Dividing the cost boundaries of vertical transport (011703), super-high construction increase (011704) and entry-exit and erection/dismantling of large plant and machinery (011705), with tests against double counting, the eave-height and storey thresholds, and the quota chapter mapping

The three charges have three different cost objects. Vertical transport (011703) covers the machine-shifts of large vertical-transport plant and the attendant labour (measured by gross floor area or by the calendar days of the construction period). Super-high construction increase (011704) covers only the efficiency loss, the pressurisation pump machine-shifts and the vertical communication caused by excessive height (measured by the gross floor area of the super-high portion), and does not count the machinery machine-shifts again. Entry-exit and erection/dismantling of large plant and machinery (011705) is a one-off charge for machinery transport and transfer and for erection and dismantling, counted by the number of machines (machine-trips); tower crane and hoist bases and track laying and removal are counted separately. The super-high increase is triggered where the eave height of a single-storey building exceeds 20m or a multi-storey building exceeds 6 storeys (basement storeys not counted); reaching either the height or the storey criterion suffices.

Applicable Codes

  • GB 50854-2013 房屋建筑与装饰工程工程量计算规范 App. S Table S.3/S.4/S.5
  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. R R.2.3
  • GB/T 50500-2024 建设工程工程量清单计价标准 App. E Table E.3.4
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 Ch. 1 第八节(FY-1023~FY-1028)
  • 湖南2025 房屋建筑与装饰工程消耗量标准 第二十章、第二十一章
  • 江苏省2026 建筑与装饰工程消耗量标准 第十九章、第二十章
  • 陕西新编消耗量定额(征求意见稿)七、八

Topic scope

In BOQ and quota pricing, the three charges among the preliminaries - vertical transport (011703), super-high construction increase (011704) and entry-exit and erection/dismantling of large plant and machinery (011705) - are often miscalculated, mutually included or double counted. This card gives the cost-object breakdown of the three, the dividing rules that prevent double counting, and the eave-height / storey thresholds and the chapter and quota line item mapping across the quota systems.

Core conclusions

1. Three different cost objects, not three names for one charge

Code Name Cost substance Measurement basis
011703 Vertical transport machine-shift consumption of large vertical-transport plant (incl. the attendant labour) by gross floor area, or by the calendar days of the construction period
011704 Super-high construction increase labour and plant efficiency loss from excessive height + pressurisation pump machine-shifts + vertical communication by the gross floor area of the super-high portion of the building
011705 Entry-exit and erection/dismantling of large plant and machinery one-off cost of machinery transport and transfer and of erection and dismantling by the number of machines used (machine-trips)

Basis: GB 50854-2013 Annex S, Table S.3 (vertical transport, 011703), Table S.4 (super-high construction increase, 011704), Table S.5 (entry-exit and erection/dismantling of large plant and machinery, 011705).

2. Boundary 1: vertical transport vs super-high construction increase - split by work content, no mutual inclusion

Railway TB/T 10831-2024, Volume 10 Building Works, Section 8, gives the clearest split in two work-content descriptions:

  • Mechanical vertical transport (FY-1023 to FY-1025), work content: 'the machine-shifts of vertical-transport plant and external hoists, and the labour attendant on them, needed to complete within a reasonable construction period all the civil items contracted for the unit project.'
  • Building super-high increase (FY-1026 to FY-1028), work content: 'the efficiency loss of workers travelling up and down, the added time of climbing, natural rest and of being affected by vertical transport, the machinery efficiency loss caused by the labour efficiency loss, and the pressurisation pump machine-shifts incurred by insufficient water pressure.'

Rule: the machine-shifts of tower cranes, builder's hoists and external hoists and their attendant labour go only into vertical transport; the super-high portion takes only the efficiency loss (by coefficient or by the gross floor area of the super-high portion), and the same machinery machine-shifts must not be counted again in the super-high increase; pressurisation pump machine-shifts for insufficient water pressure belong to the super-high increase, not to vertical transport. The notes to Chapter 20 of Jiangsu 2026 list the exclusions directly: 'the super-high efficiency loss of buildings does not include vertical transport of the building works, transport and erection of members, combined scaffolding, elevator shaft scaffolding, chimney and water-tower scaffolding, or the fabrication of site-precast concrete and steel members.'

3. Boundary 2: vertical transport vs the work sections - large plant only

GB/T 50854-2024 Annex R, Clause R.2.3: 'vertical transport in this annex includes only the large vertical-transport plant used during construction. Vertical transport performed with other lifting plant and manual aids is included in the work content of the corresponding work sections.' That is, lifting plant, manual handling and small tools are already inside the all-in unit rates of the work sections, so listing vertical transport again is double counting.

