Engineering Knowledge Cards.
Confidence HighUpdated 2026-11-08

Algebraic decomposition and value chain of the vertical transportation cost (V = SUM of gross floor area / quota unit x line-item base price; c = machine-shift content; q = quota unit / machine-shift content; banding by eave height x structural type x storeys), plus the cross-band conversion and multi-eave-height splitting rules when the eave-height boundary moves

The vertical transportation cost accrues band by band as area x banded unit price: V = SUM_i (Ai / u) x Pi (u is usually 100m2); the base price Pi = SUM(machine-shift content ci,m x plant rate per machine-shift pm) + SUM(workdays ri,l x daily labour rate pl). The machine-shift output quota and the machine-shift content are reciprocals, qi,m = u / ci,m; total machine-shifts Ni,m = (Ai / u) x ci,m. Crossing the base band: V = (A / u) x (P(base band) + k x P(per added band)), where k is the number of added bands derived from the excess height under the carry rule (each added 10m band: where the excess is under 10m, more than 5m counts as one band, 5m or less counts none). For one building with different eave heights, split vertically, measure the gross floor area separately and band each part by its own eave height.

Applicable Codes

  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 Ch. 1 土建工程 第八节 垂直运输及超高增加
  • GB 50860-2013 构筑物工程工程量计算规范 Table C.3 垂直运输(code 070303)
  • GB/T 50854-2024 App. R 措施项目(垂直运输)
  • GB/T 50860-2024 App. C 措施项目(垂直运输)
  • 江苏省建筑与装饰工程消耗量定额(2026版)垂直运输章说明第2、3、4、13条
  • 陕西省新编消耗量定额(2024征求意见稿)第十七章 措施项目 说明第二、三条

Topic positioning

This card breaks the vertical transportation cost out of 'look up and apply' pricing into verifiable algebra: the formula skeleton, the value chain of the variables (eave-height banding x gross floor area x machine-shift content / machine-shift output quota), the corresponding quota line-item codes, and the conversion and combination rules when the eave-height boundary moves (above the base band, per-added-band items, multiple eave heights, beyond the line item's stated coverage).

Core conclusions

I. Formula skeleton (quota line-item method, the primary basis) Vertical transportation is a preliminary item and covers only large vertical transportation plant (tower cranes, builder's hoists, material hoists etc.); vertical movement by other lifting plant and by manual assistance is already included in the work content of the corresponding work items and must not be counted again (GB/T 50854-2024 Annex R and GB/T 50860-2024 Annex C; for structures see Table C.3, code 070303).

  • V = SUM_i (Ai / u) x Pi, where u is the quota unit of measurement; for building-works vertical transportation line items it is usually 100m2
  • Pi = SUM_m (ci,m x pm) + SUM_l (ri,l x pl), i.e. base price = machine-shift content x plant rate per machine-shift (plant cost) + labour workdays x daily labour rate (labour cost)
  • Ni,m = (Ai / u) x ci,m, the total machine-shifts of a given plant type (for checking against hire or actual deployment)
  • qi,m = u / ci,m is the machine-shift output quota (m2 per machine-shift), the reciprocal of the machine-shift content - the conversion bridge between machine-shift output quota and quota base price: a higher machine-shift content means lower efficiency and a proportionally lower q. Example: machine-shift content 7.462 machine-shifts/100m2 gives q approx. 13.4 m2/machine-shift; 11.838 machine-shifts/100m2 gives q approx. 8.4 m2/machine-shift

II. Value chain of the variables

  • H, eave height: from the design outdoor ground level to the drip line of the eaves; for flat roofs, the soffit of the roof slab; for sloped roofs, the intersection of the outer face of the external wall with the soffit of the sloped roof slab; stairwells, lift rooms, tank rooms and roof skylights projecting above the main roof are excluded from the eave height.
  • N, number of storeys: a dual indicator with H; once either indicator reaches the stated threshold, that line item applies (Jiangsu 2026 edition, note 2).
  • S, structural type: brick-concrete / concrete frame (split at 2 storeys, below and above) / concrete bent frame / steel structure (single- or multi-storey) / shear wall / precast etc. Where part is cast in place and part is ordinary precast elements, apply the cast-in-place frame multiplied by 0.96; frame-tube and frame-shear follow the cast-in-place frame, tube structures follow shear wall (slipform) (Jiangsu 2026 edition, notes 9 and 11).
  • A, gross floor area: measured on gross floor area (including basement area); where several buildings share one integrally connected basement, the upper buildings are measured separately and the connected basement follows the dedicated basement line items (Jiangsu 2026 edition, note 6).
  • u = 100m2 (usual); P = line-item base price (base-period price, yuan/100m2); c = machine-shift content (machine-shifts/100m2); p = plant rate per machine-shift (yuan/machine-shift); k = number of added bands.

