Definition, BOQ item (011601002) and cost composition of vertical transport: the pricing vehicle for machine-shifts of large vertical handling plant and their attending labour; a preliminaries item priced as a lump sum per item and held fixed; and its boundary against the plant costs of work items (concrete pumping, extra height for concrete placing)
Vertical transport cost is the price of BOQ item 011601002 'vertical transport' in the preliminaries bill, covering only the machine-shifts of large vertical handling plant during construction (tower cranes, builder's hoists / external hoists, material hoists and the like) plus the plant-mounted and attending labour; vertical transport done with other lifting plant or manual aids is already included in the work content of the relevant work items and must not be charged again (GB/T 50854-2024 Appendix R.2.3; GB/T 50860-2024 Appendix C.2.3). The item work content covers mobilisation and demobilisation with erection and dismantling of the plant, fabrication and installation of anchorage devices and bases, laying and removal of tracks for travelling plant, and plant operation and use; pricing follows GB/T 50500-2024 clause 3.2.1, 'the preliminaries bill is preferably priced on a lump-sum basis', priced per item, with the composition entered per Appendix E schedule E.3.2 'composition detail analysis sheet for preliminaries items', held fixed under clause 3.3.7 and not re-measured or adjusted under clause 7.3.1 (save for variations, provisional-sum works not fully foreseen, employer causes and other statutory events).
Applicable Codes
- GB/T 50854-2024 · Standard for measurement of building construction and fitting out works App. R(Table R.1.1 措施项目,编码 011601;R.2.3 垂直运输)
- GB/T 50860-2024 · Standard for Measurement of Quantities of Structures Works App. C(C.2.3 垂直运输)
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 3.2.1、3.2.6、3.3.7、4.2.5、6.2.6、7.3.1 条,App. E Table E.3.2
- TB/T 10831-2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works) Ch. 1第五节(混凝土泵送及超高增加)、第八节(垂直运输及超高增加)
- SJG 181.5-2024 · Consumption Standard for Municipal Works (Volume 5) (Shenzhen) 第 3.1.16 条
- 江苏省建筑与装饰工程消耗量标准「垂直运输」章说明
- 湖南省房屋建筑与装饰工程消耗量标准第二十章「垂直运输工程」说明
Topic positioning
This card answers 'what vertical transport cost is and what it comprises': the definition boundary (large vertical handling plant only), the BOQ item and work content (011601002), the pricing method (preliminaries items priced as a lump sum per item), the composition detail (labour / materials / plant and small tools / overheads and profit / risk), the fixed-price and adjustment rules, and the boundary against the plant costs of work items (concrete pumping, extra height for concrete placing).
Core conclusions
1. Definition (standard text)
- GB/T 50854-2024, Measurement Standard for Building and Decoration Works, Appendix R.2.3: 'This appendix, Vertical Transport, covers only the large vertical handling plant used during the construction process. Vertical transport performed with other lifting plant or manual aids is included in the work content of the relevant work items.'
- GB/T 50860-2024, Measurement Standard for Structures Works, Appendix C.2.3: 'This appendix, Vertical Transport, covers only the large vertical handling plant used during the construction process; vertical transport performed with other lifting plant or manual aids is included in the work content of the relevant work items.'
- In sum: vertical transport cost = the machine-shift cost of large vertical handling plant (tower cranes, builder's hoists / external hoists, material hoists and the like) plus the plant-mounted and attending labour etc., incurred within a reasonable duration to complete all construction content of the unit works - the price of one preliminaries BOQ item, not the whole cost of 'lifting materials up'.
