Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Division of the charging objects among the extra-height formwork support addition, the extra-height construction addition and the vertical transport cost: their mutually exclusive boundaries and the test against double counting

The three fees are charged on three different bases - support height / eave height and storey count / whole-building gross floor area - and do not offset one another: the extra-height formwork support addition charges the labour, materials and plant of the raised support only on the formwork contact area where the support height exceeds 3.60 m (no efficiency loss); the extra-height construction addition charges labour and plant efficiency loss on the gross floor area of the above-threshold portion, and its work content expressly includes 'time affected by vertical transport' and 'plant efficiency loss caused by labour efficiency loss', so the efficiency loss of that portion must not be charged again against formwork quantities or labour days, nor may a separate vertical transport efficiency loss be listed for above-threshold portions; vertical transport charges machine-shifts and their attendant labour, banded by structural type and eave height, on the whole-building gross floor area (including basements), its 'attendant labour' excludes formwork support erection and dismantling labour, and the quota content may not be adjusted save as otherwise provided. Codes follow the edition: under GB/T 50854-2024, concrete formwork is Annex E Table E.5.1 (010505, moved into divisional works) and preliminaries items are Annex R Table R.1.1 (011601 series); the old 011702/011703/011704 system does not apply to 2024-edition projects.

Applicable Codes

  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 册说明第八节(FY-1015~1028)
  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. R Table R.1.1(措施项目,code 011601)、App. E Table E.5.1(混凝土模板,code 010505)
  • DB11/T 2382-2024 建设工程施工消耗量标准 第4.17.1条
  • 湖南省房屋建筑与装饰工程消耗量标准(2025)第二十章垂直运输工程、第二十一章超高增加费
  • 江苏省建筑与装饰工程消耗量定额 垂直运输章节说明
  • 陕西省消耗量定额 超高增加费、垂直运输说明

Topic positioning

The extra-height formwork support addition, the extra-height construction addition and the vertical transport cost often appear together in one building and are the easiest to swallow one another or be double charged. This card enumerates the charging object of each fee, their mutually exclusive boundaries (with negative conclusions), their code allocation, and a table of which fee takes which segment 'for the same floor and the same part', for use in BOQ preparation and budget/settlement review to prevent double counting.

Core conclusions

I. Fix the code edition first (a wrong edition ruins everything after)

  • The old codes 011702 (concrete formwork and falsework), 011703 (vertical transport), 011704 (extra-height construction addition) and 011705 (mobilisation and demobilisation of large plant) belong to the preliminaries system of Annex S of GB 50854-2013; the original text of that edition is not included in the present evidence, so codes used on 2013-edition projects must be checked line by line against the printed or electronic standard and never applied from memory.
  • The current GB/T 50854-2024 text shows concrete formwork under Annex E Table E.5.1 (code 010505), moved from preliminaries into divisional works, and the preliminaries items under Annex R Table R.1.1 (code 011601 series), with vertical transport and the like beneath them. Whether Table R.1.1 of the 2024 edition sets up a separate 'extra-height construction addition' line item must be confirmed against the original table; codes must not be invented before verification.

II. Comparison table of the three fees

Dimension (1) Extra-height formwork support addition (formwork and support item: 010505 / under old 011702) (2) Extra-height construction addition (old 011704 / current Table R.1.1 system) (3) Vertical transport (old 011703 / Annex R Table R.1.1)
Charging object Turnover materials for raising the support system, erection and dismantling labour, and minor on-site plant, where the support height exceeds the 3.60 m benchmark Losses from reduced labour and plant efficiency once the whole building passes the eave-height or storey band (including lower worker efficiency commuting to and from work, added time going up and down floors and on natural rest, time affected by vertical transport, plant efficiency loss caused by labour efficiency loss, and pressurising pump machine-shifts for insufficient water pressure) Machine-shifts of vertical transport machinery and external hoists and their attendant labour consumed in lifting materials, components and turnover materials from the ground to the work face
Trigger / band boundary Support height above 3.60 m, per additional 1 m (less than 1 m counted as 1 m); in some localities, from 6.6 m a two-stage charge of '3.6 m formwork item + separate support' applies instead Single-storey buildings with eave height >20 m, multi-storey buildings >6 storeys; one band per additional 10 m of eave height, where less than 10 m counts as 10 m if it exceeds 5 m, and is not counted below 5 m Banding on the dual indicators of eave height and storey count: within 20 m by structural type (brick-concrete / concrete frame up to two storeys or above / concrete bent / steel structure, single or multi storey); over 20 m up to 30 m, over 30 m up to 40 m, then per additional 10 m; single-storey within 3.60 m eave height not charged
Measurement base Formwork contact area of the portion above 3.60 m (taken as the whole area of the exceeding portion) Gross floor area of the above-threshold portion (railway: calculated on the GFA of the above-threshold portion of the building; Hunan: other chapters use the GFA above 20 m eave height) Whole-building gross floor area (including basement area), with line items banded by structural type and eave height; or by machine-days of plant rental
Quota attribution examples Beijing DB11/T 2382-2024 Clause 4.17.1 item 4, columns/beams/walls/slabs, 'support height above 3.60 m, per additional 1 m' Railway FY-1026 (eave height over 20 m up to 40 m, 100 m2), FY-1027 (over 40 m up to 60 m), FY-1028 (per additional 10 m); Hunan Chapter 21 extra-height addition Railway FY-1015 to 1022 (within 20 m eave height, by structural type), FY-1023 to 1025 (over 20 m up to 30 m, over 30 m up to 40 m, per additional 10 m), unit 100 m2
Exclusions Excludes labour and plant efficiency loss Excludes the materials and erection/dismantling labour of raised supports, and the vertical transport machine-shifts themselves Excludes off-site transport of tower cranes and builder's hoists, first-time erection and dismantling, and bases and track laying and removal (charged separately); excludes labour for raising formwork supports

