing scope of cable installation 030409 and the boundaries drawn by the D.17 problem notes
Earthing of the metal sheath, armour or screen at cable terminations (power cable terminations, cable joints, control cable terminations) is work content of the termination installation itself ('termination earthing') - no separate BOQ item and no separate earthing item; where cables or wires serve as earth conductors, bill under the relevant item codes of Appendix D.9 cable installation and Appendix D.12 conduits and wiring; stand-alone earth electrodes, earth bars, down conductors, grading rings, air-termination tapes (meshes), air-termination rods, equipotential bonding terminal boxes, earthing bonding jumpers and the like are billed separately under 030410 (table D.10.1). Power cable tests (including insulation resistance measurement and withstand voltage tests) and earthing installation commissioning go to table D.16.1 electrical adjustment and testing (code 030416); 'insulation checking' has no stand-alone code in the BOQ, and its test items and voltage application follow GB 50150-2016 clauses 17.0.1 and 17.0.2. Within cable installation (030409), cable trays / raceways, protective conduits for cables entering buildings, and cable branch boxes are billed instead under the relevant codes of Appendix D.12 and Appendix D.5.
- ←
Selecting quota items for TDF (integral thin-sheet-steel flange) ducts and treating the fabrication part: dedicated items first, borrowing and conversion rules where none exist, the main-material treatment of corner clips and spring clips, and the cost-gap make-up against angle-steel flanges
TDF ducts take the dedicated 'TDF duct fabrication and erection' items first (DB11/T 2382-2024 Table C.7.16, C7-2-87~C7-2-91, per m2, work content already including 'fitting corner clips and spring clips', fabrication and erection in one) - the fabrication part is never borrowed out. Systems without dedicated items run the like flanged-duct items per the volume notes (SJG 111.3-2022 clause 4.1.7 note 8: 'where flange-less connection items are used, no adjustment'), never self-applied experience factors; conversion factors come only from the notes' express text (tapered uniform-supply ducts labour x 2.50, air-curtain ducts labour x 3.00, curved ducts labour and materials x 1.12); true gaps borrow from similar processes with a paper trail or compile supplementary unit-rate build-up schedules for approval. Ducts, valves, diffusers and other main materials list in brackets, never as the base of sundry-material rates.
- ←
Treatment of insulation breaks at supporting points of equipment and pipes - fixed supports, sliding / guide supports, pipe shoes, hangers: construction requirements (expansion joints, expansion clearances, insulation inserts, anti-thermal-bridge insulating blocks, riser load-bearing trays) and measurement and pricing treatment (no deduction of insulation quantity at supports, the test for separately charging insulating blocks, and the measurement split at heat-tracing crossovers)
The insulation break at pipe shoes, supports and hangers is constructional accommodation and packing blocks, not an 'uninsulated gap': insulation quantities are calculated by the volume shown on the design with the extended metres of the pipe as the base, and apart from valves and flanges (which have separate insulation items) and pipe sections expressly left uninsulated by the design, the length occupied by supports and fittings is never deducted. Rigid insulation leaves expansion joints under support rings and between fixed supports (preferably 20 mm for pipes, 25 mm for equipment) filled tight with soft material of similar thermal conductivity, and the joints and clearances are not deducted from the volume. Fixed supports are wrapped and made up as a whole and thermal bridges are cut off with insulating blocks; sliding / guide supports leave an expansion clearance on the displacement side and the insulation accommodates the movement (mandatory where the sliding support height is less than the insulation thickness); all three support types require heat-insulating measures, and load-bearing points in cold service need rigid cold-conservation blocks. Whether insulating blocks (hardwood / packing blocks) are charged separately as materials depends on the work content of the quota line item applied - where included, no separate charge is allowed; only where the quota expressly says 'main materials charged separately' may they be listed separately. At heat tracing, the insulation layer and protective covering are calculated once on the combined tracing diameter D', not measured separately and twice; heat loss checks at breaks belong to design insulation calculation and form no measurement deduction or separate charge.
