BOQ classification under GB/T 50856-2024 of power cable earthing, handover tests and insulation checking: termination earthing included in the termination installation itself, cables (wires) used as earth conductors billed under cable installation / conduits and wiring, stand-alone lightning protection and earthing installations under 030410, tests under 030416 (electrical adjustment and testing), with the billing scope of cable installation 030409 and the boundaries drawn by the D.17 problem notes
Earthing of the metal sheath, armour or screen at cable terminations (power cable terminations, cable joints, control cable terminations) is work content of the termination installation itself ('termination earthing') - no separate BOQ item and no separate earthing item; where cables or wires serve as earth conductors, bill under the relevant item codes of Appendix D.9 cable installation and Appendix D.12 conduits and wiring; stand-alone earth electrodes, earth bars, down conductors, grading rings, air-termination tapes (meshes), air-termination rods, equipotential bonding terminal boxes, earthing bonding jumpers and the like are billed separately under 030410 (table D.10.1). Power cable tests (including insulation resistance measurement and withstand voltage tests) and earthing installation commissioning go to table D.16.1 electrical adjustment and testing (code 030416); 'insulation checking' has no stand-alone code in the BOQ, and its test items and voltage application follow GB 50150-2016 clauses 17.0.1 and 17.0.2. Within cable installation (030409), cable trays / raceways, protective conduits for cables entering buildings, and cable branch boxes are billed instead under the relevant codes of Appendix D.12 and Appendix D.5.
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准 App. D Table D.9.1 电缆安装(code 030409)
- GB/T 50856-2024 Table D.10.1 防雷及接地装置(code 030410)
- GB/T 50856-2024 Table D.16.1 电气调整试验(code 030416)
- GB/T 50856-2024 App. D 问题说明 D.17.12 / D.17.13 / D.17.18
- GB/T 50856-2024 Table D.17.3-5 电缆敷设预留长度及附加长度、Table D.17.3-6 接地母线及避雷网附加长度
- GB/T 50856-2024 第3.0.10条(支架、吊架、基础型钢含于本体安装)
- GB 50150-2016 电气装置安装工程电气设备交接试验标准 第17.0.1条、第17.0.2条
- GB/T 50854 房屋建筑与装饰工程工程量计算标准(接地极、室外母线、降阻剂土石方)
- SJG 181.7-2024 市政工程消耗量标准 Vol. 7 电力通道、通信管道及照明工程 第8.1.4条
Topic positioning
This card resolves the three most mis-slotted issues in electrical installation BOQ preparation: which table bills power cable earthing, which bills tests, and whether insulation checking has its own code; it also gives the billing scope of GB/T 50856-2024 table D.9.1 (cable installation, code 030409) and the 'included in the laying item / bill separately' boundary, for duplicate-pricing control in BOQ preparation and settlement checking.
Core conclusions
1. How the three BOQ tables split the work
- Table D.9.1 cable installation (code 030409) - 'the item setting, item-description content, units of measurement and measurement rules of the cable installation BOQ items shall follow the provisions of table D.9.1'.
- Table D.10.1 lightning protection and earthing installations - the introduction prints 'code: 0304010' (it should be 030410), same rule as above.
- Table D.16.1 electrical adjustment and testing (code 030416) - 'the item setting, item-description content, units of measurement and measurement rules of the electrical adjustment and testing BOQ items shall follow the provisions of table D.16.1'. The boundaries between the three tables are drawn by their 'notes on problems' (D.17.12 / D.17.13 / D.17.18); these three notes are the sole authoritative basis of classification, not optional hints.
2. Cable earthing: three situations, three homes
- Earthing at cable terminations (power cable terminations, joints, control cable terminations): work content of the termination installation itself. In table D.9.1, items 030409003 power cable termination, 030409004 cable joint and 030409005 control cable termination all list the work content '1. fabrication of the termination 2. installation of the termination 3. cable termination earthing', and the corresponding local pricing guides likewise mark the item 'included in the body installation'. -> conclusion: the earthing connections of metal sheath, armour and screen at the termination are not billed as a separate item and take no separate earthing item.
- Cables or wires used as earth conductors: D.17.13 note 4 reads - 'where cables or wires are used as earth conductors, bill under the relevant item codes of Appendix D.9 cable installation and Appendix D.12 conduits and wiring of this standard'. -> conclusion: no separate 'earth conductor' BOQ item is set; quantities and price follow the cable laying or wire drawing itself.
