Vertical transportation quantity calculation: buildings by floor area (incl. basements) x eave-height steps, structures by count/volume, rules for height-increase fees
Vertical transportation is a preliminaries (measures) item; the BOQ covers only large vertical-transport plant (tower cranes, construction hoists, material hoists etc.) — hoisting plant and manual assistance are already included in the work content of trade items and must not be double-counted. Buildings apply quota items by floor area (incl. basements) with structural type and eave-height steps; single-storey buildings with eaves <=3.6 m are excluded; structures (chimneys, water towers, silos, elevator shafts etc.) are counted per unit; foundations without basements with embedment depth >=4 m and underground water pools are measured by volume per design dimensions; the height-increase fee is computed on the floor area of the super-height portion, with eave height stepped per additional 10 m — remainders over 5 m (but under 10 m) count as 10 m, and 5 m or under is not counted.
Applicable Codes
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准
- GB/T 50860-2024 构筑物工程工程量计算标准
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
Topic Positioning
Vertical transportation is a measures item. Measurement calibers: buildings by floor area (incl. basements) x structure/eave-height steps; structures by count or volume; the BOQ covers only large vertical-transportation plant.
Core Conclusions
- Only large plant counts (tower cranes, construction hoists, material hoists etc.); hoisting and manual handling are already included in trade-item work content and must not be double-counted; mobilization/demobilization and erection/dismantling fees are listed separately.
- Buildings apply quota items by floor area (incl. basements) with structural type and eave-height steps; single-storey buildings with eaves within 3.60 m are not counted.
- Height-increase fee: starts for single-storey eaves >20 m and multi-storey above 6 storeys, computed on the floor area of the super-height portion; eave height steps per additional 10 m — remainders over 5 m (but under 10 m) count as 10 m, 5 m and under not counted.
- Structures: chimneys, water towers, silos, elevator shafts etc. counted per unit; foundations without basements with embedment >=4 m and underground water pools measured by volume per design dimensions; ordinary structures measured by volume.
Applicable Boundaries
BOQ calibers per GB/T 50854-2024 appendix R and GB/T 50860-2024 appendix C; quota calibers differ markedly by industry and region (eave-height threshold and stepping, applicable height caps etc.) — apply the current local quota of the project location. This card covers measurement calibers only, not fee estimation or measures-fee adjustment.
Further Reading
See GB/T 50854-2024 appendix R measures items (vertical transportation, super-height construction addition), GB/T 50860-2024 appendix C measures items (chimneys/water towers/silos by count; foundations embedded >=4 m and pools by volume); railway TB/T 10831-2024 Volume 10 Section 8 vertical transportation (single storey within 3.6 m excluded; starts at 20 m/6 storeys; 10 m rounding).