Basis values and additional-point rules for cable tray support and hanger spacing: two layers of sources (design versus installation and acceptance), 1.5m~3m horizontal and up to 2m vertical, added support points at bends, ends, joints and section changes, the tie to span-load curves and strength, stiffness and stability checks, the supports-per-metre formula, and the comparison with lateral/longitudinal seismic support spacing
The design basis for cable tray support spacing is GB 51348-2019 clause 8.5.4: 'for horizontal runs the optimum span should be chosen from the load curve, with spans of 1.5m~3m; for vertical runs the spacing of fixing points should not exceed 2m'; the installation layout basis is GB 50606-2010 clause 4.3.2 (1.5~2.0m on straight runs, supports within 0.5m of ends, branches and bends) and DB11/T 1832.17-2021 clause 9.4.2 (support points within 500mm at entry to and exit from boxes and enclosures, corners and bends, both ends of movement joints and all three ends of T-joints). JB/T 10216 is a cable tray product standard containing no support-spacing provision and cannot be cited as the source of these values. The 1.5~3m is the top of a code range; the actual span must follow the manufacturer's span-load curve and pass the strength check (load at first permanent deformation / 1.5), the stiffness check (steel deflection no more than 1/200, aluminium no more than 1/300) and the stability check (steel bracket tilt-to-arm-length ratio no more than 1/100). Supports per metre n = 1/s (units/m); total supports on a straight run N = ceil(L/s) + 1; support weight per metre w/s.
Applicable Codes
- GB 51348-2019 民用建筑电气设计标准 第8.5.4条
- GB 50606-2010 智能建筑工程施工规范 第4.3.2条
- GB 50217-2018 电力工程电缆设计标准 第6.1.2条(Table 6.1.2)、第6.2.5条
- GB 50981-2014 建筑机电工程抗震设计规范 第8.2.3条(Table 8.2.3)、第8.3.2条、第8.3.3条、第8.3.5条
- GB 50311-2016 综合布线系统工程设计规范 第7.5.10条
- DB11/T 1832.17-2021 建筑工程施工工艺规程 第17部分:电气动力安装工程 第9.4.2条
- T/JSTJXH 12-2022 城市轨道交通工程装配式支吊架技术标准 第4.4.2条、App. C.3.2
- T/SHGBC 006-2022 民用建筑电气绿色设计与应用规范 第8.5.1条
- JB/T 10216 电控配电用电缆桥架(产品标准,仅涉载荷试验与挠度,不含间距条文)
- GB 50168 电气装置安装工程 电缆线路施工及验收规范
- https://openstd.samr.gov.cn/bzgk/std/newGbInfo?hcno=19A5C2C0E51CCE5F1C378584DA296F74
- https://openstd.samr.gov.cn/bzgk/std/newGbInfo?hcno=6F1B79527F19B6B7FB4F7CF03853259A
- https://openstd.samr.gov.cn/bzgk/std/newGbInfo?hcno=3858E9FF9F57F1B4824C9DDA727E6226
Scope and purpose
How the spacing of cable tray (ladder trays, trays and trunking collectively) supports and hangers (support frames) is fixed: the layering of the normative sources, the numeric bands, the added points at bends, ends, joints and section changes, the linking tests between spacing and load/deflection, the chain from spacing to support count to cost, and the relation to lateral/longitudinal seismic support spacing.
Core conclusions
1. First fix the source: JB/T 10216 is not the source of the spacing
JB/T 10216, Cable Trays for Electrical Power Distribution and Control, is a product standard whose scope is limited to terms and definitions, type designations, structural requirements, test methods, inspection rules, marking, transport and storage; it governs the tray body itself (structural parameters, sheet thickness, rated uniformly distributed load testing, stiffness) and contains no provision on support and hanger spacing. Attributing '1.5~3m horizontal, up to 2m vertical' to JB/T 10216 is wrong; if that standard is cited at all, only its deflection/load test parts may be cited. Spacing hangs on the following design and installation codes.
2. Design-layer basis (sets the span ceiling)
GB 51348-2019, Standard for Electrical Design of Civil Buildings, clause 8.5.4: 'Cable trays run horizontally should be supported at the optimum span chosen from the load curve, and the span should preferably be 1.5m~3m. When run vertically, the spacing of fixing points should not exceed 2m.' Two key qualifiers: (1) the horizontal span is 'the optimum span chosen from the load curve' - 1.5~3m is an optional band, not a fixed value to be taken at its top; (2) for vertical runs the fixing-point spacing is a ceiling of 'preferably not more than 2m'.
3. Installation and acceptance layer (fixes the point layout)
- GB 50606-2010 clause 4.3.2: supports on straight runs preferably at 1.5m~2.0m spacing, evenly spaced within one straight run; within 0.5m of tray ends, branches and bends, supports must be installed; supports must be straight without obvious distortion, welded firmly without notable deformation, and corrosion-protected; expansion-bolt fixings must be tight with spring washers fitted; where round bars serve as hangers, anti-sway supports must be installed at tray bends and every 30m along straight runs.
