Cost attribution of lifting and positioning of HVAC (building services) equipment: included in the plant cost of the equipment erection line items vs itemised separately as preliminary items, and the charging and rate build-up connection of the super-height inefficiency coefficient where the erection height exceeds 6m
Lifting costs are attributed on two tests: routine lifting within the plant deployment of a quota line item is not charged separately - it sits in the equipment erection BOQ all-in unit rate (GB/T 50856-2024 cl. 4.1.3 states that the work content of billed items includes the on-site transport of materials and equipment); heavy-piece lifting needing a dedicated scheme (special cranes, lifting strengthening, temporary supports, secondary cartage, mobilisation and dismantling of large plant) goes to preliminary items (Annex P Table P.1.1, code 031401). Where the erection height exceeds 6m, the lifting inefficiency is charged as the labour consumption of the corresponding item multiplied by a coefficient (0.10 within 10m, 0.20 within 30m, 0.50 within 50m, DB11/T 2382-2024 cl. 6.1.2 and cl. 6.7.2), merged into the divisional works all-in unit rate - labour only is adjusted, with no separate super-height item.
Applicable Codes
- DB11/T 2382-2024 第6.1.2条及Table 6.1.2、第6.7.2条、第6.7.1条
- GB/T 50856-2024 第4.1.3条、App. P Table P.1.1(措施项目,编码 031401)
Topic positioning
This card answers one question only: where the lifting and positioning costs of air-conditioning / ventilation equipment belong - whether they are already in the equipment erection quota line item (the BOQ all-in unit rate) or must be charged separately as preliminary items - and how the inefficiency caused by lifting shows up in the labour cost when the equipment erection height exceeds 6m. The three-way price split of anti-vibration bases, equipment hangers and concrete equipment foundations is a separate question with its own rules (see the companion card) and is not expanded here.
Core conclusions
Two tests: (1) lifting within the plant deployment of the quota line item is not charged again; (2) heavy-piece lifting beyond the quota's contemplation goes to preliminary items. Plus one labour-only rule: where the erection height exceeds 6m, multiply the labour consumption by the super-height inefficiency coefficient and merge the result into the divisional works all-in unit rate.
| Lifting scenario | Cost attribution | BOQ coverage | Quota / rate build-up coverage | Basis |
|---|---|---|---|---|
| Routine lifting and positioning of equipment (lifting plant within the line item's plant deployment: winches, hydraulic forklifts, A-frames etc.) | Erection side | Not listed separately; included in the equipment erection BOQ all-in unit rate | No extra line item - the equipment erection line item's machine-shifts already include the lifting plant | GB/T 50856-2024 cl. 4.1.3: 'for the billed items of Annexes A to P of this standard, the work content includes, unless otherwise stated, the on-site transport of materials (semi-finished and finished), components or equipment'; the line item's plant deployment is the quota basis |
| Out-of-range heavy-piece lifting (special cranes, lifting strengthening, temporary support frames, secondary cartage, mobilisation and dismantling of large plant per an approved dedicated scheme) | Preliminary items | Listed separately per item | Charged separately | GB/T 50856-2024 Annex P Table P.1.1 preliminary items (code 031401) |
| Labour inefficiency from lifting at an erection height over 6m | Erection side (labour inefficiency, not a preliminary item) | Not listed separately; merged into the corresponding divisional works all-in unit rate | Multiply the labour consumption of the corresponding item by the super-height inefficiency coefficient: 0.10 within a 10m working height, 0.20 within 30m, 0.50 within 50m | DB11/T 2382-2024 cl. 6.1.2 and Table 6.1.2; cl. 6.7.2: 'where equipment or materials in ventilation and air-conditioning erection works are installed above 6m, the labour inefficiency caused by super-height work shall follow cl. 6.1.2 of this standard' |
| Secondary re-handling and positioning adjustment of bases / supports needed for the lifting plant to complete the positioning | Erection side | Not listed separately | Already included, not charged again (auxiliary content is included in the work content by default) | Work-content inclusion principle; DB11/T 2382-2024 cl. 6.1.1: plant erection consumption includes the erection of auxiliary equipment connected to the plant body, supports, protective guards and the like, temporary moves of water and power sources, assistance with inspection and acceptance, adjustment, testing and single-machine trial runs etc. |
Rate build-up sequence (no gaps or overlaps against vibration isolation and foundations): concrete equipment foundation (civil side, per the relevant items of building and decoration works, DB11/T 2382-2024 cl. 6.7.1) -> structural steel base / equipment supports / hangers (erection side, by weight or count) -> vibration isolation elements (principal materials charged separately) -> lifting and positioning (already in the equipment erection line item, no extra plant charge) -> super-height inefficiency coefficient adjusting labour -> grouting (per the relevant items of plant and machinery erection works, as an extra line item merged into the all-in unit rate) -> out-of-range heavy-piece lifting listed separately under preliminary items.
Three red lines against double charging: (1) the same lifting must not be charged both in the plant cost of a divisional works line item and again as a 'lifting fee' in the preliminary items; (2) the super-height adjustment touches labour only, not materials or machine-shifts, and once adjusted by coefficient no separate 'super-height fee' item may be listed; (3) the mobilisation and dismantling of large plant in the preliminary items is a one-off cost of plant transfer and erection / dismantling and does not include the positioning of the lifted equipment - the two cannot substitute for each other.
Applicable boundaries
- The precondition of 'included in the line item' is that the plant deployment of the applied equipment erection line item already covers the lifting method in the project execution plan; only once the plan adopts a lifting process outside the quota's contemplation (special cranes, twin-crane lifts, lifting strengthening, temporary supports) does the excess go to preliminary items, with an approved construction scheme as the measurement basis.
- The measurement and pricing of preliminary items follow the current BOQ pricing standard (unit-rate, lump-sum or percentage-rate pricing); the divisional works percentage rates must not simply be borrowed.
- The trigger height of the super-height inefficiency is an erection height over 6m (the building services coverage), different from the civil side's 'additional cost for super-high-rise building work' banded by eave height / storeys; the two must not be interchanged; the coefficient bands are within 10m / 30m / 50m, and the part beyond 50m needs separate agreement.
- The plant deployment content varies with the consumption standard adopted (discipline volume, edition); before pricing, check whether the line item's machine-shifts already include the lifting plant - this card gives the attribution tests, not unverified line-item codes.
Further reading
- DB11/T 2382-2024 'Construction consumption standard for building works', cl. 6.1 general provisions (cl. 6.1.1 content of erection consumption, cl. 6.1.2 and Table 6.1.2 super-height inefficiency coefficient table); cl. 6.7 general provisions (cl. 6.7.1 attribution of foundation casting and grouting, cl. 6.7.2 reference for the HVAC super-height inefficiency).
- GB/T 50856-2024 'Quantity take-off standard for general building services works', cl. 4.1.3 (on-site transport included in the work content), Annex P Table P.1.1 preliminary items (code 031401, covering mobilisation and dismantling of large plant, lifting strengthening, temporary supports, secondary cartage etc.).
- Companion checks: the trigger heights and coefficient bands of super-height inefficiency in erection works (the 'super-height fee'; the erection coverage starts at 5m/6m vs the civil coverage at 20m / eave height); the three-way boundary among vertical transportation, super-height work additions and the mobilisation and dismantling of large plant.