Pricing-attribution rules for equipment foundations, secondary grouting, and vibration-isolation devices: BOQ caliber vs quota caliber
Equipment concrete foundations belong to civil works and are priced separately; the installation work content already includes base channel steel (GB/T 50856-2024 Clause 3.0.10), listed separately per kg under Appendix N only with special design. Secondary grouting is already included in the equipment installation work content at the BOQ level (Clause 3.0.9) and not listed separately, but some quota items exclude grouting, requiring a grouting item applied and merged into the all-in unit rate. Vibration-isolation devices are listed with equipment installation — installation included, main materials counted separately.
Applicable Codes
- GB/T 50856-2024 通用安装工程工程量计算标准
- SJG 111.3-2022 城市地下综合管廊工程消耗量标准
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
- DB11/T 2382-2024 建设工程施工消耗量标准
- GB 50738-2011 通风与空调工程施工规范
Topic Positioning
This card covers the attribution judgment of "whether equipment foundations, secondary grouting, and vibration-isolation devices are priced separately" in installation BOQ pricing — the key is distinguishing the BOQ caliber from the quota caliber, and the civil-works from the installation interface.
Core Conclusions
(1) Equipment concrete foundations belong to civil works, priced separately by the civil specialty, outside the installation scope. What the installation work content includes is the base channel steel — GB/T 50856-2024 Clause 3.0.10 makes clear that the work content of equipment, pipeline, and accessory installation items includes the fabrication, installation, and painting of supports, hangers, and base channel steel, not charged separately; only with special design requirements is it listed separately per kg under Appendix N Table N.1.1 "supports/hangers, base channel steel" (code 031301005). (2) Secondary grouting has two layers: the BOQ caliber (GB/T 50856-2024 Clause 3.0.9) — except where machinery installation works already note grouting, the work content of other equipment items shall include the grouting needed to complete the items; the BOQ does not list it separately, the cost merging into the equipment installation all-in unit rate; the quota caliber — some installation quota items exclude grouting, e.g., the SJG 111.3-2022 machinery installation chapter explanation explicitly excludes anchor-bolt holes and foundation grouting, special leveling irons, and equipment foundation grouting; then a grouting item must be applied (e.g., TB/T 10831-2024 FY-477 equipment foundation secondary grouting, Beijing DB11/T 2382-2024 A-5-55 concrete/A-5-56 grouting material) and merged into the all-in unit rate. (3) Vibration-isolation devices are listed with the equipment installation item features (vibration-isolation form); the installation cost is already included in the equipment installation work content, while isolators, isolation pads, and isolation bases are counted separately as main materials per the design configuration (or included in the equipment supply price, per the contract).
Applicable Boundaries
Applies to installation BOQ pricing (the GB/T 50856-2024 system). Whether equipment foundations are built by the civil general contractor follows the contract interface agreement; industry quotas such as railway (TB/T 10831-2024 FY-471~476 cast-in-place equipment foundations) contain foundation items, charged by specialty attribution. Whether a grouting item is applied depends on whether the applied quota item's work content includes grouting — check each item's work content before pricing; no one-size-fits-all.
Further Reading
GB/T 50856-2024 Clause 3.0.9 (grouting work content), Clause 3.0.10 (supports, hangers, base channel steel), Appendix N Table N.1.1; SJG 111.3-2022 Volume 3 Chapter 1 machinery installation works, chapter explanation (list of grouting exclusions); TB/T 10831-2024 Volume 10 Section 5 equipment foundations (FY-471~477); DB11/T 2382-2024 Appendix A other components A-5-55/A-5-56; for vibration-isolation installation requirements see GB 50738-2011 Clause 10.8.3, and vibration-isolation form features see GB/T 50856-2024 Appendix G HVAC works Table G.1.1.
Keywords
- 设备基础
- 二次灌浆
- 减振装置
- 基础型钢
- 另行计价
- all-in unit rate
- GB/T 50856-2024
- 灌浆子目