4. Boundary 3: entry-exit and erection/dismantling of large machinery (011705) - by machine-trip, with no overlap with vertical-transport machine-shifts

  • Definition (Shaanxi new consumption quota, draft for comments): 'the entry-exit and erection/dismantling cost of large machinery refers to the machinery transport and transfer costs incurred in moving the machinery as a whole or in parts from its parking yard to the site or from one construction site to another, together with the labour, materials, machinery, trial-run costs and the cost of auxiliary facilities needed for installation and dismantling on site.' Transport is by machine-trip and distance, erection and dismantling by count, and the cost already includes the trial run after erection.
  • Anti-double-counting criterion against vertical transport (Jiangsu 2026 Chapter 19, note 1): the vertical transport chapter 'does not include off-site transport of machinery, first installation, dismantling, road-bed bedding and track laying and removal. The bases of construction tower cranes and hoists, and the connections of tower cranes and hoists to the building, are calculated separately.' These must therefore be taken under 011705, and conversely, where entry-exit / erection-dismantling is already inside the all-in unit rate of vertical transport it must not be listed again under 011705.
  • Detail on bases and track: tower crane track laying and removal is priced for straight tracks, curved laying multiplying the item by 1.15; fixed bases apply to tower crane bases of up to 60m3 of concrete, beyond which the concrete, formwork and rebar works are measured separately; where piling is needed for a fixed base, the piling cost is calculated separately (Shaanxi draft). The erection and dismantling cost of diesel pile drivers already includes track erection and dismantling.
  • The erection and dismantling cost of self-climbing tower cranes is set at a tower height of 45m; where the tower exceeds 45m and the eave height is no more than 200m, the item cost rises by 10% for each 10m of added tower height, remainders under 10m counted as 10m (Shaanxi draft).
  • GB/T 50500-2024 Annex E, Table E.3.4 'breakdown of large machinery entry-exit and erection/dismantling costs', notes: 1. where the same large machinery has different entry-exit prices, list items separately; 2. where the manufacturer has special requirements, they may be stated in the remarks column.

5. Prerequisites for the super-high construction increase (011704) - three tests

  1. Trigger (either one): eave height of a single-storey building over 20m, or more than 6 storeys for a multi-storey building; in counting storeys, basements do not count. Reaching either the height or the storey indicator suffices (Jiangsu 2026 Chapter 19 note 3: 'the items of this chapter are bounded by the two indicators of eave height and storeys; reaching either one suffices to apply the item'; Chapter 20 super-high efficiency loss applies where 'the structural height from the design outdoor ground to the floor slab exceeds 20m or the storeys exceed 6'). Hunan 2025 Chapter 21 notes: 'where the eave height of a building exceeds 20m, the super-high increase is calculated under this consumption standard.'
  2. Definition of eave height (Table S.3 note and Table S.4 note, same wording): 'the height from the design outdoor ground to the drip edge of the eave (for flat roofs, the underside of the roof slab); lift machine rooms, stair exit rooms, water tank rooms, watchtowers and smoke extraction rooms projecting above the main roof do not count.' Counting roof machine rooms, tank rooms and stair exits into eave height is the most frequent over-classification error.
  3. Different eave heights in one building: divide vertically by eave height, measure the gross floor area of each part separately, and code and price items separately for each eave height (Table S.4 note; Hunan 2025 Chapter 21 note 2 says the same).

The calculation base varies by region: Hunan 2025 finish works Chapters 11 to 17 multiply the 'labour cost plus plant cost' of the quantities above the 20m eave height by the super-high increase coefficient, while other chapters measure by the gross floor area above the 20m eave height; Jiangsu 2026 takes the 'labour cost' of the portion above 20m (or above 6 storeys) as the base of the super-high efficiency loss.