- Stand-alone earthing installations: earth electrodes, earth bars, down conductors, grading rings, air-termination tapes (meshes), air-termination rods, equipotential bonding terminal boxes and test plates, insulation mats, intelligent lightning protection devices, earth resistance reducers, earthing bonding jumpers, lightning protection disconnection cards (boxes), semiconductor lightning dissipation devices and the like are billed separately under table D.10.1 (from 030410001). Measurement basis: earth electrodes, air-termination rods, equipotential terminal boxes and earthing bonding jumpers by the quantities shown on the design drawings; earth bars and air-termination tapes by 'the total length shown on the design drawings plus the reserve length'; grading rings by 'the total length shown on the design drawings' (no reserve added); earth resistance reducers by mass in kg.
3. Key clauses of the table D.10.1 problem notes (D.17.13)
- Where pile foundations serve as earth electrodes, the number of piles under the pile cap shall be stated in the item description, and the pile main bars are measured as column down conductors; where foundation reinforcement serves as the earth electrode, bill under the 'grading ring' code of this table.
- Where column bars serve as down conductors, the number of bars welded shall be stated in the item description.
- Where ring-beam bars serve as grading rings, the number of bars welded shall be stated in the item description.
- The additional lengths of earth bars, lightning down conductors and lightning meshes are given in table D.17.3-6.
- Earthing bonding means: cross-bonding of the earth grid, equipotential bonding, earthing of steel and aluminium windows, earthing of structures, cross-bonding between down-conductor main bars and ring-beam bars, and earthing connections of pile caps.
- The intelligent lightning monitoring system includes surge protective devices, dedicated SPD back-up protectors, SPD intelligent monitoring units, intelligent lightning monitoring and early-warning host equipment, earthing performance monitors and other lightning protection products.
- Cathodic protection earthing is billed under the relevant item codes of Appendix M, painting, anti-corrosion and insulation works.
- The earth and rock works of earth electrodes, outdoor busbars and earth resistance reducers are billed under the relevant item codes of the current national standard GB/T 50854, Measurement Standard for Building and Decoration Works.
4. Cable installation (030409) billing scope and the included / separate boundary (D.17.12)
- The laying method of cable protective conduits means above ground or underground; the protective conduit of cables entering a building is billed under the 'connecting short conduit' code in Appendix D.12, conduits and wiring.
- The reserve and additional lengths for cable laying are given in table D.17.3-5 (the basis for the cable itself being measured in m as 'total length of each single cable plus the reserve length').
- Cable trays and cable raceways are billed under the relevant item codes of Appendix D.12, conduits and wiring (not within 030409).
- Cable branch boxes are billed under the 'terminal box' code of Appendix D.5, low-voltage electrical equipment installation.
- The laying methods of cables mean direct burial, in cable trenches (tunnels), in ducts, indoors, in riser shafts and the like - the item description 'laying method' is described on that basis, not as 'above ground / underground'. The other items of the table (power cable / control cable 030409001/002, the various terminations, cable protective conduits, flame-retardant trunking, sand bedding with protective slabs (bricks), fire slot belts, fire barrier boards and fire walls, fire stopping compound, fireproof coatings, and the add-on items of trunking / cable trench excavation and backfill / pavement cutting / cable protection) are measured by length, area, mass or quantity as shown on the design drawings; 'removing (replacing) cover slabs' is expressly listed in the work content of power cable / control cable laying, while 'sand bedding and protective slabs (bricks)' is a separately billed item - the two must not be conflated.
5. Tests and insulation checking
- Power cable tests and earthing installation (earth resistance) commissioning go to table D.16.1, electrical adjustment and testing (code 030416), as separate items (the exact item codes and units follow the table itself).
- 'Insulation checking' has no stand-alone BOQ code: insulation resistance measurement and withstand voltage testing are work content of the cable test items, not separate items, and must not be charged twice.
- Test items and voltage application follow GB 50150-2016 clause 17.0.1; power cable line tests shall include: 1 measurement of insulation resistance of the main insulation and the outer sheath; 2 DC withstand voltage test of the main insulation with leakage current measurement; 3 AC withstand voltage test of the main insulation; 4 DC withstand voltage test of the outer sheath; 5 phasing check at both ends of the cable line; 6 insulation oil tests of oil-filled cables; 7 cross-bonding system tests; 8 partial discharge measurement of power cable lines.