2. BOQ item and work content (GB/T 50854-2024 table R.1.1, preliminaries code 011601)
| Item code | Item name | Unit | Work content as tabulated |
|---|---|---|---|
| 011601001 | Scaffolding | item | erecting scaffolds, ramps and loading platforms, spreading safety nets, etc. |
| 011601002 | Vertical transport | item | mobilisation and demobilisation with erection and dismantling of vertical handling plant; fabrication and installation of anchorage devices and bases; laying and removal of tracks for travelling plant; operation and use of equipment, etc. |
| 011601003 | Mobilisation, demobilisation, erection and dismantling of other large plant | item | installation, testing, trial running and dismantling of large plant other than vertical handling plant |
Basis gap (a high-frequency trap in practice): at BOQ level, 'mobilisation and demobilisation with erection and dismantling of vertical handling plant, anchorage devices and bases, track laying and removal' sit inside the work content of 011601002; most provincial consumption-standard chapters on vertical transport exclude these from the line items and require separate computation - the current Jiangsu building and decoration consumption standard states 'plant off-site transport, first erection, dismantling, roadbed bedding and track laying and removal are not included; the costs of tower-crane and hoist bases and of tying the tower crane and hoist to the building are computed separately'; the current Hunan building and decoration consumption standard likewise provides that 'the vertical handling plant consumption items exclude tower-crane and builder's-hoist mobilisation, erection and dismantling, bases, roadbed bedding and track laying and removal, which are computed separately when incurred'. The municipal basis (SJG 181.5-2024 clause 3.1.16) is the same: vertical transport items cover plant operators, attending labour, power and fuel, but exclude plant hire, off-site transport, erection and dismantling and track laying and removal, with tower-crane bases and ties to the structure computed separately. Principle: what the quota excludes must be gathered into the 011601002 item (or, where local rules so provide, into a separate large-plant mobilisation item); take it at one end only - never both inside the vertical transport item and again in another preliminaries item.
3. Pricing method (GB/T 50500-2024 clause 3.2.1, text) 'Within the works bill and the preliminaries bill, items priced on a unit-rate basis are computed as the quantity multiplied by the all-in unit rate; items priced on a lump-sum basis are priced per item. The works bill is preferably priced on a unit-rate basis; the preliminaries bill is preferably priced on a lump-sum basis. The all-in unit rate of works-bill items shall allow for the reasonable risk cost of the item. Works-bill and preliminaries-bill items priced on a lump-sum basis may be priced per item. Where the tenderer agrees in the contract that a dedicated method statement for high-risk works must have passed expert panel review, unit-rate pricing may be used, with the item listed in the works bill and priced as the quantity multiplied by the all-in unit rate.' -> vertical transport is priced 'per item' at BOQ level, in principle a lump sum; its price is built up from the composition detail, not settled directly as floor area multiplied by a unit rate.
4. Composition detail (vertical transport cost = the price of item 011601002)
| Component | Content | Inclusion boundary |
|---|---|---|
| Labour cost | plant-mounted operators and attending labour: tower-crane drivers, builder's-hoist (external hoist) drivers, material-hoist operators, signal and direction staff etc. | Included. In the railway TB/T 10831-2024 Volume 10 Section 8 mechanical vertical transport items, the item with eaves height over 20 m and up to 30 m carries plant cost only and no labour, while the items for over 30 m and up to 40 m and 'each extra 10 m above 20 m eaves height' do list attending labour (labour cost), reflecting attending labour on external hoists and the like at high levels |
| Material cost | amortised materials - track sleepers, track spikes, wire ropes, lubricants, wiping materials - and power / fuel consumption (entered as materials or plant per the quota basis) | Included; take per the material column of the chosen quota items |
| Plant and small tools cost (plant cost) | machine-shift depreciation / hire of tower cranes, builder's hoists and material hoists, operation and use; plant mobilisation transport, first erection and dismantling, fabrication and installation of bases and anchorage devices, laying and removal of travelling tracks | Entered under 011601002; but check the quota chapter notes: off-site transport, erection and dismantling, bases and track laying and removal 'computed separately' in the quota shall be merged into this item's all-in rate or listed separately per local rules - neither omitted nor duplicated |
| Overheads, profit and agreed risk cost | taken with the rate build-up on the all-in-rate basis (labour + materials + plant and small tools + overheads + profit + risk within the agreed range and band, excluding VAT) | Included; for preliminaries items priced as a lump sum it appears 'per item', with the detail split in schedule E.3.2 |