- ←
Pricing boundaries of anti-vibration pedestals, equipment hangers and equipment foundations for ventilation and air-conditioning equipment: installation-side metal structure and pedestal line items, civil-side concrete foundations, and vibration isolation elements as principal materials - a three-part split and the test against double counting
Anti-vibration arrangements are priced in three parts: (1) steel pedestals, supports and hangers integral with the equipment go to the installation side (railway rule: 'fan vibration-damping pedestals may be priced under the equipment support line items, with dampers priced separately', FY-2675/FY-2676 per 100kg; Beijing DB11/T 2382-2024 has standalone vibration isolation pedestal line items C1-6-105 to C1-6-109 measured per unit by equipment weight, and the equipment support items may not be applied as well); (2) concrete equipment foundations and plinths belong to civil works and are listed separately in m3 (reinforcement and formwork priced separately), the installation side keeping only the steel base sections, shim plates and grouting; (3) vibration isolators, isolation pads and spring dampers are principal materials priced separately per piece or per group - wherever the line item work content already includes them (supports and packing supplied with the equipment, fan installation including isolator installation), they must not be counted again.
- ←
Content boundary between duct fabrication and installation line items and supports and hangers (hanging/supporting brackets), and preventing double counting: the BOQ layer 'items include supports and hangers' versus the quota layer 'volume preamble plus line-item work content', three parallel yardsticks (included / priced separately / composite duct as a complete set), the weight linkage to 100 kg support line items when priced separately, and no separate charge for stiffening
The test runs on two layers. At the BOQ layer, GB/T 50856-2024 Table G.2.1 note 6 (ventilation duct items include fabrication and installation of supports and hangers; where listed separately, itemise under Appendix N) and Clause 3.0.10. At the quota layer, the volume preamble plus the work-content column of the governing line item must be checked: railway TB/T 10831-2024 volume preamble 'the thin steel sheet and GRP ventilation duct fabrication and installation quotas include flanges, stiffening frames and hanging/supporting brackets, but exclude floor-standing frames spanning ducts (price floor-standing frames under the equipment support quota)'; Shenzhen SJG 111.3-2022 4.1.7-3 same yardstick; Beijing DB11/T 2382-2024 line item C7-2-87 work content includes making and installing hanging/supporting brackets - all fall under 'included', and supports and hangers must not be priced separately. Two further yardsticks exist: 'excluded, price support line items separately per design quantity (in kg / 100 kg)' and 'composite duct supports supplied with the complete product, installation only'. The same support or hanger may be charged once only; duct stiffening (beading / stiffening ribs / stiffening frames) is inside the fabrication line item and must not be charged again; floor-standing frames spanning ducts are the sole exception to the 'included' yardstick.
- ←
Where pipe support and hanger costs sit for water supply and drainage (heating, gas) piping, and the boundary for billing them separately: three sets of tests - the BOQ measurement criterion, the Beijing consumption standard criterion, and the diameter gates of the national unified quota and the railway quota
Support and hanger costs cannot be answered wholesale as 'included' or 'not included'; they split by criterion. Under the BOQ measurement criterion, GB/T 50856-2024 clause 3.0.10, the work content of pipe installation items already covers fabrication and erection of supports, hangers and base structural steel plus painting, so no separate item is generally listed (yet rate build-up must still load the support line items into the all-in unit rate); Beijing DB11/T 2382-2024 clauses 6.10.29 and 6.10.35 require supports, pipe clips and hooks to be billed separately under 6.10.39-6.10.42, with no diameter gate; Jing Jian Fa [2021] No. 201 (Beijing), Volume 10, chapter 2 notes item 11 states 'pipe installation does not include pipe support erection', and the 2012 edition of the same note added '(plastic pipes excepted)', which the 2021 edition deleted. The Volume 8 family formula 'DN32 and below include clips and hooks, above that billed separately' of the national unified installation quota and the railway TB/T 10831-2024 'steel pipe below DN25 includes clips and hooks' are both volume-notes-level local or sector criteria, not a national rule. Supports are measured by design-shown mass in kg (quota unit 100kg); proprietary clips and proprietary seismic supports are counted by design-shown number, and seismic supports must be listed separately under the proprietary-support item code.