- Clause 17.0.2 application points: extruded-insulation cables may be tested under items 1, 3, 5 and 8, with items 4 and 7 added for single-core AC cables; for cables of rated voltage U0/U of 18/30 kV and below, where conditions do not permit, a 0.1 Hz voltage of 3U0 r.m.s. applied for 15 min, or DC withstand voltage testing with leakage current measurement, may replace the AC withstand test; paper-insulated cables under items 1, 2 and 5; self-contained oil-filled cables under items 1, 2, 4, 5, 6, 7 and 8; 0.6/1 kV cable lines may use a 2500 V megger to measure conductor-to-earth insulation resistance in place of a withstand test, the measurement lasting 1 min; the outer sheath of single-core AC cables shall undergo a DC withstand test; when testing beside sheath overvoltage protectors, the temporary earth must be short-circuited. Extruded-insulation power cables means power cables with PVC insulation, cross-linked polyethylene insulation or ethylene-propylene rubber insulation; paper-insulated cables means cables with viscous oil-impregnated paper insulation and cables with non-draining oil-impregnated paper insulation.
- Commissioning problem notes (D.17.18) bearing on test pricing: the steam, electricity and other energy consumed in the start-up commissioning of motors and generators above 10 kW, and the electricity consumed in no-load trial-run commissioning of transformers together with any drying the equipment requires, shall be stated; 'other item commissioning' means the electrical commissioning of earth-fault loop impedance, EPS and UPS power supplies, surge arresters, capacitors, reactors, rectifier equipment, arc-suppression coils, busbars, luminaire illuminance and the like.
6. Catch-all clause (the last question in deciding 'bill separately or not')
GB/T 50856-2024 clause 3.0.10 reads: 'The work content of the equipment, piping and accessory installation items of this standard all includes the fabrication and installation of supports, hangers and base section steel together with painting; where special design requirements apply, bill under the relevant item codes of Appendix N, other and ancillary works, or Appendix M, painting, anti-corrosion and insulation works, of this standard.' -> so cable supports, tray hangers and base section steel are not billed separately absent special design requirements; where such requirements exist, they move to Appendix N (ancillary works) or Appendix M (painting and anti-corrosion).
Applicability boundaries
- This card's basis is the general building-services installation works of GB/T 50856-2024 Appendix D; municipal, railway and other systems carry their own consumption standards: SJG 181.7-2024, Municipal Works Consumption Standard, Volume 7, Power Ducts, Communication Ducts and Lighting Works, clause 8.1.4 provides that 'cable tests, insulation oil tests, insulator tests and tests of other equipment elements are all entered in the relevant system commissioning items and are not computed separately' - the same test is merged into system commissioning under the municipal basis but billed separately as 030416 under the general installation BOQ basis; carrying it across systems double counts or omits.
- The exact item codes and units of table D.16.1 (cable tests, earthing installations and the like) must be checked against the current text of the standard; this card does not substitute for it.
- Local installation BOQ pricing guides give 'combinable budget base-price items' for every BOQ item, their codes mapping one-to-one to the regional quota; such content is region-specific and must not be carried across provinces.
- The 'code: 0304010' of table D.10.1 is as printed or transcribed in the text; the BOQ code is used uniformly as 030410; table D.9.1 shows isolated digit transcription drift in some rows (such as the sand-bedding items) - check item name and code sequence together when preparing.
- The 'included' treatment of termination earthing is limited to the earthing connections at the termination; a stand-alone earth bar run from the termination to the earthing main or earth grid is still billed separately under 030410.
Further reading
- GB/T 50856-2024, Measurement Standard for General Building Services Installation Works, Appendix D, electrical equipment installation works: table D.9.1 cable installation (030409), table D.10.1 lightning protection and earthing installations (030410), table D.16.1 electrical adjustment and testing (030416), and their 'notes on problems' D.17.12, D.17.13 and D.17.18.
- The same standard: table D.17.3-5 (reserve and additional lengths for cable laying) and table D.17.3-6 (additional lengths of earth bars, lightning down conductors, lightning meshes); Appendix D.5 low-voltage electrical equipment installation (terminal boxes); Appendix D.12 conduits and wiring (connecting short conduits, trays, raceways); Appendix N other and ancillary works; Appendix M painting, anti-corrosion and insulation works; clause 3.0.10 general provision on work content.
- GB 50150-2016, Standard for Handover Tests of Electrical Equipment in Electrical Device Installation, Chapter 17 power cable lines (17.0.1 test items; 17.0.2 handover test provisions).
- GB/T 50854, Measurement Standard for Building and Decoration Works (earth and rock works of earth electrodes, outdoor busbars, earth resistance reducers).
- Municipal comparison: SJG 181.7-2024 clause 8.1.4 (tests entered in system commissioning, not computed separately).
- Local application: the provincial Installation Works BOQ Pricing Guides, tables D.9 and D.10, used to map BOQ items to budget base-price items and to check the 'included in the body installation' markings.
Keywords
- GB/T 50856-2024
- 电缆安装 030409
- 电缆头接地
- 防雷及接地装置 030410
- 电气调整试验 030416
- 电缆试验
- GB 50150-2016
- 绝缘电阻测量