6. Thresholds and chapter mapping by system (take one system's criteria; no cross-system grading)

System Chapter of vertical transport Grading of vertical transport Chapter of super-high increase Grading of super-high increase
National BOQ GB 50854-2013 Annex S (2024 edition GB/T 50854-2024 Annex R) Table S.3 (011703) by gross floor area or by the calendar days of the construction period Table S.4 (011704) from the '20m / 6-storey' threshold, by the gross floor area of the super-high portion
Railway TB/T 10831-2024 Volume 10 Building Works, Chapter 1 civil works, Section 8 'vertical transport and super-high increase', item 1 mechanical vertical transport FY-1023 eave height over 20m up to 30m; FY-1024 over 30m up to 40m; FY-1025 each 10m added above 20m eave height (per 100m2) same section, item 2 building super-high increase FY-1026 eave height over 20m up to 40m; FY-1027 over 40m up to 60m; FY-1028 each 10m added (per 100m2)
Hunan 2025 consumption standard for building and finish works Chapter 20 vertical transport works builder's hoists per machine-day, other vertical transport per 100m2; eave heights beyond the scope of the quota calculated separately Chapter 21 super-high increase eave height over 20m; finish chapters 11 to 17 by labour cost plus plant cost times a coefficient, other chapters by the gross floor area above 20m
Jiangsu 2026 consumption standard for building and finish works Chapter 19 vertical transport works either 'eave height' or 'storeys' reaching the threshold suffices; single-storey buildings under 3.6m eave height, detached basements and walls with vertical transport height under 3.6m excluded Chapter 20 super-high efficiency loss of building works height from outdoor ground to floor structure over 20m, or over 6 storeys
Shaanxi new consumption quota (draft for comments) vertical transport (incl. re-decoration reusing existing hoists or manual transport via stairs measured as incurred; separately tendered finish works applying the finish-work vertical transport items whatever the structural type) graded by structural type and eave height building super-high increase projects with eave height over 20m, being the cost added by reduced labour and plant efficiency; separately tendered finish works applying the finish-work super-high items whatever the structural type

Note: within one system the grading boundaries of vertical transport and of the super-high increase differ (railway vertical transport grades at 20/30/40m, the super-high increase at 20/40/60m); a grade read from one table must not be applied to the other. The per-machine-trip rules of 011705 (transport by trip and distance, erection and dismantling by count, bases and track separate) are cited here only as anti-double-counting conditions.

Applicable boundaries

  • The codes 011703/011704/011705 come from GB 50854-2013 Annex S; that standard has been replaced by GB/T 50854-2024, Standard for Measurement of Quantities of Work for Housing Construction and Decoration (Annex S -> Annex R); the 2024 note that vertical transport 'includes only large vertical-transport plant' matches the 2013 edition, but the codes and tables must be verified against the current text.
  • The chapters, grading boundaries and calculation bases of the industry and local quotas differ markedly (railway per 100m2, Hunan finish works by labour plus plant cost times a coefficient, Jiangsu by the labour cost of the portion above 20m); one project uses one system's criteria only.
  • This card covers building and finish (civil) works and railway building works; the starting heights of the 'working above ground' charge in installation works differ (of the order of 5m / 6m), so the 20m / 6-storey thresholds here must not be applied.
  • The boundaries above settle that one charge may not be counted twice; the pricing methods of the preliminaries (unit rate / lump sum / percentage rate) and the adjustment rules on variation follow the pricing standard.

Further reading

  • GB 50854-2013, Code for Measurement of Quantities of Work for Housing Construction and Decoration, Annex S (preliminaries): Table S.3 vertical transport (011703), Table S.4 super-high construction increase (011704), Table S.5 entry-exit and erection/dismantling of large plant and machinery (011705), with the table notes (definition of eave height, the single-storey over 20m / multi-storey over 6 storey trigger, separate listing for different eave heights).
  • GB/T 50854-2024, Standard for Measurement of Quantities of Work for Housing Construction and Decoration, Annex R (preliminaries), Clause R.2.3 (note on the scope of vertical transport).
  • GB/T 50500-2024, Standard for BOQ Pricing of Construction Works, Annex E, Table E.3.4, breakdown of large machinery entry-exit and erection/dismantling costs, with its notes.
  • TB/T 10831-2024, Railway Works Budget Quota Manual, Volume 10 Building Works, Chapter 1 civil works, Section 8 vertical transport and super-high increase: item 1 mechanical vertical transport (FY-1023 to FY-1025); item 2 building super-high increase (FY-1026 to FY-1028), with their work contents.
  • Hunan 2025 consumption standard for housing construction and finish works: Chapter 20 vertical transport works, Chapter 21 super-high increase (notes and measurement rules).
  • Jiangsu 2026 consumption standard for building and finish works: Chapter 19 vertical transport works, Chapter 20 super-high efficiency loss of building works (notes and measurement rules).
  • Shaanxi new consumption quota (draft for comments): item 7 building super-high increase; item 8 entry-exit and erection/dismantling of large machinery (incl. tower crane and hoist bases, track laying and removal, the tower-height setting of self-climbing crane erection costs and the super-high increase percentage).