- ←
Spacing limits and load-check selection of load-bearing supports for cable trays: horizontal 1.5m~3m / vertical preferably no more than 2m, three-parameter limits of strength, stiffness and stability (relative deflection 1/200 for steel, 1/300 for aluminium, steel bracket-arm deflection-to-arm-length ratio 1/100, safety factor 1.5), selecting bracket-arm and bearer sizes by tray load per metre, the duty to provide and to verify span-load curves, load superposition for stacked layers and combined supports, and the demarcation from seismic support spacing under GB 50981-2014
Load-bearing support spacing: for horizontal runs 'the optimum span should be selected from the load curve for support, and the span should be 1.5m~3m'; for vertical runs 'the spacing of fixing points should preferably not exceed 2m' (GB 51348-2019 Clause 8.5.4; GB 50054-2011 Clause 7.6.15; at the construction-acceptance level GB/T 51239-2017 Clause 9.3.7 uses 'shall'; where the design is silent GB 50397-2007 Clause 16.2.1 takes 1.5~3m / no more than 2m). Load checking follows the three parameters of GB 50217-2018 Clause 6.2.5: the load-bearing capacity must not exceed the maximum load at which the tray first suffers permanent deformation divided by the safety factor 1.5; the relative deflection under the permissible safe working load should preferably not exceed 1/200 for steel and 1/300 for aluminium; the ratio of the deflection of a steel bracket arm under permissible load to the arm length should preferably not exceed 1/100. Manufacturers should provide span-load curves, otherwise a calculation must be made (T/SHGBC 006-2022 Clause 8.5.1). Seismic support spacing is calculated separately under GB 50981-2014 Clause 8.2.3 as l = l0.aEk.k and checked separately from load-bearing support spacing; the two are not interchangeable.
- ←
Quota measurement-unit conversion and line-item splitting for fabrication and erection of supports and hangers (pipe supports / metal supports and steelwork): the three bases 100kg, kg and t; the support-quantity reference table where the design is silent; the switch to equipment supports above 50kg per assembly; and the no-double-count test where the cable tray line item already includes support and hanger erection
Quota quantity = support net weight (kg) divided by the quota unit weight: the same net weight of 100.381kg gives 1.004 under the pipe-support fabrication line item in '100kg' units, 100.381 under the metal-support fabrication line item in 'kg' units, and 0.100381 t under the railway 't' unit - conversion is division only, and wastage is already inside the item and must not be multiplied in again. Under DB11/T 2382-2024 table C.10.23-1, C10-4-1 fabrication and C10-4-2 erection of general pipe stands are per 100kg (section steel 105kg per 100kg, implying about 5% wastage), steelwork-type metal supports are per kg, and railway items such as TB/T 10832-2024 PY-365~370 are per t; where the design is silent, pipe support quantities may be taken as the kg/m reference values of table 6.10.39 x pipe length; where one assembly weighs more than 50kg, equipment-support fabrication and erection applies. The cable tray erection line item already includes support and hanger erection, so the site-fabrication route adds only the 'fabrication' item - erection must not be charged again.
