Eaves-height banding for vertical transport and super-height additions: the 3.6m / 20m / 6-storey thresholds, the per-10m rule rounding up remainders over 5m, the structure x height two-dimensional banding, and separate banding for multiple eaves heights or structures

Eaves-height banding for vertical transport and super-height additions means 'selecting a line item', not multiplying a rate: no vertical transport for single-storey buildings within 3.6m; the super-height addition starts above 20m (single-storey) or 6 storeys (multi-storey); above 20m one band per 10m, remainders over 5m rounding up to 10m and under 5m not counted; quantities by gross floor area (basements included), the super-height addition on the super-height portion's area only; with several eaves heights, split the area vertically and band each part; reaching either the height or the storey threshold qualifies for the item.

Applicable Codes

  • TB/T 10831-2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works) 册说明第八节「垂直运输及超高增加」一~四
  • GB/T 50854-2024 · Standard for measurement of building construction and fitting out works App. R 措施项目(垂直运输)
  • 江苏省 2026 版建筑与装饰工程消耗量 垂直运输章节说明第 1~14 条
  • 湖南省 2025 版房屋建筑与装饰工程消耗量标准 第二十章 垂直运输工程、第二十一章 超高增加费
  • 陕西省 2024 年新编消耗量定额(征求意见稿)第十七章 措施项目 说明二~四

Positioning

How vertical transport and super-height additions band by eaves height: three thresholds, interval bands, the per-10m rounding rule, and the treatment of multiple heights or structures. About banding edges and rate form - how the height itself is measured is another card.

Core conclusions

1. Three thresholds (railway TB/T 10831-2024 Volume 10, volume note 8)

  1. "Mechanical vertical transport quotas are compiled on conventional project execution plans and, save as otherwise provided or specially required, may not be adjusted." - plant configuration and machine-shift content are not adjustable for actual schemes.
  2. "Single-storey buildings with eaves height within 3.60m take no vertical transport."
  3. "The super-height addition applies to single-storey buildings over 20m eaves height and multi-storey buildings over 6 storeys." - 20m for single-storey, 6 storeys for multi-storey, two separate tests.

2. Banding and rounding (quantity rules of the same note)

  1. "Mechanical vertical transport is computed, by structure and eaves height, on gross floor area (basement included)." - banding variables are structure type x eaves height; area includes basements.
  2. "Above 20m, for the per-10m increment items of vertical transport and the super-height addition, remainders under 10m count as 10m when over 5m and are ignored at or under 5m." - e.g. 26m: the 6m over 20m counts one 10m band; 24m: 4m over, ignored.
  3. "The super-height addition is computed on the gross floor area of the super-height portion." - only that area, not the whole building.

3. Railway band structure (base prices excluded)

  • Within 20m: FY-1015~FY-1022 by structure - brick-concrete; concrete frame (within / over 2 storeys); concrete bents; steel (single-storey up to 7m and per extra 1m; multi-storey within 20m and per extra 1m).
  • Above 20m: FY-1023 (20-30m), FY-1024 (30-40m), FY-1025 (per extra 10m above 20m).
  • Super-height addition: FY-1026 (20-40m), FY-1027 (40-60m), FY-1028 (per 10m). Banding is two-dimensional - structure x height interval, not one price per height; above 20m both "main vertical transport" and "super-height addition" items exist, measured separately, non-fungible.

4. Multiple indicators and heights (local quotas)

  • Jiangsu 2026: items "are defined by eaves height and storey count - reaching either suffices"; "where one project has two or more eaves heights (storey counts) sharing one machine, the item is not adjusted; with different machines, compute separately per the duration quota"; "single-storey buildings under 3.6m, isolated basements and walls with transport height under 3.6m take no machine-shifts"; several buildings sharing one tower crane still compute per unit works, the shared-period machine-shifts factored (two buildings 1.15, three 1.20, four 1.35) and apportioned by area.
  • Shaanxi 2024 draft: "a building with different eaves heights splits vertically by height, areas computed separately and banded by each height; different structures compute separately"; transport and super-height are "computed on gross floor area".
  • Hunan 2025: applies to buildings up to 150m (beyond, per the actual scheme); "no vertical transport cost within 3.6m"; "several heights in one building follow the different vertical heights; basement areas under a tower merge into the tower's area"; within 24m or 6 storeys the "other vertical transport" item applies.

5. Rate form: item selection, not a coefficient

  • Structural super-height additions: super-height area x the band's item (railway; Hunan: "other chapters' super-height additions on the area above 20m eaves").
  • Fit-out runs a factor: Hunan 2025 - "fit-out chapters 11-17 compute the super-height addition as labour + plant x the factor", on the works above 20m.
  • The two are non-interchangeable: area method on super-height area; factor method amplifying only the labour + plant of works above 20m.

6. BOQ boundary

GB/T 50854-2024 Appendix R: "'Vertical transport' covers only large vertical transport plant during construction; vertical transport by other lifting plant and manual aids is inside the corresponding work items." - no extra charge for small hoisting regardless of height bands.

Applicable boundaries

  • The threshold numbers (3.6m, 20m, 6 storeys, per 10m, 5m rounding) are the railway Volume 10's; local quotas differ (storey tests, height caps, factor methods, crane-sharing factors) - band per the governing quota's notes and rules.
  • Wrong height measurement (start, end, roof projections excluded) breaks any banding - fix the height first per the measurement rules.
  • No base prices, machine-shift contents or plant configuration adjustments; no banding for structures (chimneys, water towers, silos, walls).
  • Local quotas are of different vintages - watch version differences across provinces.

Further reading

  • TB/T 10831-2024 Volume 10 volume note 8 sections 1-4 and chapter 1 section 8 items FY-1015~FY-1028.
  • GB/T 50854-2024 Appendix R; GB 50860 Appendix C Table C.3 (code 070303).
  • Jiangsu 2026 vertical transport notes 1-14; Hunan 2025 chapters 20-21; Shaanxi 2024 draft chapter 17 notes 2-4.