Spacing limits and load-check selection of load-bearing supports for cable trays: horizontal 1.5m~3m / vertical preferably no more than 2m, three-parameter limits of strength, stiffness and stability (relative deflection 1/200 for steel, 1/300 for aluminium, steel bracket-arm deflection-to-arm-length ratio 1/100, safety factor 1.5), selecting bracket-arm and bearer sizes by tray load per metre, the duty to provide and to verify span-load curves, load superposition for stacked layers and combined supports, and the demarcation from seismic support spacing under GB 50981-2014
Load-bearing support spacing: for horizontal runs 'the optimum span should be selected from the load curve for support, and the span should be 1.5m~3m'; for vertical runs 'the spacing of fixing points should preferably not exceed 2m' (GB 51348-2019 Clause 8.5.4; GB 50054-2011 Clause 7.6.15; at the construction-acceptance level GB/T 51239-2017 Clause 9.3.7 uses 'shall'; where the design is silent GB 50397-2007 Clause 16.2.1 takes 1.5~3m / no more than 2m). Load checking follows the three parameters of GB 50217-2018 Clause 6.2.5: the load-bearing capacity must not exceed the maximum load at which the tray first suffers permanent deformation divided by the safety factor 1.5; the relative deflection under the permissible safe working load should preferably not exceed 1/200 for steel and 1/300 for aluminium; the ratio of the deflection of a steel bracket arm under permissible load to the arm length should preferably not exceed 1/100. Manufacturers should provide span-load curves, otherwise a calculation must be made (T/SHGBC 006-2022 Clause 8.5.1). Seismic support spacing is calculated separately under GB 50981-2014 Clause 8.2.3 as l = l0.aEk.k and checked separately from load-bearing support spacing; the two are not interchangeable.
Applicable Codes
- GB 51348-2019 第8.5.4条
- GB 50054-2011 第7.6.15条
- GB/T 51239-2017 第9.3.7条
- GB 50397-2007 第16.2.1条
- GB 50606-2010 第4.3.2条
- GB 50217-2018 第6.2.5条
- GB 50981-2014 第8.2.3、8.3.2、8.3.3、8.3.5、8.3.15条
- T/SHGBC 006-2022 第8.5.1条
- T/CIAS-3-2020 第4.0.2条(含 T/CECS 31-2017 桥架安全工作荷载)
- DB 32/T 4071-2021 第5.2.2条
- DB 51/T 5047-2007 第12.4.2条
- DB11/T 1384-2016 第5.4.1条
- DB11/T 1810-2020 第5.3.2条
- DBJ 46-059-2021 第8.1.5条
- SJG 139-2023 第7.0.1条
Topic scope
Spacing limits and load-check selection of load-bearing supports for cable trays (ladder racks, trays, troughs): the wording and values of the clauses, the three-parameter limits of strength, stiffness and stability, checking support capacity and bracket-arm / bearer sizes against the tray load per metre, the duty to calculate where curves are missing, and the demarcation from seismic support spacing.
Core conclusions
1. Load-bearing support spacing limits (clause wording and values)
- GB 51348-2019 Clause 8.5.4 (electrical design of civil buildings): 'Where a cable tray runs horizontally, the optimum span should be selected from the load curve for support, and the span should be 1.5m~3m. Where it runs vertically, the spacing of fixing points should preferably not exceed 2m.'
- GB 50054-2011 Clause 7.6.15 (low-voltage distribution design): 'Where cable trays and ladder racks run horizontally, the optimum span should be selected from the load curve for support, and the spacing of support points should be 1.5m~3m. Where they run vertically, the spacing of fixing points should preferably not exceed 2m.'
- GB/T 51239-2017 Clause 9.3.7 (construction quality acceptance level, using 'shall'): 'the support spacing of horizontal trays is 1.5m~3m and the support spacing of vertical trays shall not exceed 2m'; the same clause also requires expansion joints where straight steel trays exceed 30m, aluminium or glass-fibre trays exceed 15m, and where trays cross building expansion joints; the bending radius at tray bends shall be no smaller than the minimum permissible bending radius of the cables in the tray; anti-galvanic-corrosion measures shall be taken where aluminium trays are fixed to steel supports; the net clearance to general process pipelines should preferably be no less than 0.4m in parallel and no less than 0.3m at crossings.