- DB11/T 1832.17-2021 clause 9.4.2: fixed-point spacing generally not more than 1.5m~3m, vertical support spacing not more than 2m; support points within 500mm of entry to and exit from junction boxes and enclosures, corners and bends, both ends of movement joints and all three ends of T-joints; rods suspending trunking above ceilings must be at least 8mm in diameter; in vibration locations such as underground car parks, internal-expansion anchors are prohibited for fixing supports and hangers.
- T/JSTJXH 12-2022 Appendix C.3.2: support spacing for horizontally installed cable trays 1.5m~3.0m; for vertically installed trays preferably not more than 2m.
- GB 50311-2016 clause 7.5.10 (surface-mounted trunking): hangers or supports preferably at no more than 3m on straight runs and at joints, at first and last ends and 0.5m from junction boxes at entry and exit, and at corners.
4. Additional-point rules at bends, ends, joints and section changes
| Position | Rule | Source |
|---|---|---|
| Tray ends (start and finish), branches, bends | Supports must be installed within 0.5m | GB 50606-2010 4.3.2 |
| Junction boxes/enclosures entry and exit, corners, bends | Support points within 500mm | DB11/T 1832.17-2021 9.4.2 |
| Both ends of movement joints (expansion and settlement joints) | Support points within 500mm at both ends (when crossing, add expansion devices, protective earth and conductor slack) | DB11/T 1832.17-2021 9.4.2 |
| Three ends of T-joints | Support points within 500mm | DB11/T 1832.17-2021 9.4.2 |
| Straight-run joints, first and last ends and corners of surface-mounted trunking | Hangers/supports at no more than 3m on straight runs and at joints, at ends and 0.5m from junction boxes, and at corners | GB 50311-2016 7.5.10 |
| Start and end of pipe runs, tees and elbows, wall crossings and entry/exit positions | Prefabricated supports and hangers preferable | T/JSTJXH 12-2022 4.4.2 |
| Where light working equipment or conversion equipment sits mid-run | Preferable | T/JSTJXH 12-2022 4.4.2 |
| Where the pipe section or shape changes (widening/reduction) | Preferable | T/JSTJXH 12-2022 4.4.2 |
5. Linking spacing to load and deflection (criteria only, no mechanics derivation)
T/SHGBC 006-2022 clause 8.5.1: tray selection should follow load requirements together with strength, stiffness and stability, saving material while meeting safety; the manufacturer must supply selection parameters such as the span-load curve, otherwise verification is required. The three mechanical indices (consistent with GB 50217-2018 clause 6.2.5):
- Strength - the tray's load capacity must not exceed the load at which the tray first suffers permanent deformation, divided by the safety factor 1.5;
- Stiffness - the relative deflection of ladders and trays under the allowable safe working load should not exceed 1/200 for steel and 1/300 for aluminium;
- Stability - the ratio of the steel bracket's tilt under allowable load to the arm length should not exceed 1/100. Decision logic: for one tray size, the larger the uniformly distributed line load q, the smaller the allowable span given by the span-load curve; where the intended span exceeds the curve's allowable value at that load, or the verified relative deflection exceeds 1/200 (steel)/1/300 (aluminium), or bracket tilt-to-arm-length exceeds 1/100, the verdict is to shorten the span or strengthen the bracket (larger bracket section, added raking struts, shorter cantilever); the 1.5~3m band must not be applied while out of limits. The actual span is the lesser of the code-range ceiling and the curve/verification allowable value.
6. Do not mix in GB 50217-2018 table 6.1.2 - spans for supports 'directly carrying cables'
Table 6.1.2, 'allowable spans (mm) of ordinary supports (cantilever brackets) and hangers', applies to cable supports/hangers that carry cables directly, not to tray supports: non-metallic-sheathed small-section cables without metallic sheath or armour, 400 horizontal/1000 vertical; medium and low voltage cables other than the above, 800 horizontal/1500 vertical; high voltage cables of 35kV and above, 1500 horizontal/3000 vertical. Note: these values may be doubled where the cable can be kept fairly straight. The table's earlier wording 'above 35kV' has been changed to '35kV and above'; the commentary confirms that a 35kV cable's own strength meets horizontal support spacing of 1.5m and vertical spacing of 3m, consistent with GB 50168.
7. Supports per metre and cost conversion
Variables: s - support and hanger spacing (m); L - straight-run length (m); w - weight per support (kg/unit); n - supports per metre (units/m); N - total supports on a straight run (units).
- Supports per metre: n = 1/s. s=1.5m gives 0.667; 2.0m gives 0.5; 2.5m gives 0.4; 3.0m gives 0.333 (units/m).
- Total on a straight run (points at both ends, rounded up): N = ceil(L/s) + 1; the densified points at bends, branches, panel entries and exits and both ends of movement joints are added separately.
- Support weight per metre: w/s (kg/m); total weight on a run W = N x w.
- Cost chain: formed-steel support cost = total support weight (kg) x fabrication-and-erection rate (yuan/kg); proprietary/seismic support cost = number of sets x unit price (yuan/set). Widening the spacing from 1.5m to 3.0m cuts supports per metre from 0.667 to 0.333, roughly halving support count and support cost - but the reduction is bounded by the span-load allowable values in section 5; spacing must not be widened merely to save supports.