- ←
Re-measurement and price adjustment rules after quantity changes caused by variations or BOQ errors: recalculating from the variation instruction and the actual construction drawings, the separate track for BOQ errors, the 15% banded unit-rate adjustment, and the scheme-approval precondition for pricing preliminaries and new preliminary items (GB/T 50500-2024 clauses 7.4.2-7.4.4, 8.2.1, 8.9.1-8.9.2; GB 50500-2013 clauses 9.3.1, 9.3.2, 9.6.2)
Re-measurement after a variation takes as its basis the quantities recalculated from 'the variation instruction issued or confirmed by the employer and the actual construction drawings', compared with the BOQ quantities after the BOQ errors have been corrected, to determine the added or deleted variation items and their quantities; differences between the contract drawings and the contract BOQ are BOQ errors (corrected under unit-rate contracts, not adjusted under lump-sum contracts). Where the quantity difference is within 15% (15% inclusive), the unit rate is set under GB/T 50500-2024 clause 8.9.1; beyond 15% (exclusive), clause 8.9.2 adjusts downward on increase and upward on decrease in light of labour and material purchase concessions (the 2013 edition corresponds to the four tiers of clause 9.3.1 and clause 9.6.2). Preliminaries adjustment requires prior submission of the proposed scheme confirmed by the employer and the contractor; failure to submit is deemed to cause no preliminaries adjustment or a waiver of the right to adjust. New preliminary items take the added temporary works and plant machine-shifts priced from the approved scheme; the added cost of extended use of existing preliminaries and supervisory staff from variations off the critical path need not be measured.
- ←
Pricing comparison method for prefabricated supports versus site-fabricated supports: precondition test of the billing itemisation basis, item-by-item comparison of cost components (principal materials / wastage / fabrication labour and plant / anti-corrosion and galvanising / installation labour), comparison of fabrication and installation quota line items, and the code-based selection rule that favours prefabrication
Prefabricated supports (billed per set) and site-fabricated supports (steel sections priced by kg through fabrication plus installation quota line items) cannot be compared directly as CNY/kg against CNY/set. The billing itemisation basis must first be tested under GB/T 50856-2024 clause 3.0.10: without a special design requirement, supports and hangers are already included in the all-in unit rate for pipe installation and must not be listed separately; with a special design requirement (Annex N, code 031301), prefabricated supports are billed per set and supports and hangers per kg, while seismic supports are always coded as prefabricated supports per set and must not be converted into kg to apply fabrication line items. The cost component differences concentrate in four points: whether the principal materials include fittings, anchors and galvanising; site fabrication labour and hot-work cutting plant; consumables such as welding materials and gases; and the anti-corrosion grade (fabrication line items include ordinary anti-rust paint plus ready-mixed paint only, and hot-dip galvanising must be priced separately).
- ←
Cable-tray support and hanger mass calculation and norm charging: count positions by spacing, unit mass from section-steel theoretical mass; Beijing 2024 "tray installation includes support installation; support fabrication listed separately per kg"
Total support mass W = sum(single length x theoretical mass); round hanger rods w = 0.00617 x d2 (kg/m), flats/plates w = 0.00785 x b x t. Under Beijing 2024: tray installation items include "support/hanger installation" (do not re-charge) but exclude fabrication — support fabrication (cutting, welding, painting) is priced separately per kg under "metal support fabrication" (C4-13-1, C4-13-2), whose work content already includes painting — do not re-charge painting.
- ←
Basis values and additional-point rules for cable tray support and hanger spacing: two layers of sources (design versus installation and acceptance), 1.5m~3m horizontal and up to 2m vertical, added support points at bends, ends, joints and section changes, the tie to span-load curves and strength, stiffness and stability checks, the supports-per-metre formula, and the comparison with lateral/longitudinal seismic support spacing
The design basis for cable tray support spacing is GB 51348-2019 clause 8.5.4: 'for horizontal runs the optimum span should be chosen from the load curve, with spans of 1.5m~3m; for vertical runs the spacing of fixing points should not exceed 2m'; the installation layout basis is GB 50606-2010 clause 4.3.2 (1.5~2.0m on straight runs, supports within 0.5m of ends, branches and bends) and DB11/T 1832.17-2021 clause 9.4.2 (support points within 500mm at entry to and exit from boxes and enclosures, corners and bends, both ends of movement joints and all three ends of T-joints). JB/T 10216 is a cable tray product standard containing no support-spacing provision and cannot be cited as the source of these values. The 1.5~3m is the top of a code range; the actual span must follow the manufacturer's span-load curve and pass the strength check (load at first permanent deformation / 1.5), the stiffness check (steel deflection no more than 1/200, aluminium no more than 1/300) and the stability check (steel bracket tilt-to-arm-length ratio no more than 1/100). Supports per metre n = 1/s (units/m); total supports on a straight run N = ceil(L/s) + 1; support weight per metre w/s.
