Computing vertical transport cost and machine-shift demand: the quota-item route (floor area x structure x eaves height), the shift-estimation route (hoisted quantities of each trade x conversion indices), the hire-per-machine-day route - with the 3.6 m charging test, plant configuration factors and local consumption-standard values
Vertical transport is a preliminaries item covering large vertical transport plant only (tower cranes, builder's hoists, material hoists); vertical movement by other hoisting plant and manual aids sits inside the divisional work content and never double-charges (GB/T 50854-2024 Annex R; GB/T 50860-2024 Annex C). Three routes to cost and shifts: (1) quota items - cost = floor area / 100 x the item base price (yuan per 100 m2), banded by structure and eaves height; (2) shift estimation where plant types are unset - shifts = sum of (hoisted quantity x conversion index), cost = shifts x shift rate; (3) hire per machine-day for cranes and hoists. Charging test first: eaves height (structure height) 3.6 m or less - no vertical transport charge; walls and structures (chimneys, towers and silos excepted) over 3.6 m charge 5% of the labour consumption of the part above 3.6 m.
Applicable Codes
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. R 措施项目
- GB/T 50860-2024 构筑物工程工程量计算标准 App. C 措施项目
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
- 湖南省2025版房屋建筑与装饰工程消耗量标准(第二十章 垂直运输工程)
- 江苏省2026版建筑与装饰工程消耗量(垂直运输章)
- 《建筑安装工程工期定额》TY01-89-2016
Topic Positioning
The three routes to vertical transport cost and machine-shift demand in building works - quota items (floor area x structure x eaves height), shift estimation (hoisted quantities x indices where plant is unset), and hire per machine-day - plus the charging test (eaves 3.6 m), plant configuration factors and local consumption values. For budgets, low-rise worked examples and quick cost checks.
Core Conclusions
1. Pricing boundary (may it charge at all) Vertical transport is a preliminaries item covering large vertical transport plant only (tower cranes, builder's hoists, material hoists); movement by other hoisting plant and manual aids sits inside the divisional work content - never double-charged (GB/T 50854-2024 Annex R; GB/T 50860-2024 Annex C).
2. Charging test (the 3.6 m line)
- Hunan 2024 standard (2025 edition in the source data), chapter 20 notes: eaves or structure height within 3.6 m - no vertical transport charge; the chapter suits buildings of 150 m eaves or less; above 150 m compute per the actual method statement.
- Jiangsu 2024 standard (2026 edition in the source data): single-storey buildings under 3.6 m eaves, stand-alone basements and walls under 3.6 m transport height - no shifts; walls and structures (chimneys, water towers and silos excepted) over 3.6 m charge 5% of the labour consumption above 3.6 m.
- Railway TB/T 10831-2024 Volume 10 section 8: single-storey buildings within 3.60 m - none; the mechanical items assume a normal method statement and adjust only by express provision; superheight items suit single-storey over 20 m eaves and multi-storey over 6 storeys.
- Charging height datum: quota eaves height usually runs from design outdoor ground; a stated "interior-exterior level difference" completes it (eaves height + difference = charging eaves); if the given eaves already run from outdoor ground, add nothing. Both datums falling in one band changes neither item nor test.
3. Route 1: quota items (by floor area) Cost = floor area / 100 x item base price (yuan per 100 m2), banded by structure type and eaves height. Buildings compute by structure and eaves on floor area including basements (TB/T 10831-2024 Volume 10 section 8); above 20 m eaves, superheight runs per additional 10 m - over 5 m counts 10 m, 5 m or less none - charged on the superheight floor area. Hunan: within 24 m or 6 storeys, the "other vertical transport" items (comprehensive, per m2 of floor area). Jiangsu: items band on eaves AND storeys, either indicator sufficing; "cast-in-place frame" = fully cast columns, beams, slabs - part-precast x 0.96; fully cast frame-tube and frame-shear follow the frame items, tubes follow shear walls (slipformed); single-storey sheds with precast roof trusses take precast bent items whatever the columns; precast concrete buildings take the precast items with crane models adjusted per the method statement.
