Pricing boundaries of anti-vibration pedestals, equipment hangers and equipment foundations for ventilation and air-conditioning equipment: installation-side metal structure and pedestal line items, civil-side concrete foundations, and vibration isolation elements as principal materials - a three-part split and the test against double counting
Anti-vibration arrangements are priced in three parts: (1) steel pedestals, supports and hangers integral with the equipment go to the installation side (railway rule: 'fan vibration-damping pedestals may be priced under the equipment support line items, with dampers priced separately', FY-2675/FY-2676 per 100kg; Beijing DB11/T 2382-2024 has standalone vibration isolation pedestal line items C1-6-105 to C1-6-109 measured per unit by equipment weight, and the equipment support items may not be applied as well); (2) concrete equipment foundations and plinths belong to civil works and are listed separately in m3 (reinforcement and formwork priced separately), the installation side keeping only the steel base sections, shim plates and grouting; (3) vibration isolators, isolation pads and spring dampers are principal materials priced separately per piece or per group - wherever the line item work content already includes them (supports and packing supplied with the equipment, fan installation including isolator installation), they must not be counted again.
Applicable Codes
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程(册说明 Ch. 3 第三节 通风及空调工程;Ch. 1 第五节 设备基础 FY-471~FY-477;Ch. 3 第三节 设备支架制作安装 FY-2675、FY-2676)
- DB11/T 2382-2024 建设工程施工消耗量标准(第6.7.1、6.7.5、6.7.24、6.7.31、6.1.34、6.1.37、6.1.38、6.1.39条;App. C C1-6-102、C1-6-105~109、C7-1-173/174、C10-4-2)
- GB/T 50856-2024 通用安装工程工程量计算标准(第3.0.9、3.0.10条,App. A.14.2、App. N.2.4)
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准(App. E.7.2)
- SJG 77-2020 房屋建筑工程造价文件分部分项和措施项目划分标准(第6.1.8条)
Topic positioning
Anti-vibration arrangements for ventilation and air-conditioning equipment (fans, air-conditioning units, VRF systems etc.) usually consist of a 'steel pedestal or hanger + concrete plinth or equipment foundation + isolation elements'; the three parts belong to installation works and civil works respectively, and to different quota (consumption) line items and BOQ codes. This card gives a reusable split test: which parts take installation-side line items and in what measurement units, which must go to civil works, which are principal materials priced separately, and which would be double counting.
Core conclusions
1. Decision skeleton: a three-part split
- Metal supports integral with the equipment body (steel pedestals, equipment supports, hangers, base steel sections, bases, shim plates) -> installation-side line items.
- Concrete plinths and concrete equipment foundations -> civil side, listed separately in m3, reinforcement and formwork priced separately; not counted again on the installation side.
- Isolation elements (rubber isolation pads, spring isolators, vibration-damping hooks) -> decided by the line item work content: either priced separately as principal materials per piece/block/group, or already included in the installation / pedestal line item and not to be added.
2. Railway rules (TB/T 10831-2024 Volume 10 Building Works)
Volume notes, Chapter 3 Section 3 ventilation and air-conditioning works, item 2 under '1. Air-conditioning components and equipment supports':
'2. Fan vibration-damping pedestals may be priced under the equipment support line items, with dampers priced separately.'
Item 4 under '2. Ducts' of the same section (attribution of floor-standing supports):
'The fabrication and installation quota for thin steel sheet and GRP ventilation ducts includes bends, tees, reducers, oval-to-round transition fittings, flanges, stiffening frames and hanger and support brackets; floor-standing supports spanning the duct are not included - floor-standing supports take the equipment support quota.'
The corresponding equipment support line items: FY-2675 'equipment support fabrication and installation, up to 50kg' and FY-2676 'equipment support fabrication and installation, over 50kg', measurement unit 100kg, work content 'setting out, cutting, straightening, drilling, welding, forming, positioning, installing, bolting, fixing, hole drilling, embedding of supports' - metal structure fabrication and installation only, no concrete pouring. So for the 'steel frame + concrete plinth' type of vibration pedestal, the railway rules price the steel per kg under FY-2675/FY-2676 and send the plinth concrete to civil works: Chapter 1 Section 5 concrete and reinforced concrete works, '(2) Equipment foundations' FY-471 to FY-476 (rubble concrete, concrete, bracketed by volume: no more than 5m3 / 20m3 / 100m3, unit 10m3, work content including 'formwork fabrication, erection, cleaning, release agent application, striking, tidying and stacking; concrete placing, compaction and curing'), and secondary grouting FY-477 (unit 10m3).
Note the railway versus building-works difference: the equipment foundation line items above synthesise formwork into the work content, unlike the building-works BOQ practice of three separate bills 'concrete (m3) + formwork (m2) + reinforcement (t)'; cross-system borrowing must not be copied blindly.