- ←
The determination chain for when building MEP piping must have seismic supports and hangers: the overall determination by fortification intensity (GB 50981-2014 clause 1.0.4 / GB 55002-2021 clause 1.0.2), the per-system component threshold clauses (3.1.6, 4.1.2, 5.1.3, 5.1.4, 6.1.1, 7.1.2), the combined-use and substitution boundaries with load-bearing and anti-sway supports, and the exemption situations
Determination is two-step: (1) overall threshold - GB 50981-2014 clause 1.0.4 (a mandatory provision, superseded by GB 55002-2021 from 1 January 2022): 'building MEP works in areas of seismic fortification intensity 6 and above must be seismically designed'; the current basis is GB 55002-2021 clauses 1.0.2 and 5.1.12; (2) component thresholds - clause 3.1.6 sets an overall gate at 'equipment gravity over 1.8 kN / hanger rod calculated length over 300 mm', with per-system thresholds: horizontal pipes of water, hot water and fire protection piping DN65 and above (clause 4.1.2 item 3, 'shall'), gas piping of internal diameter no less than 25 mm (6.1.1, 'shall'), ducts with rectangular section no less than 0.38 m2 and circular diameter no less than 0.70 m (5.1.3 item 3, original wording 'may'), smoke control and exhaust and emergency ventilation ducts and related equipment (5.1.4, 'shall'), electrical conduits of internal diameter no less than 60 mm and cable trays, troughs and busways of gravity no less than 150 N/m (7.1.2, 'shall'). Seismic supports and hangers take seismic force as their principal load (2.1.6) and must resist seismic action from any horizontal direction (8.1.1); ordinary load-bearing supports are no substitute; where they coincide with anti-sway supports, seismic bracing alone may be provided (4.1.2 item 3), and where they coincide with gravity supports, if the seismic support can carry the gravity the seismic support alone may be used, subject to seismic verification and gravity calculation sheets (DBJ 46-059-2021 clause 8.1.5).
- ←
Beijing DB11/T 2382-2024 consumption standard: pipe supports must be computed separately with dedicated items (C10-4-1/C10-4-2 per 100kg, factory-made seismic braces per pair, factory pipe clamps per piece, industrial pipe racks C8-14-1)
Beijing DB11/T 2382-2024 sets independent items for pipe-support fabrication and installation — budgets must compute and apply them separately: general racks C10-4-1 (fabrication) / C10-4-2 (installation) per 100kg; factory seismic braces C10-4-3/C10-4-4 per "pair" (side-longitudinal braces under the transverse item, labor x 1.05; main material includes anchors and undercut anchors); factory pipe clamps C10-4-5 per "piece"; industrial pipe racks C8-14-1 per 100kg (special-shaped racks x 1.3, stainless racks x 1.1). Wood-cushion and spring racks use the corresponding pipe-support fabrication/installation items, with anti-corrosion wood cushions and spring dampers as separately priced materials; outdoor above-ground shaped-steel supports use Annex C.3.
- ←
Beijing DB11/T 2382-2024 consumption standard: quota-application method for water-tank (assembled / integral) installation - capacity banding, measurement per unit, and the treatment of accessories and peripheral works
Water-tank installation quantities shall be classified by total tank capacity and calculated by the numbers shown on the design (Clause 6.10.88), measured per "unit"; site panel assembly applies Table C.10.72-2 assembled-tank installation (work content includes panel assembly and water testing), and factory-finished whole tanks delivered to site apply Table C.10.72-1 integral-tank installation (including fitting-up of parts and the full-water test). Accessories supplied complete with the tank are included in the sub-item work content and not itemized separately; the tank body is priced as an unpriced main material/equipment; steel-section supports are executed under equipment-support fabrication and installation per Clause 6.10.41 (classified by support-group weight, calculated by the design mass in kg); control cabinets (panels) follow the electrical volume, and vibration-isolation devices follow the machinery volume.