4. Route 2: shift estimation (plant types unset) Shifts = sum over trades of (hoisted quantity x index); cost = shifts x shift rate (yuan per machine-shift). Indices take their own bases (per 100 m2 floor / per 10 m3 / per t) - mixed bases never compute together. The Hunan chapter-20 note 7 indices:
- Tower cranes: comprehensive scaffolding 0.03 shift per 100 m2 floor; masonry 0.28 per 10 m3; foundations and blinding by crane 0.28 per 10 m3 concrete (concrete 0.245, formwork 0.035); beams, slabs, columns, walls 0.56 per 10 m3 (0.28 + 0.28); other concrete members 1.12 per 10 m3 (0.56 + 0.56); rebar 0.05 per t; doors and windows 0.23 per 100 m2; floors, walls, ceilings 0.15 per 100 m2 developed finish; roofs (planted-roof items above the rigid course excluded) 0.1 per 100 m2 of sheeting; tiled roofs 0.175 per 100 m2.
- Builder's hoists: within 100 m, 0.875 shift per 100 m2 floor; within 150 m, 1.0.
- Separately tendered decoration without cranes: on labour, by eaves - under 40 m 4.5%, 60 m 5%, 80 m 5.5%, 100 m 5.7%, 120 m 6%, 140 m 7.8%, 160 m 8.5%, beyond 160 m 9.5%.
5. Route 3: hire per machine-day Cranes and hoists compute by hire per machine-day (Hunan rules); the standards exclude mobilisation, erection and dismantling, foundations, subgrade bedding and track laying - charged as occurring; machine foundations follow the method statement or the quota annexes. Jiangsu the same: the chapter covers shifts, high-pressure pump amortisation and communications within the quota period, excluding off-site transport, first erection, dismantling, bedding and tracks, crane and hoist foundations and building ties - charged separately.
6. Plant configuration and hire period (for checking estimates) Hunan: above 24 m or 6 storeys, one tower crane per unit work plus one hoist from level 6; per extra 1500 m2 of ground floor beyond the first 1500, one extra 800 kN.m crane; precast buildings take the ordinary items with the model switched to 2500 kN.m; at least one hoist per unit work (dwellings, classrooms and dormitories one per 800 m2 single storey, extra beyond; others one per 1500 m2). Hire periods per the Building and Installation Duration Quota (TY01-89-2016); with cranes, hoist time deducts the sub-level-6 duration. Jiangsu: one machine over several eaves heights (storeys) - no adjustment; different machines - separate durations; one crane shared by two or more buildings - each unit computes its own, the shared shifts factored (two buildings 1.15, three 1.20, four 1.35) and apportioned by floor area; several towers over one linked basement - towers per rules, the basement as a stand-alone; the items assume 2 material hoists or 1 crane + 1 hoist - actual counts scale the shift content; hoisting of ordinary precast slabs, hollow cores and small members is inside.
Applicability Boundaries
- The indices and configuration rules are REGION- AND EDITION-SPECIFIC (Hunan 2024 (2025 edition in the source data); Jiangsu 2024 (2026 edition in the source data)); other regions differ - follow the project location's current standard notes and rules; coursework follows the textbook tables.
- Shift estimation approximates at the "plant unset" stage - for budgets and scheme comparison; once an approved method statement fixes models and counts, price the actual shifts - never charge both routes.
- No amounts here: yuan needs two inputs - hoisted quantities (or item base prices in the simplified route) and shift rates (yuan per machine-shift). From outlines alone, only floor-area-based items like comprehensive scaffolding have basis - invent nothing; mark where values would come from (the vertical-transport item base prices; the plant machine-shift cost quota for rates) - never substitute other regions' figures or guesses.
- Eaves from outdoor or indoor ground, and whether to add the level difference, is a regional datum - check the local notes.
- This card prices; measurement by floor area (basements included), structures per unit / volume, and superheight triggers sit on the measurement cards.
Further Reading
- Hunan 2024 building and decoration consumption standard (2025 edition in the source data), chapter 20 "vertical transport" notes (configuration, hire periods, note-7 hoisting indices) and rules.
- Jiangsu 2024 building and decoration consumption standard (2026 edition in the source data), chapter 20 (content boundaries, dual indicators, structure mapping, shared-crane factors, basement and wall rules).
- TB/T 10831-2024 Volume 10, section 8 "vertical transport and superheight".
- GB/T 50854-2024 Annex R (preliminaries); GB/T 50860-2024 Annex C (preliminaries).
- Building and Installation Duration Quota TY01-89-2016 (hire periods).