8. Comparison with lateral/longitudinal seismic support spacing
- Spacing calculation: GB 50981-2014 clause 8.2.3, l = l0 x aEk x k. l0 is the maximum seismic support spacing, from table 8.2.3; aEk is the comprehensive horizontal seismic force coefficient, taken as 1.0 when below 1.0; k is the brace-angle adjustment factor - for a vertical-to-horizontal brace length ratio of 1.00 take 1.00, up to 1.50 take 1.67, up to 2.00 take 2.33. Table note: for alteration works the maximum seismic strengthening spacing is half the tabulated value.
- Lateral addition: clause 8.3.2, where two lateral seismic supports are farther apart than the maximum design spacing, an additional lateral seismic support is added between them (example: a rigidly connected metal pipe 24m long with a 12m maximum lateral spacing - add at both ends first, then set at 12m intervals).
- Longitudinal addition: clause 8.3.3, each horizontal straight pipe section needs at least one longitudinal seismic support; where two longitudinal supports are farther apart than the maximum design spacing, add supports at the spacing of clause 8.2.3 (example: a 36m pipe at the maximum 24m spacing).
- Longitudinal offset limits: clause 8.3.5, allowable longitudinal offset between adjacent seismic supports on rigidly connected horizontal pipe runs - water pipes and electrical conduit no more than 1/16 of the maximum lateral support spacing; ducts, cable ladders, cable trays and cable trunking no more than 2 times their width.
- Comparison: gravity (ordinary) support spacing is governed by GB 51348-2019's 1.5~3m/up to 2m and obeys tray load and deflection; seismic support spacing is computed as l0 x aEk x k and obeys seismic action; the two are independent and additive, and neither may substitute for the other. Tray width matters in seismic terms only as the base of the longitudinal offset limit (up to twice tray width) and is not a grading basis for gravity support spacing.
Applicability limits
- A support-spacing table graded by tray width does not exist in current codes: spacing follows the run direction (horizontal/vertical) and the load curve; width affects allowable span only through section stiffness.
- 1.5~3m is a design-recommendation/installation-acceptance band; where design documents expressly provide, the design governs. GB 50606-2010's 1.5~2.0m for straight runs is clearly stricter than other codes (intelligent-building services); where multiple standards coexist take the stricter, follow the current standard family of the project, and do not mix families.
- The graded values of GB 50217-2018 table 6.1.2 apply only to supports/hangers carrying cables directly; applying them to tray supports gives markedly small values and is a misuse.
- Whether seismic supports are required at all (intensity and component threshold tests), and their quantity take-off and pricing, belong to related cards; this card covers spacing calculation and addition rules only.
- This card does not replace project layout drawings or manufacturer selection tables; the exact strengthening of long-span brackets still follows the span-load curve or dedicated verification.
Further reading
- Design basis: GB 51348-2019, Standard for Electrical Design of Civil Buildings, clause 8.5.4; T/SHGBC 006-2022, Specification for Green Electrical Design and Application in Civil Buildings, clause 8.5.1 (span-load curve and the strength/stiffness/stability triad).
- Installation basis: GB 50606-2010, Code for Construction of Intelligent Building Engineering, clause 4.3.2; DB11/T 1832.17-2021, Construction Work Procedure, Part 17: Electrical Power Installation, clause 9.4.2 (fabrication of supports, bonding, corrosion protection, movement-joint treatment); GB 50311-2016, Code for Engineering Design of Generic Cabling Systems, clause 7.5.10; T/JSTJXH 12-2022, Technical Standard for Prefabricated Supports and Hangers in Urban Rail Transit Engineering, clause 4.4.2 and Appendix C.3.2.
- Cable support (non-tray) spans: GB 50217-2018, Standard for Design of Cables of Electric Power Engineering, clause 6.1.2 and table 6.1.2, clause 6.2.5 (strength/stiffness/stability indices); companion construction acceptance in GB 50168.
- Seismic: GB 50981-2014, Code for Seismic Design of Building Mechanical and Electrical Engineering, clauses 8.2.3 (table 8.2.3), 8.3.2, 8.3.3 and 8.3.5.
- National standard full-text system (official standard information / online access): https://openstd.samr.gov.cn/bzgk/std/newGbInfo?hcno=19A5C2C0E51CCE5F1C378584DA296F74 ; https://openstd.samr.gov.cn/bzgk/std/newGbInfo?hcno=6F1B79527F19B6B7FB4F7CF03853259A ; https://openstd.samr.gov.cn/bzgk/std/newGbInfo?hcno=3858E9FF9F57F1B4824C9DDA727E6226 .
- Product layer: JB/T 10216, Cable Trays for Electrical Power Distribution and Control - cite only its load tests and deflection requirements, never its (non-existent) spacing.
Keywords
- 桥架支吊架间距
- 电缆桥架
- 支吊架最大间距
- GB 51348-2019
- 抗震支吊架侧向纵向间距
- 跨度-荷载曲线
- 每延米支架数量
- 转角端部增设支吊架