- ←
Beijing DB11/T 2382-2024: determining chapter by chapter and material by material whether pipe installation quota line items include pipe fittings (gas piping: only galvanized steel pipe with threaded joints includes fittings; indoor water supply/drainage and heating piping include fittings)
Beijing DB11/T 2382-2024: in gas piping, only the galvanized steel pipe (threaded joints) installation items include fittings and pipe clamps (6.10.34); for welded steel pipe, PE pipe and other materials, the fittings must additionally follow the "fitting and pipe-clamp installation" items; the indoor water supply, drainage and heating piping runs the opposite way - the pipe installation items include the fitting installation content, the fitting materials being taken as the design-shown quantities or per Table 6.10.32 (6.10.32). Pipes are measured along the design-shown centreline length without deducting the lengths occupied by fittings, valves and accessories (6.10.36); fittings are measured as the design-shown number of pieces (6.10.37).
- ←
Pricing rules for fan-coil-unit installation: the installation sub-item measured per "unit" by installation type, the unit body listed separately as an unpriced main material, and supports distinguished between supplied with the equipment (included) and fabricated on site (applying equipment-support fabrication and installation banded by each support's weight) - per Beijing DB11/T 2382-2024 Section 6.7, with a railway TB/T 10831-2024 quota comparison
FCU pricing splits into three blocks: (1) installation applies the corresponding "ventilation and air-conditioning works - fan coil installation" item, classified by installation type and counted by the design quantities per "unit" (DB11/T 2382-2024 Clause 6.7.11); (2) the equipment body is an unpriced main material listed separately at compilation-period prices, shown in brackets and excluded from the other-materials fee base (Clause 6.7.3); (3) supports are judged first by supply mode: supports/underlay supplied with the equipment are included in the equipment-installation consumptions and not re-applied (Clause 6.7.5), while site-fabricated supports apply "equipment-support fabrication and installation", classified by each support's weight and calculated by the design mass (Clause 6.7.24). Railway TB/T 10831-2024 comparison: FCU exposed FY-2670 (RMB 69.13/unit), concealed FY-2671 (RMB 172.46/unit); equipment supports FY-2675 (<= 50 kg, RMB 907.54/100 kg), FY-2676 (> 50 kg, RMB 624.47/100 kg).
- ←
Measurement of metal-surface rust removal (and painting, anti-corrosion): routed by object - plant and piping by area m2, metal structures by theoretical mass t/kg - with the companion rule of matching the unit of the quota item applied
Rust-removal quantities route by the OBJECT treated, not an either-or: plant and piping rust removal is computed by area (m2) on the design-shown surface, metal-structure rust removal by the theoretical mass of the structure (DB11/T 2382-2024 clauses 6.12.8, 6.12.9), and the outcome must match the unit of the quota item applied. Within metal structures a further split applies: general steelwork (hangers, supports, brackets, ladders, railings, platforms) and pipe-rack steelwork measure in kg; steelwork of sections over 300 mm and H sections over 300 mm measure by developed area in m2 (GB/T 50856-2024 Annex M table M.1.1 note 8); pipe surface S = pi x D x L, with fittings, valves, flanges, manholes and nozzle irregularities comprehended and not added. The municipal basis agrees (DB11/T 2382-2024 clause 7.4.51: pipe rust removal and painting on pipe surface area; steelwork rust removal and metal-structure painting on theoretical mass).
