Three measurement bases for the added support cost of formwork above the 3.60 m formwork-height threshold, the rules for taking formwork height, and the line-item selection rules
The formwork itself enters the BOQ by contact area with the concrete in m2 (GB/T 50854-2024 Appendix E table E.5.1 concrete formwork, code 010505, no height-excess line item); the added support cost for excess height is priced separately at consumption-standard level under three measurement bases: by the whole area of the excess portion (m2; Beijing DB11/T 2382-2024 from 3.60 m of formwork height, per added 1 m, fractions of 1 m taken as 1 m), by horizontal projected area x support height (m3), or by the mass of the erected falsework (t). Formwork height for columns, walls and slabs runs from the designed exterior ground or slab top to the slab soffit; basements from the top of the structural base slab to the structural floor above; first-floor beams from the exterior ground to the beam top above; storeys from the floor slab (or beam) top to the beam top above; some local quotas provide that where the formwork height of beams and slabs reaches 6.6 m or more, the formwork runs under the 3.6 m items and the support cost is priced under a separate falsework item.
Applicable Codes
- DB11/T 2382-2024 建设工程施工消耗量标准 第4.17.1条、第4.17.6条
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. E Table E.5.1(混凝土模板,code 010505)
- 湖南省房屋建筑与装饰工程消耗量标准(2025)模板章节说明及A19系列子目
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 第八节
Topic scope
The extra cost of a taller support system once formwork height passes the benchmark (generally 3.60 m; some local standards draw the line at 6.6 m) is measured under three different bases at different levels and in different regions. This card answers four questions - how the formwork itself is measured, how the height-excess support cost is added, how formwork height is taken, and when a separate falsework item applies - and marks the boundary against the excess-height works addition (efficiency loss).
Core conclusions
- BOQ layer: formwork itself by contact area in m2, no height-excess item. GB/T 50854-2024 lists concrete formwork in Appendix E table E.5.1 (code 010505, under the measured-works part; the former 011702 belonged to the GB 50854-2013 Appendix S preliminaries system and does not apply to the 2024 edition's items). The BOQ measures formwork by contact area with the cast-in-place concrete member; the height-excess support cost has no separate BOQ line item and must be priced at consumption-standard (quota) level or absorbed into the all-in unit rate.
- Three measurement bases at quota level: (1) by the whole area of the excess portion (m2) - e.g. Beijing DB11/T 2382-2024 clause 4.17.1 item 4: the portion within 3.60 m of formwork height is determined comprehensively without height distinction; the portion above 3.60 m is determined comprehensively at each added 1 m of formwork height, the quantity being the whole area of the excess portion; where the excess is under 1 m, the per-added-1 m item applies. (2) By horizontal projected area x support height (m3, a support-envelope volume basis). (3) By the mass of the erected support frames (t). The three cannot be mixed; the unit must match the quota applied; quotas list 'per added 1 m' line items and distinguish timber from steel supports (e.g. the slab support height above 3.6 m, per each 1 m exceeded, items; surcharge items for curved beams and slabs).
- Taking formwork height: columns, beams, walls and slabs are each determined by formwork height (between the designed exterior ground or slab top and the slab soffit); basements by the height from the top of the structural base slab to the structural floor above; the other storeys by the difference between that floor's structural level and the corresponding upper level; first-floor beams from the exterior ground (interior ground for basements) to the beam top above; storeys from the floor slab (or beam) top to the beam top above. Formwork quantity by contact area: column perimeter x column height; beam length taken to the face of columns, walls and main beams; walls and slabs without deducting single holes up to 0.30 m2; column heads merged into flat slabs; inclined slabs by inclined area (Beijing 4.17.6).
- Closing special case: some local quotas provide that where the formwork height of concrete beams and slabs is 6.6 m or more, the formwork runs under the 3.60 m items (support cost not deducted from them), while the support cost is computed separately under a standalone falsework item - price then in two parts, 'formwork + standalone falsework', and do not stack the height-excess support items on top, avoiding duplicate charges on the same part.
Applicable boundaries
- The height-excess support cost covers only the labour, the consumable support materials (steel tubes, couplers, jacks, adjustable heads, amortisation or hire of timber and steel supports) and the minor on-site machinery needed to heighten the support system; it excludes labour and plant efficiency loss; efficiency loss belongs to the excess-height works addition (single storey over 20 m eave height, or multi-storey over 6 storeys) - different bases (formwork area versus the floor area of the excess portion), charged in parallel, neither containing the other and neither convertible into the other.
- The 3.60 m and 6.6 m thresholds, the rounding (fractions of 1 m as 1 m or as measured), whether comprehensive hire rates are allowed, and whether the falsework is listed separately are all set by industry or local quotas and differ markedly; check the current local quota before pricing - this card is no substitute for verifying specific line-item prices.
- Support contents already comprehended in the quota (timber versus steel differences) must not be converted or adjusted even where they differ from site reality; not applicable to decorative scaffolding height excess or slipformed structures, which carry their own items.
Further reading
Beijing DB11/T 2382-2024 clause 4.17.1 (determination principles for formwork and supports, formwork-height banding and the rounding of fractions under 1 m) and clause 4.17.6 (formwork quantity by contact area and the rules by columns, beams, walls and slabs); Hunan provincial building and decoration consumption standard (2025), formwork chapter notes and quantity calculation rules (the formwork-height algorithm, the standalone falsework for beams and slabs at 6.6 m or more, coefficients for sloped and inclined roofs) and the A19 series height-excess formwork items; GB/T 50854-2024 Appendix E table E.5.1 concrete formwork (code 010505); railway TB/T 10831-2024 volume 10 section 8, work content of the height-excess surcharge items (used to distinguish efficiency loss from support heightening).
Keywords
- 模板超高支撑增加费
- 支模高度3.6m
- 支模高度6.6m
- 超过部分整体面积
- 混凝土模板及支架
- 010505
- 单独支架项目