- GB 50397-2007 Clause 16.2.1: 'where the design is silent, the support spacing of horizontally installed cable trays is 1.5~3m and that of vertically installed trays is no more than 2m, and supports within one zone shall keep a consistent spacing, with a deviation no greater than 100mm'. Posts shall be added about 300mm before and after each horizontal bend and at mid-bend; about 300mm before and after points of marked level change; about 300mm before and after expansion joints. Posts shall show no obvious tilt, with vertical deviation no more than 2 per mille of their length; welds at fixing points shall be full and corrosion-protected; fixing tray posts to brick walls with expansion bolts is forbidden.
- GB 50606-2010 Clause 4.3.2 (intelligent buildings, combined services, stricter): 'the support and hanger spacing on straight runs should be 1.5m~2.0m and shall be uniform on one straight run'; supports shall be installed within 0.5m of tray ends, branches and bends; where round steel is used for hangers, anti-sway supports shall be installed at tray bends and every 30m on straight runs.
- DB 32/T 4071-2021 Clause 5.2.2: 'where metal troughs run horizontally, the optimum span should be selected from the load curve for support, the span being 1.5m~3m; where they run vertically, the spacing of fixing points should preferably not exceed 2m. Installation supports shall be provided 200mm~300mm from the head, the tail and the joints of metal troughs and 500mm at bends.' DB 51/T 5047-2007 Clause 12.4.2 takes the same values (1.5~3m / no more than 2m).
Key points on the values: 3m is only an upper bound. The design-level wording is 'select the optimum span from the load curve', i.e. the span is a function of the load and not a default 3m; the actual span is the smallest of (code range), (product span-load curve) and (project or local standard) - e.g. the stricter 1.5~2.0m of GB 50606-2010.
2. The three load-check parameters (strength, stiffness, stability) and their limits
GB 50217-2018 Clause 6.2.5: the structural elements of a tray shall satisfy strength, stiffness and stability and comply with the following - '1. the load-bearing capacity of the tray shall not exceed the value obtained by dividing the maximum load at which the tray first suffers permanent deformation by the safety factor of 1.5; 2. the relative deflection of ladder racks and trays under the permissible safe working load should preferably not exceed 1/200 for steel and 1/300 for aluminium; 3. the ratio of the deflection of a steel bracket arm under permissible load to the arm length should preferably not exceed 1/100; 4. cable trays of safety-class circuits in nuclear power plants shall meet the seismic Class I design requirements for items'. T/SHGBC 006-2022 Clause 8.5.1 repeats the same values and explains the three parameters: strength - the maximum normal stress under load shall be below the permissible stress of the material; stiffness - the limit on relative deflection under the permissible safe working load; stability - the deformation of side plates under load kept within the permissible range, characterised by the deflection-to-arm-length ratio 1/100 of steel bracket arms.
3. Load composition and the 'load per metre' check
T/CIAS-3-2020 Clause 4.0.2: the vertical load of horizontal services on supports and hangers mainly includes the self-weight of the services, of service attachments, of insulation, of the medium carried inside, and of components inside; 'the weight of components inside refers to the weight of cables and wires in the troughs' - so when checking support capacity against the tray load per metre, the self-weight of the tray body and its cover plates, the weight of cables (wires) at the filling ratio, and the weight of attachments must all be included. For electrical trays and busways the same clause provides: the load of trays and ladder racks on supports and hangers is determined, under the Technical Specification for Steel Cable Trays T/CECS 31-2017, by the span L with equal spans on the two sides of the support, the safe working load qE of each layer of tray or ladder, the self-weight G of trays, ladders, covers and attachments, and the safety factor n0 (taken as 1.5); busway weight is taken as 1.1 times the busway self-weight within the calculated support spacing. Stacked layers and shared supports: qE is taken per layer of tray or ladder as its permissible safe working load, and as the number of layers grows the qE of each layer and the self-weights are accumulated; the eccentric load on the two sides of a cable trough shall not twist the support; combined supports shall be checked by superposing the vertical loads of all services, the centre of gravity of the whole load should preferably lie close to the centre line of the combined support, and where it does not, the attachment positions of the diagonal steel ropes on the combined support shall be adjusted (DB11/T 1384-2016 Clause 5.4.1); supports and hangers shall be analysed for pipe layout, service weight and structural loads, and the force calculation shall be made by structural engineers (SJG 139-2023 Clause 7.0.1). As a superposition reference, the horizontal load of water pipes may be taken as 0.3 times the vertical load, with separate checking where large cold-to-hot movement or unbalanced internal forces exist (T/CIAS-3-2020 Clause 4.0.2).