| Form | GB/T 50500-2024 Appendix E schedule E.3.2, 'composition detail analysis sheet for preliminaries items' | percentage-rate pricing fills the 'calculation base', 'percentage rate' and 'price' columns; lump-sum pricing may fill 'price' only |
5. Fixed-price scope and adjustment boundary (GB/T 50500-2024)
- Clause 3.2.6: pricing of preliminaries items shall meet the tender documents and contract and the provisions of the national and sectoral measurement standards on preliminaries items and their work content, including, without limitation, the costs of performing the contract and completing the works: 1 temporary facilities on and near the site, temporary water and power, ventilation and extraction and similar; 2 measures for working in underground space (basements, dark rooms, stores, tunnels), high-rise or super high-rise buildings, health-hazardous environments, severe climates, winter and rainy seasons, and cross operations; 3 tidying material storage areas, boosting water for the works, draining rain and waste water from construction, removing and disposing of construction and household waste (except where listed in the demolition and renovation works bill), protecting finished work, final cleaning and site clearance; 4 costs of meeting the safety requirements of government authorities, including the consequential safety-provision costs; 5 apart from the preliminaries costs adjustable under clauses 8.3.2 and 8.3.4, the measures needed to deliver provisional-sum items; 6 other preliminaries costs incurred in performing the contract. And expressly: as this standard and the national and sectoral measurement standards can hardly itemise exhaustively or describe the work content completely, the contractor shall allow comprehensively for the preliminaries costs of performing the contract and completing the whole works.
- Clause 3.3.7: the preliminaries method statement priced by the contractor at tender is deemed reasonable, feasible and suited to the actual construction requirements; its preliminaries cost is a fixed price, and the contractor bears the risk of extra cost from its own changes of method; only extra cost from variations, from provisional-sum works not fully foreseen or described, or from employer-caused delayed use, dismantling and alteration, addition or re-provision of preliminaries items is adjusted under Chapter 8; extra cost from an infeasible tender proposal or inability to implement is borne by the contractor.
- Clause 7.3.1: save as otherwise agreed in the contract and as listed below, the priced preliminaries items in the BOQ are not re-measured or adjusted - 1 preliminaries works listed in the works bill and preliminaries items the contract makes measurable follow clauses 7.2.1 and 7.2.2; 2 the statutory work safety levy follows the contract; 3 preliminaries changes caused by variations follow clause 7.4.4; 4 preliminaries changes caused by BOQ errors and omissions follow clauses 8.2.2 and 8.2.3; 5 preliminaries changes caused by works within provisional sums not fully foreseen or described follow clause 7.7.2. The preliminaries cost of specialist subcontract works within provisional sums for nominated specialist works is already inside the subcontract lump sum and is not re-measured; whatever supplements to preliminaries items or prices were made at tender, preliminaries items are not re-measured or adjusted - except that where provisional sums are spent at the employer's request on works not fully foreseen or described, on variations, works interference, discovery of relics and like events, the corresponding preliminaries cost is measured and adjusted.
- Clause 4.2.5 (preparation): the preliminaries bill shall be prepared in light of the actual tendered works and the departmental rules, per conventional construction technology and sequence and the non-entity requirements of living, safety, environment, temporary facilities and site tidiness, following the preliminaries classification and supplementary rules of the national and sectoral measurement standards together with the tender documents and contract conditions; statutory safety-provision items are set per the administrative requirements of the state, provincial and sectoral authorities and the actual tendered works. Tenderers may inspect the site, re-check the completeness and fitness of the items, and decide at their own discretion whether to add items and prices.
- Clause 6.2.6 (pricing): tenderers price the preliminaries bill at their own discretion on their own implementation scheme and tendered duration and the preliminaries items framed under clause 6.1.5, the statutory work safety levy complying with the state, provincial and sectoral rules; the price shall allow for the character of the tendered works and the section division and delivery standards, the ground conditions and neighbouring buildings / site facilities / surrounding roads / traffic / hydrology / environment, the contract liabilities stated in the tender documents, the contractor risk allocated in the tender documents, the goods supply and main-contracting attendance for employer-provided materials, and the contractor risk arising from the fixed-price preliminaries.