3. Beijing rules (DB11/T 2382-2024 Construction Consumption Standard)
- Vibration pedestals have standalone line items; the equipment support items are not used. Table C.1.43-3 'vibration isolation pedestal' is bracketed by equipment weight (within 0.5t / 1t / 3t / 5t / 7t, line items C1-6-105 to C1-6-109), measurement unit 'unit', work content: 'handling within the site, foundation setting out, steel structure fabrication, derusting, painting, concrete placing and curing' - steel frame and concrete plinth are integrated. So once it is billed per 'unit' in full, the equipment support fabrication and installation items C7-1-172 to 174 may not be applied as well (that table is bracketed by each support weight, 40kg, 60kg etc., unit 10kg, work content 'handling within the site, setting out, cutting, straightening, drilling, welding and forming, positioning, assembly, installing, bolting, fixing'), nor may the plinth concrete be added separately.
- General attribution (clause 6.7.1): 'Foundation concreting for ventilation and air-conditioning works shall be executed under the corresponding items of building and decoration works; grouting shall be executed under the corresponding items of mechanical equipment installation works.'
- Hanger and packing measurement (clause 6.7.24): 'Equipment support fabrication and installation quantities shall, by each support weight, be computed from the weights shown on the design drawings; fan hanger fabrication and installation quantities shall, by fan model, be computed from the quantities shown on the design drawings; equipment base packing installation quantities shall, by material, be computed from the weights shown on the design drawings.' Clause 6.7.31: fabrication and installation of floor-standing supports spanning ducts likewise follows clause 6.7.24.
- Isolation elements as principal materials: Annex C line item C1-6-102 'isolation pad (support point)' measured 'per piece', material SD rubber isolation pad (per 'group'); the pipe-side analogue is the C10-4-2 'installation, general pipe supports' work content note: 'where pipe supports are of the timber-insert type or the spring type, the corresponding pipe support fabrication and installation items apply, and the preservative timber inserts and spring dampers are principal materials priced separately'.
- Inter-volume attribution of fan installation and supports: fans of general industrial and civil building works are installed under the ventilation and air-conditioning items (clause 6.1.37), and their supports and hangers follow clause 6.7.24; only where fan installation itself is billed under mechanical equipment installation (clause 6.1.38), 'fan support fabrication and installation shall be executed under the corresponding items of static equipment and process metal structure fabrication and installation works'. Clause 6.1.39 adds how fan weight is computed: direct-drive types include the body, the motor and the base; non-direct-drive types include the body and the base, excluding the motor.
4. National BOQ rules (GB/T 50856-2024 General Installation Works Measurement Standard)
- Clause 3.0.10: 'The work content of the equipment, piping and fitting installation items in this standard all includes the fabrication, installation and painting of supports, hangers and base steel sections; where special design requirements exist, items shall be coded and listed under the corresponding items of Annex N Other and Ancillary Works or of Annex M Painting, Anti-corrosion and Insulation Works.'
- Clause 3.0.9: 'Apart from mechanical equipment installation, where grouting is marked in this standard, although the work content of the other equipment items does not mention grouting, it shall all include the grouting work content needed to complete the relevant items.'
- Annex A.14.2: 'Steel structures needed for equipment installation shall be coded and listed under the corresponding items of Annex C Static Equipment and Process Metal Structure Fabrication and Installation Works. Where special design requirements exist, the fabrication and installation of supports and hangers needed for equipment installation shall be coded and listed under the relevant installation items of support and hanger fabrication in Annex N of this standard.'
- Annex N.2.4: 'Where the design drawings require liners on supports, this shall be stated in the item description; liner categories mean preservative timber inserts, stainless steel liners, aluminium liners etc. Where spring dampers are used, the item description shall state whether a damping test is performed. Anti-corrosion and painting of supports and hangers shall be coded and listed under the corresponding items of Annex M Painting, Anti-corrosion and Insulation Works of this standard.'
5. Positive authority for foundations going to civil works
- SJG 77-2020 clause 6.1.8: 'Concrete equipment foundations, concrete water tanks and the like shall be listed under the corresponding civil works.'
- GB/T 50854-2024 Annex E.7.2, cast in-situ reinforced concrete foundations: 'Frame-type equipment foundations shall be coded and listed separately under the corresponding items for foundations, columns, beams, walls and slabs.'
- The installation side keeps only the steel base sections, shim plates, equipment supports and grouting integral with the equipment (grouting under the mechanical equipment installation basis).
6. Negative conclusions (no double counting)
- Equipment supports or base packing supplied with the equipment are already inside the equipment installation consumption (DB11/T 2382-2024 clause 6.7.5) and may not be listed as separate support / packing line items.
- The fan installation consumption already includes 'cleaning, scraping and assembling couplings and fittings, piping and lubrication and cooling devices integral with the body, and installing couplings, belts, vibration dampers and safety guards' (clause 6.1.34); the damper installation cost must not be counted twice (the principal material is priced separately into equipment / principal material costs per the design).
- The per-'unit' vibration pedestal line items already synthesise the plinth concrete with steel fabrication and painting; equipment support or plinth concrete line items may not be added.