4. Selecting bracket arms / bearers by load grade - order of checks
(1) from the support spacing L and the permissible safe working load qE of each layer (accumulated across layers), derive the design load of the support at that point; (2) from the product table of common sizes against safe working load grades (T/CECS 31-2017 table: safe working loads of trays and ladder racks and their common size grades) select bracket arm and bearer (with post and hanger rod) sizes whose permissible safe working load is no less than the design load, the safety factor being controlled at 1.5; (3) re-check the three parameters: relative deflection (1/200 steel, 1/300 aluminium), steel arm deflection-to-length ratio 1/100, side-plate stability; (4) where any parameter fails, tighten the support spacing (add supports) or upgrade the arm / bearer grade rather than relax the limits. Hanger rods shall be no smaller than 8mm in diameter (DB11/T 1832.19-2023 Clause 3.4.4); anti-galvanic (insulating) measures shall be taken where aluminium trays are fixed to steel supports (GB/T 51239-2017 Clause 9.3.7; DB 51/T 5047-2007 Clause 12.4.2).
5. Responsibility checks where spacing is exceeded or trays deform
- Duty to provide selection parameters: T/SHGBC 006-2022 Clause 8.5.1 states that 'tray selection shall follow the load requirements and the conditions of strength, stiffness and stability, saving material subject to the safety principle'; 'the manufacturer shall provide selection parameters such as span-load curves, otherwise a calculation shall be made; it is recommended that manufacturers provide site survey and secondary calculation' - where curves are missing, defaulting to a 3m layout is not allowed; the manufacturer or the designer must supply the calculation.
- Order of checking design conditions: GB 50397-2007 Clause 16.2.1 makes 'where the design is silent' the premise of the 1.5~3m / no more than 2m values; where the design documents give spans or load conditions, follow the design; where they do not, take the code range - but the duty of load checking (the three parameters) remains.
- Consequences of exceeding: enlarging horizontal spans beyond 3m or vertical fixing spacing beyond 2m in construction directly breaches GB/T 51239-2017 Clause 9.3.7 ('shall') and GB 50397-2007 Clause 16.2.1; failure of strength, stiffness or stability leads to excessive tray deflection, permanent deformation or side-plate instability (GB 50217-2018 Clause 6.2.5; T/SHGBC 006-2022 Clause 8.5.1).
6. Demarcation from GB 50981-2014 seismic support spacing (separate checks, no substitution)
- Ordinary load-bearing (gravity) supports carry gravity: horizontal 1.5m~3m, vertical no more than 2m, checked by span-load curves and strength / stiffness / stability.
- Seismic supports carry seismic action, with spacing calculated under GB 50981-2014 Clause 8.2.3: l = l0.aEk.k, where l0 is the maximum seismic support spacing (from Table 8.2.3), aEk is the comprehensive coefficient of the horizontal seismic force (taken as 1.0 when less than 1.0), and k is the adjustment factor for the angle of the diagonal brace (1.00 where the ratio of vertical to horizontal length of the brace is 1.00; 1.67 where the ratio is no more than 1.50; 2.33 where no more than 2.00); in retrofit works the maximum seismic strengthening spacing is half the table value.