6. Boundary against the plant costs of work items
- Large vertical handling plant (tower cranes, builder's hoists, material hoists) -> preliminaries item 011601002.
- Vertical transport by other lifting plant (spot lifts by mobile cranes etc.) or by manual aids -> already included in the work content of the relevant work items, not charged again (Appendices R.2.3, C.2.3).
- Concrete pumping is not vertical transport: railway TB/T 10831-2024 Volume 10 puts 'concrete pumping, pump truck / concrete pumping, stationary pump' (work content: erection and dismantling, cleaning, tidying and stacking of pumping pipes, positioning of the (truck-mounted) pump, conveying concrete, clearing up) in Chapter 1 Section 5, Concrete and Reinforced Concrete Works, separate from Section 8, Vertical Transport and Extra Height - a plant cost within concrete works (work items), which must not be charged again under the vertical transport preliminaries item.
- Two 'extra heights' not to be conflated: Section 5's 'extra height for concrete placing above 4.5 m, each extra 1 m (columns / beams / walls / slabs)' is the extra height of the placing operation, within concrete works; Section 8's vertical transport and extra-height items computed by building eaves height (each extra 10 m above 20 m eaves etc.) are the preliminaries basis. Apply by quota chapter; never take both under one 'extra height' label.
- Structures and municipal bases likewise: vertical transport items cover plant operation and attending labour and power only; plant hire, off-site transport, erection and dismantling and track laying and removal are computed separately and gathered into the vertical transport item (SJG 181.5-2024 clause 3.1.16).
Applicability boundaries
- Definition and BOQ work content follow GB/T 50854-2024 (building and decoration) and GB/T 50860-2024 (structures); municipal, railway, highway and other sectors have their own measurement standards and budget quotas - check item setting and chapter attribution against the sectoral standard; no direct cross-sector application.
- Code 011601002 is the 2024 basis and differs from the preliminaries coding of the 2013 building measurement code; where old and new coexist, verify the standard edition before citing codes.
- 'Lump-sum fixed' is not absolutely unadjustable: only the events listed in clauses 3.3.7 and 7.3.1 - variations, provisional-sum works not fully foreseen or described, employer-caused delayed use / dismantling and alteration / addition / re-provision, BOQ errors and omissions and the like - are adjusted under Chapters 7 and 8; increases from the contractor's own method changes or infeasible proposals are borne by the contractor.
- The statutory work safety levy is constrained by the state, provincial and sectoral rules (clauses 4.2.5 and 6.2.6) and is not freely discountable within the lump sum.
- This card carries no regional unit rates or quota base prices: build prices from the current consumption-standard item base prices at the project location and the machine-shift rates at the preparation date; do not carry figures across regions or editions.
- The measurement rules for vertical transport (gross floor area by eaves-height bands, structures per unit or by volume) and machine-shift demand estimation are outside this card - see the companion cards.
Further reading
- Definition and items: GB/T 50854-2024 Appendix R (table R.1.1 preliminaries, code 011601; R.2.3 vertical transport notes); GB/T 50860-2024 Appendix C (table C.1.1; notes C.2.3).
- Pricing and adjustment: GB/T 50500-2024 clauses 3.2.1 (pricing method), 3.2.6 (content of preliminaries costs), 3.3.7 (fixed price and adjustment), 4.2.5 (bill preparation), 6.2.6 (tender pricing), 7.3.1 (no re-measurement of contract preliminaries and the exceptions); Appendix E schedule E.3.2 'composition detail analysis sheet for preliminaries items' (with E.3.1 pricing sheet, E.3.3 cost split sheet, E.3.4 large-plant mobilisation detail sheet).
- Sectoral / local bases: SJG 181.5-2024 clause 3.1.16 (municipal water-treatment vertical transport inclusions / exclusions); TB/T 10831-2024 Volume 10 Chapter 1 Section 5 'concrete pumping and extra height' and Section 8 'vertical transport and extra height'; Jiangsu Building and Decoration Consumption Standard and Hunan Building and Decoration Consumption Standard, vertical transport chapter notes (item split indicators, plant configuration, separately computed items).