III. Mutually exclusive boundaries (negative conclusions)

  1. The extra-height construction addition already carries the efficiency loss and it must not be charged again as such. The railway extra-height addition line item states its work content as: 'lower worker efficiency commuting to and from work, added time going up and down floors and on natural rest, time affected by vertical transport, plant efficiency loss caused by labour efficiency loss, and pressurising pump machine-shifts for insufficient water pressure.' Accordingly: (1) the labour and plant efficiency loss of above-threshold portions is charged once on the GFA of the above-threshold portion and must not be converted and charged again against formwork quantities, concrete quantities or labour days; (2) 'time affected by vertical transport' is already inside the extra-height addition, so a vertical transport efficiency loss for above-threshold portions must not be listed as a further line item.
  2. The extra-height formwork support addition and the extra-height construction addition run in parallel without duplication. The former charges the labour, materials and plant of the raised support only on the formwork area above 3.60 m support height; the latter charges the efficiency loss on the GFA of the above-threshold portion; their objects and bases differ, both may be charged, but neither may bleed into the other - no efficiency-loss coefficient may be folded into the all-in unit rate of the extra-height formwork support line item, and the extra-height addition may not be surcharged by segments of formwork contact area.
  3. The line between vertical transport machine-shifts and the extra-height efficiency loss: the eave-height banded vertical transport machine-shifts are normal lifting consumption (including the per-additional-10 m items above 20 m eave height, which are normal quantity charging, not duplication); the 'time affected by vertical transport' inside the extra-height addition is efficiency-loss compensation. Two amounts may appear at the same part, but they are not one duplicated charge - in review, do not delete the banded vertical transport machine-shifts because 'the extra-height addition is already charged', and do not list a separate efficiency loss outside the extra-height addition.
  4. The 'attendant labour' of vertical transport excludes formwork support workers. The railway work content for vertical transport above 20 m eave height reads 'the machine-shifts of the vertical transport machinery and external hoists and their attendant labour required for all the civil works items contracted within a reasonable period for the unit work'; that labour means the crew attached to the vertical transport machinery; the erection and dismantling labour for raised supports in the extra-height formwork sections sits in the formwork item (including the extra-height support line items) and must not be counted as attendant labour of the vertical transport machine-shifts.
  5. The quota content of vertical transport machinery must not be adjusted at will. The railway volume notes say the mechanical vertical transport quota is compiled on a conventional project execution plan and may not be adjusted save as otherwise provided or specially required - that is, the machine-shift content may not be scaled up for high formwork, over-heavy members and the like; where a local quota allows proportional adjustment by plant count (e.g. a shared tower crane apportioned by a building-count coefficient, or machine-shift content swapped where only tower cranes are used without material hoists), the quota notes must be the basis and a record kept.
  6. Cases with no vertical transport charge: railway - single-storey buildings with eave height within 3.60 m carry no vertical transport; some local quotas - single-storey buildings with eave height <3.6 m, and stand-alone basements and fences with vertical transport height <3.6 m, carry no vertical transport machine-shifts. Such parts also generate no extra-height construction addition (below the 20 m / 6-storey band) but may still carry the extra-height formwork support addition (judged independently on a support height above 3.60 m).