- Layout rules: Clause 8.3.2 - where two transverse seismic supports are farther apart than the maximum design spacing, a further transverse seismic support is added between them; Clause 8.3.3 - each horizontal straight pipe run has at least one longitudinal seismic support, and where two longitudinal supports are farther apart than the maximum design spacing, further supports are added at the Clause 8.2.3 spacing in turn; Clause 8.3.5 - for horizontally laid rigidly connected piping, the permissible longitudinal offset between two adjacent seismic supports is no more than 1/16 of the maximum transverse support spacing for water pipes and electrical conduits, and no more than twice the width for air ducts, cable ladder racks, cable trays and cable troughs; Clause 8.3.15 - a portal seismic support has at least one transverse seismic brace or two longitudinal seismic braces, and where multi-storey portal hangers hang from one load-bearing hanger they are strengthened independently, with seismic braces set.
- Substitution boundary: a support of a branch run (branch tray) cannot serve as the seismic support of the main run (main tray); where a seismic support coincides with an anti-sway support, only the seismic support need be set (DB11/T 1810-2020 Clause 5.3.2). Where a seismic support coincides with a gravity support, if the seismic support can carry the gravity of the building services at that point, only the seismic support may be installed, subject to providing the seismic verification and the gravity calculation for that point (DBJ 46-059-2021 Clause 8.1.5).
- Conclusion: load-bearing supports are laid out at 1.5m~3m / no more than 2m and checked for load; seismic supports are laid out and verified separately by l = l0.aEk.k; in magnitude seismic transverse / longitudinal spacing may reach ten to twenty-odd metres, so a seismic support spacing must never serve as load-bearing support spacing, nor the reverse; the two are checked separately.
Applicable boundaries
- Distinguish 'should' from 'shall': 1.5m~3m is the 'should' range with 3m an upper bound, not a default; the vertical 2m is 'should preferably not' at design level and 'shall not' at the acceptance level (GB/T 51239-2017 Clause 9.3.7), acceptance being stricter.
- Where standards differ, follow the system / region of the project: GB 50606-2010 Clause 4.3.2 is stricter at 1.5~2.0m on straight runs; metro and other dedicated standards are stricter still; do not mix systems.
- The deflection 1/200 and 1/300 and the arm ratio 1/100 are 'should preferably' limits used for product selection and checking, and cannot be read backwards as an acceptable upper bound of support spacing; trays of nuclear safety-class circuits are subject to the seismic Class I design requirements (GB 50217-2018 Clause 6.2.5 item 4).
- The load formula (L, qE, G, n0 = 1.5) comes from the T/CECS 31-2017 system and must follow the product safe working load grade tables; where span-load curves are missing a calculation is required, and another manufacturer's curves may not be cited.
- The fixing spacing of tray supports is not the same as the fixing spacing of cables tied inside the tray: DB 51/T 5047-2007 Clause 12.4.2 has separate rules for the cables themselves (cables laid at over 45 degrees fixed every 2m; horizontally laid cables fixed at both ends, at both sides of bends and every 5~10m), not to be confused with support spacing.
- Whether seismic supports must be set at all (component thresholds) and seismic spacing calculation are covered by other cards (the seismic support decision chain and seismic support measurement and pricing).
Further reading
- Spacing clauses: GB 51348-2019 Clause 8.5.4; GB 50054-2011 Clause 7.6.15; GB/T 51239-2017 Clause 9.3.7; GB 50397-2007 Clause 16.2.1; GB 50606-2010 Clause 4.3.2; DB 32/T 4071-2021 Clause 5.2.2; DB 51/T 5047-2007 Clause 12.4.2 and Tables 12.4.2-1 to 12.4.2-3.
- Loads and the three parameters: GB 50217-2018 Clause 6.2.5 and its commentary; T/SHGBC 006-2022 Clause 8.5.1; T/CIAS-3-2020 Clause 4.0.2 (load analysis, citing the tray load formula and the safe working load tables of T/CECS 31-2017, Technical Specification for Steel Cable Trays).
- Seismic demarcation: GB 50981-2014 Clause 8.2.3 (Table 8.2.3 maximum seismic support spacing), Clauses 8.3.2, 8.3.3, 8.3.5, 8.3.15; DB11/T 1810-2020 Clause 5.3.2; DBJ 46-059-2021 Clause 8.1.5.
- Combined supports and force calculation: DB11/T 1384-2016 Clause 5.4.1; SJG 139-2023 Clause 7.0.1; DB11/T 1832.19-2023 Clause 3.4.4 (hanger rod diameter, fixed support spacing).