- ←
Sleeves for rainwater/soil (drainage) pipes through floors: mandatory setting, dimensions and construction, and BOQ measurement (GB 55020-2021 / GB/T 50856-2024)
Indoor rain/soil (drainage) pipes through floors shall have metal or plastic sleeves (GB 55020-2021 Clause 8.2.3, fully mandatory): in-floor sleeve tops 20 mm above the finished floor (50 mm in bathrooms and kitchens), bottoms flush with the slab soffit; the sleeve-pipe gap packed with flame-retardant dense material and waterproof ointment, pipe joints not inside sleeves; sleeve size, where unspecified, two nominal sizes larger (DB11/T 1832.13-2022 Clause 3.4.4); BOQ per GB/T 50856-2024 Appendix N (031301003) by count per design quantity, different sleeve classes listed separately.
- ←
Calculating fire-protection system commissioning fees: BOQ listing, measurement units, and point-count rules (GB/T 50856-2024 Appendix J, code 030909)
Fire-protection system commissioning fees are listed separately in the BOQ (GB/T 50856-2024 code 030909), not charged as a percentage of the works cost, but measured by system/point/count with commissioning items: water extinguishing control devices by points from flow indicators/hydrant pump-start buttons/monitor counts, gas extinguishing by cylinder-valve count as points, automatic alarm and other systems by device counts as points and measured by "system", fire barrier control devices by count (valves) or unit (fire lifts); when applying quotas, price by the point-tier steps of the chosen quota — local standards differ in caliber.
- ←
Difference between grounding electrodes and grounding busbars, and their BOQ listing, measurement, and pricing calibers (GB/T 50856-2024 lightning protection and grounding devices, Table D.10.1)
The grounding electrode is the current-dispersing element, measured by design quantity in "pieces (blocks, sets)"; the grounding busbar is the connecting conductor, measured in "m" by total design length plus reserve (additional) length — separate items with different units, not interchangeable in pricing. Additional lengths of busbars, down-conductors, and lightning networks per Table D.17.3-6; TB/T 10829-2024 (per 10 m) and SJG 181.7-2024 (per linear meter) both add 3.9% to design length (turns, undulations, obstacle avoidance, splices).
- ←
Beijing DB11/T 2382-2024 consumption standard: rules for determining whether pipe installation quota line items include pipe fittings - in the gas chapter only galvanized steel pipe (threaded joints) items include fittings and pipe clamps while fittings of other materials are billed separately; pipe items of the water supply/drainage and heating chapters include fitting installation
Under DB11/T 2382-2024 clauses 6.10.32/6.10.34: pipe line items for indoor water supply, drainage and heating "shall include the fitting installation content" (fitting material quantities taken as the design-shown quantities or per Table 6.10.32), so no separate fitting-installation item may be applied; for gas piping, only galvanized steel pipe (threaded joints) items include fittings and pipe clamps, while for other materials (welded steel pipe, PE pipe, steel-skeleton plastic composite pipe etc.) the fittings and clamps must follow the corresponding "fitting and pipe-clamp installation" items. Pipes are measured along the design-shown centreline length with no deduction for lengths occupied by fittings and valves (6.10.36); fittings are counted as the design-shown number of pieces (6.10.37) - in gas works "pipe (m)" and "fittings (piece)" are two independent billed items.
- ←
Charging rules for pipeline pressure testing, flushing, disinfection, and water-quality testing costs (included in BOQ items vs. separately billed under quota norms vs. borne by the employer)
BOQ basis: GB/T 50856-2024 Table K.1.1 note 9 — the work content of all pipeline items includes pressure testing and purging/cleaning, so pressure testing/flushing are not billed separately; municipal quota norms (e.g., SJG 181.4-2024) exclude functional testing and disinfection flushing from pipeline laying, so dedicated quota line items must be applied; the water-quality testing fee is a statutory delivery inspection borne by the employer and is not within installation quota norms.