- Under the BOQ basis, the work content of equipment installation items already includes supports, hangers and base steel sections with painting (GB/T 50856-2024 clause 3.0.10) and, absent special design requirements, no separate listing is allowed; grouting is likewise included (clause 3.0.9).
7. Anti-vibration arrangements of floor-standing versus suspended equipment compared
| Split item | Floor-standing equipment (steel vibration pedestal + concrete plinth) | Suspended equipment (hanger + vibration-damping hook) |
|---|---|---|
| Metal supports | Equipment support line items by weight (railway FY-2675/2676, unit 100kg); or dedicated vibration pedestal line items by equipment weight 'per unit' (DB11/T C1-6-105 to 109; the two are mutually exclusive) | Equipment supports by each support weight (C7-1-173/174, unit 10kg); fan hangers by fan model 'per unit' (clause 6.7.24) |
| Concrete part | Plinth / equipment foundation goes to civil works, listed in m3, reinforcement and formwork priced separately (railway FY-471 to 476 already include formwork) | Usually no concrete foundation; hanging-point embeds and expansion-bolt anchoring are inside the hanger line item work content |
| Isolation elements | Isolators / isolation pads as principal materials priced separately (railway: 'dampers priced separately'); rubber isolation pads 'per group', isolation pad line items 'per piece' (C1-6-102) | Vibration-damping hooks (isolators) priced 'per piece'; where the applied fan installation line item already includes isolator installation (clause 6.1.34), only the principal material is priced, not the installation again |
| Secondary grouting | Yes: under the mechanical equipment installation basis (clause 6.7.1) / railway FY-477 | None |
| Painting and anti-corrosion | Inside the support / pedestal line items (GB/T 50856-2024 clause 3.0.10); with special design requirements listed separately under Annex M | Same as left; liner category and whether a damping test is done are stated in the item description (Annex N.2.4) |
Applicability boundaries
- The railway basis (TB/T 10831-2024 Volume 10 Building Works), the Beijing consumption standard (DB11/T 2382-2024) and the national BOQ (GB/T 50856-2024, GB/T 50854-2024) are different pricing systems and can only be used as complete sets within one system; when borrowing line items across systems, check the work content differences (especially whether formwork is synthesised and whether the pedestal already contains the plinth concrete).
- 'Vibration pedestal billed whole per unit (Beijing)' and 'steel pedestal per kg + plinth to civil works (railway)' are two mutually exclusive routes and must not be mixed; within one estimate, declare the system relied upon.
- This card fixes line item attribution and measurement bases only; rates and percentages must be computed from the quota edition and base-date prices agreed in the contract.
- Where the design imposes special requirements on supports (prefabricated supports, seismic supports, special liners, damping test requirements), list separately under Annex N / Annex M and describe in the item description; the fallback rule 'already included in equipment installation' no longer applies.
- Where the hanging points of suspended equipment involve post-installed rebar in the structure, or openings and strengthening through floor slabs, that is civil or structural strengthening scope, not a ventilation and air-conditioning hanger line item.
Further reading
- TB/T 10831-2024 'Railway Works Budget Quota Manual, Volume 10: Building Works', volume notes, Chapter 3 Building Services Works: Section 3 ventilation and air-conditioning works, 1. air-conditioning components and equipment supports, item 2 (fan vibration-damping pedestals), 2. ducts, item 4 (floor-standing supports), 3. rules of measurement; Section 4 others (system commissioning, scaffolding); Chapter 1 Section 5 concrete and reinforced concrete works, '(2) Equipment foundations' FY-471 to FY-477; Chapter 3 Section 3, '1. Installation of ventilation and air-conditioning equipment and components', (8) equipment support fabrication and installation FY-2675, FY-2676.
- DB11/T 2382-2024 'Construction Consumption Standard', section 6.7 ventilation and air-conditioning installation works: clauses 6.7.1, 6.7.4, 6.7.5, 6.7.24, 6.7.31; section 6.1 mechanical equipment installation works: clauses 6.1.34, 6.1.37, 6.1.38, 6.1.39, 6.1.53 to 6.1.56; section 6.3 static equipment and process metal structure fabrication and installation works: clauses 6.3.6, 6.3.37 to 6.3.51 (table 6.3.38 labour-material-plant proportions of process metal structure fabrication and installation); Annex C table C.1.43-3 vibration isolation pedestals (C1-6-105 to 109), table C.7.12-1 equipment support fabrication and installation (C7-1-173, C7-1-174), C1-6-102 isolation pad (support point), C10-4-2 installation of general pipe supports.
- GB/T 50856-2024 'General Installation Works Measurement Standard' clauses 3.0.9 and 3.0.10, Annex A.14.2, Annex N.2.4, Annex M Painting, Anti-corrosion and Insulation Works.
- GB/T 50854-2024 'Measurement Standard for Building and Decoration Works' Annex E.7.2 (cast in-situ reinforced concrete foundations and frame-type equipment foundation listing).
- SJG 77-2020 'Standard for the division of billed work sections and preliminaries in building works cost documents' clause 6.1.8 (concrete equipment foundations listed under civil works).