III. Quota line-item codes as measured (TB/T 10831-2024 Volume 10, Chapter 1, Section 8) I. Mechanical vertical transportation. (1) Eave height within 20m: FY-1015 brick-concrete; FY-1016 concrete frame, up to 2 storeys; FY-1017 concrete frame, above 2 storeys; FY-1018 concrete bent frame; FY-1019 steel structure, single storey, eave height no more than 7m, plus FY-1020 single storey, each 1m added; FY-1021 steel structure, multi-storey, eave height no more than 20m, plus FY-1022 multi-storey, each 1m added. Work content: the vertical transportation machine-shifts needed to complete all contracted items of one structure within a reasonable duration. (2) Eave height above 20m: FY-1023 (20m < eave height no more than 30m), FY-1024 (30m < eave height no more than 40m), FY-1025 (eave height above 20m, each 10m added); the work content of this group includes vertical transportation plant and external hoist machine-shifts together with the crews operating them, so the items for 30m < eave height no more than 40m and for each 10m added carry labour cost, while the 20m < eave height no more than 30m items are all plant cost. II. Additional cost for super-high-rise building work: FY-1026 (20m < eave height no more than 40m), FY-1027 (40m < eave height no more than 60m), FY-1028 (each 10m added); work content covers workers' reduced efficiency commuting, extra time for going up and down and for natural rests, time lost to vertical transportation, plant inefficiency induced by labour inefficiency, and pressurising pump machine-shifts where water pressure falls short - so this group's base price is mostly labour cost with plant cost only a tiny share (a labour-inefficiency type cost, not plant machine-shift cost).

IV. Conversion rules when the eave-height boundary moves

  • R1 Banding: H and N are dual indicators; reaching either one applies that band's line item.
  • R2 Crossing the base band (super-height): V = (A / u) x (P(base band) + k x P(per added band)). Carry rule for each added 10m band: where the height above the base band is under 10m, more than 5m counts as one 10m band and 5m or less counts none. Example: eave height 46m with base band 30m < H no more than 40m gives a 6m excess, so k = 1 and the unit price is P(30~40m) + P(per 10m added).
  • R3 Per-1m-added items: steel single storey (base eave height no more than 7m, FY-1020) and steel multi-storey (base no more than 20m, FY-1022) are priced per 'each 1m added to eave height', not on the 10m carry.
  • R4 Multiple eave heights / multiple structures: where one building has different eave heights, split vertically by eave height, measure the gross floor area separately and apply each band by its own eave height; where the building mixes structure types, measure separately by structure.
  • R5 One machine serving several eave heights: where one project shows two or more eave heights (storeys) served by the same vertical transportation machine, the line item is not adjusted; where different machines are used, measure separately under the current duration norms.
  • R6 Plant quantity differing from the stated deployment: the machine-shift content c may be adjusted pro rata (q moves inversely); where only tower cranes are used and no material hoist, the tower-crane machine-shift content is taken at the material-hoist content and the material hoist is deducted.
  • R7 Beyond the stated coverage: where eave height or storey count exceeds the line item's coverage, calculate separately (compile a supplementary line item or price per the approved construction scheme).
  • R8 Keep it apart from the super-high-rise additional cost: mechanical vertical transportation items cover only the 'lifting'; where the eave height crosses the threshold (single storey above 20m eave height, multi-storey above 6 storeys), the additional cost for super-high-rise building work applies, measured on the gross floor area of the super-high part, one band per 10m added, same 5m carry rule.

Applicable boundaries

  • This card gives the formula structure and conversion logic, not base prices; to reach yuan, two steps are needed: look up the quota base-period price and adjust to the compilation period, and take machine-shift plant rates from the plant rate norms per machine-shift / published construction cost information.
  • Sectors and regions differ in banding and carry rules: building vertical transportation commonly starts at eave height 3.6m (below which nothing is counted) and above the cap (say 150m) pricing follows the actual construction scheme; the estimating indicators of local consumption standards (machine-shifts converted per 100m2 or per 10m3) must not be mixed with this line-item method - one cost takes one path only.
  • Construction organisation conditions already absorbed in the quota (normal plant deployment, reasonable duration) must not be adjusted except as otherwise provided or specially required; a conversion (plant model or quantity) needs a quota basis and must be logged with the 'conversion' mark.
  • Band names (brick-concrete, frame below/above 2 storeys etc.) follow the titles of the quota line items actually applied; when borrowing line items across sectors, the on-costs follow the sector of the quota applied.

Further reading

TB/T 10831-2024 'Railway works budget quota manual, Volume 10, Building works', Chapter 1 civil works, Section 8 vertical transportation and super-high-rise additions: I. mechanical vertical transportation, (1) eave height within 20m FY-1015~FY-1022, (2) above 20m FY-1023~FY-1025; II. additional cost for super-high-rise building work FY-1026~FY-1028. BOQ coverage: GB 50860-2013 Table C.3 vertical transportation (code 070303), GB/T 50854-2024 Annex R, GB/T 50860-2024 Annex C. Eave-height definition and vertical splitting for multiple eave heights: Shaanxi new consumption quota (2024 exposure draft), Chapter 17 preliminary items, notes 2 and 3; dual-indicator banding, one machine over several eave heights, pro-rata adjustment of plant quantity, separate calculation beyond coverage: Jiangsu consumption quota for building and decoration works (2026 edition), vertical transportation chapter notes 2, 3, 4 and 13.

Keywords

  • 垂直运输费
  • 台班产量定额
  • 台班含量
  • 檐高
  • 跨档换算
  • 建筑物超高增加费
  • FY-1025
  • TB/T 10831-2024