- ←
Quantity-calculation rules and itemizing method for busways (low-voltage enclosed plug-in busway / common-enclosure busway): by centre-line length, supports included, accessories listed separately by count - distinct from strip busbars
Common-enclosure busway and low-voltage enclosed plug-in busway installation quantities are calculated by the centre-line length of the dimensions shown on the design (m); support installation is included in the installation consumptions and not listed separately; tap-off (plug-in) boxes, end (staring) boxes, copper-busbar expansion joints, supporting insulators etc. are listed separately by the design quantities, and flexible copper connections are calculated per "phase/unit". Strip busbars follow different rules: calculated by per-phase length (including reservations) - 0.30 m/end for busbar terminations and 0.50 m/end for terminations to branch lines or equipment. Basis: DB11/T 2382-2024 Clauses 6.4.21-6.4.24 and Table 6.4.23; the BOQ basis is GB/T 50856-2024 Appendix D, Table D.3.1 (code 030403).
- ←
Cable-tray support (bearing frame) quantity calculation: measured in kg, count by support/hanger spacing, unit mass by section-steel theoretical mass
Cable-tray supports are measured by design finished mass in kg and itemized separately (GB/T 50856-2024, 3.0.10; SJG 181.7-2024, SJG 111.4-2022); counts follow support spacing — 1.5-3m horizontal, <= 2m vertical, densified at bends/branches/panel entries/expansion joints (GB 50397-2007, GB 50606-2010, GB/T 51239-2017, DB11/T 1832.17/19, etc.); unit mass = sum(member net length x unit theoretical mass), unit mass (kg/m) = section area (mm2) x 0.00785; factory supports (incl. seismic) count per piece/set without mass conversion.
- ←
Beijing DB11/T 2382-2024 general building services installation: quota item selection for cabinet (box-type) centrifugal fans - Table C.7.8-7 fan box items, discernment between the box-type and machinery-volume centrifugal fan scopes, and the treatment of supports, hangers and bottom bedding
Cabinet (box-type) centrifugal fan installation is priced under Table C.7.8-7 "fan box installation" (C7-1-104 to 115), banded by installation type and airflow and counted per unit (clause 6.7.17); ventilator installation in general industrial and civil building works follows the applicable ventilation and air-conditioning items (clause 6.1.37) and must not use the machinery-volume "centrifugal forced/induced draft fan" items; the installation items cover labour and plant only, the fan itself being unpriced equipment billed separately; supports and bottom bedding supplied with the equipment are already included and not billed again (clause 6.7.5), site-fabricated supports fall under Table C7.12-1 by the weight of each support and hangers under Table C7.12-2 per unit by fan model (clause 6.7.24).
- ←
Ventilation duct quantity calculation and classified measurement: whether supply / exhaust / fresh-air ducts are computed separately, the developed (unfolded) area rules, BOQ listing, and quota-norm tiering basis
Ducts are computed from design dimensions as developed (unfolded) area (m2): no deduction is made for inspection ports, measuring ports, supply openings or suction openings; length is taken along the design centreline (main and branch ducts divided at their centreline intersections), including the length of elbows, tees, reducers and rectangular-to-round adapters, but excluding the length occupied by components. Supply, exhaust and fresh-air systems are governed by one and the same rule set — there are no per-system differences in the calculation method; "separation" is expressed at the BOQ listing and rate build-up levels — listed by item description (use/name, material, shape, size, plate thickness, joint form), and split when quota line items are applied according to tiering factors such as joint form and size; the system itself is not a tiering factor.
- ←
Cost confirmation after a design change to seismic supports: the four-step rule of qualification → measurement → rate build-up → certification and sign-off
A seismic-support design change (designer-issued variation / employer's instruction) constitutes a variation and the price is adjustable; finished supports are measured in sets under code 031301004, and quantities must be recalculated per Chapter 8 of GB 50981-2014; rate build-up follows GB/T 50500-2024 Clause 8.9.1: identical item descriptions take the contract unit rate, analogous items take a conversion of contract unit rates, and items neither identical nor analogous are determined by negotiation; a quantity difference exceeding 15% triggers adjustment of the unit rate per Clause 8.9.2, and additions beyond the contract scope are treated as additional works per Clause 8.10; differences arising from the contractor's own detailed layout are not adjusted (Clause 3.3.9); after the supervisor's certification and sign-off and the signing of the deliverables by both parties, payment is made together with the interim payment.