IV. Table of segment allocation for the same floor and part

Part / case Vertical transport Extra-height construction addition Extra-height formwork support addition
Single-storey building with eave height up to 3.6 m Not charged Not charged (below the 20 m / 6-storey band) Still charged where support height >3.60 m (regardless of eave height; support height only)
Eave height within 20 m, up to 6 storeys Charged once on GFA x structural type against the within-20 m line items Not charged Portion with support height above 3.60 m charged per additional 1 m
Floors with eave height >20 m or >6 storeys The above-20 m portion banded 20-30 m, 30-40 m and per additional 10 m, calculated on GFA (whole building including basement) Charged once only on the GFA of that above-threshold portion (efficiency loss included) Charged only on the formwork area of that part above 3.60 m; no efficiency loss converted and charged on top
Basement Counted into the GFA for vertical transport (basement area included) Generally not charged (the storey count excludes basements and eave height runs from the external ground level; the quota notes prevail) Support height judged from the top surface of the structural base slab to the floor slab of the storey above
Same floor with both high formwork and extra height The GFA of that floor enters the matching eave-height band once only The above-threshold GFA of that floor charged once only The high-formwork formwork area of that floor charged once only; the two amounts do not offset
Buildings with several eave heights or several towers Calculated separately by vertical height; where one machine serves all, the line items are not adjusted; with different machines, calculated separately under the period quota Split vertically by differing eave heights, the GFA calculated separately for each and the line items applied separately Support height judged separately for each vertical segment

V. Review sequence (concrete steps against duplication)

Step 1, fix the edition (2013 or 2024 list) -> Step 2, check the quantities separately on the three different bases 'support-height band / eave-height and storey band / whole-building GFA' and see whether one area is reused across the three fees (the formwork contact area, the above-threshold GFA and the whole-building GFA should differ in value; identical values mean the bases are being mixed) -> Step 3, check whether the work content of the line items already includes (the efficiency loss, the time affected by vertical transport, the attendant plant labour) -> Step 4, check whether the mobilisation and demobilisation of plant, the bases and the track laying and removal are already inside the vertical transport line items or are duplicated elsewhere.

Applicable boundaries

  • Quota bases differ sharply by industry and region: railways follow Volume 10 of TB/T 10831-2024, building and fit-out works follow the local consumption quotas, and the BOQ basis follows GB/T 50854-2024; the band thresholds (20 m / 6 storeys, 24 m, the 150 m cap), the rounding rules and whether the machine-shift content may be adjusted must all be checked against the quota applicable to the project.
  • This card gives the allocation-and-anti-duplication framework and the sources of the provisions; it does not replace the verification of specific line-item base prices or the calculation of the fees.
  • Whether the 2024 edition sets a separate code for 'extra-height construction addition' must be verified against the original Table R.1.1; the 2013 code system must not be used directly on 2024-edition projects.

Further reading

  • TB/T 10831-2024, Volume 10 Building Works, volume notes Section 8 items one to four (vertical transport compiled comprehensively and not adjustable; single-storey within 3.60 m eave height not charged; the extra-height addition starts from single-storey over 20 m or multi-storey over 6 storeys; calculated on GFA including basements; the rounding rule below 10 m) and the work content of line items FY-1015 to 1022, FY-1023 to 1025 (mechanical vertical transport) and FY-1026 to 1028 (extra-height addition for buildings).
  • GB/T 50854-2024, Annex R Table R.1.1 preliminaries items (code 011601) and Annex E Table E.5.1 concrete formwork (code 010505).
  • DB11/T 2382-2024, Clause 4.17.1 item 4 (support-height banding and the per-additional-1 m rounding).
  • Hunan Consumption Standard for Building and Fit-out Works (2025), Chapter 20 vertical transport notes (applies below 150 m eave height; within 3.6 m not charged; several eave heights calculated separately; excludes the mobilisation, demobilisation and bases of tower cranes and builder's hoists) and Chapter 21 extra-height addition notes and measurement rules (above 20 m eave height; vertical splitting by differing eave heights; fit-out Chapters 11 to 17 apply a coefficient to labour cost + plant cost; other chapters use the GFA above 20 m).
  • Jiangsu Consumption Quota for Building and Fit-out Works, vertical transport chapter notes (work content includes vertical transport machine-shifts, high-pressure pump amortisation and two-way communication; excludes off-site transport and erection/dismantling; execution once either of the eave-height or storey indicators is reached; where eave height or storeys exceed the line-item setting, calculated separately).
  • Shaanxi Consumption Quota notes (the extra-height addition covers the extra cost of reduced labour and plant efficiency on projects over 20 m eave height; separately tendered fit-out works follow the fit-out vertical transport and extra-height addition line items).

Keywords

  • double counting
  • 模板超高支撑增加费
  • 超高施工增加费
  • 垂直运输费
  • 人工机械降效
  • 檐高分档
  • 措施项目编码
  • 011601