GB/T 50854-2024 vs. GB 50854-2013, new vs. old edition: mandatory changed to recommendatory, five revision highlights, and the restructuring of preliminary items priced per item
GB/T 50854-2024 'Standard for Measurement of Building and Decoration Works', approved by MOHURD Announcement No. 191 of 2024 and effective 1 September 2025, repeals GB 50854-2013 'Code for Measurement of Building and Decoration Works' simultaneously; the nature changed from a mandatory national standard (GB, with several mandatory provisions of codes) to recommendatory (GB/T), with no more mandatory provisions in the text. Five main revisions: item description (work item specification); units of measurement and method of measurement; work contents; deletion of demolition works and obsolete-process items; and formwork moved into the work-item BOQ with other preliminary items priced per item.
Applicable Codes
- GB/T 50854-2024 · Standard for measurement of building construction and fitting out works
- GB 50854-2013 · Code for Measurement of Quantities of Building and Decoration Works (2025-09-01 起废止)
- 住房城乡建设部公告 2024 年第 191 号(www.mohurd.gov.cn)
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works
Topic Positioning
This card compares the overall differences between GB/T 50854-2024 'Standard for Measurement of Building and Decoration Works' and its predecessor GB 50854-2013 'Code for Measurement of Building and Decoration Works': edition status and repeal, five revision highlights, restructuring of the preliminary items rules, and changes in the boundary demarcation with other measurement standards — for cost engineers choosing the correct measurement basis during the edition transition.
Core Conclusions
1. Edition status and repeal
- The 2013 edition was a mandatory national standard (GB) with several mandatory provisions of codes: General 1.0.3 — 'for the pricing of building and decoration works, the measurement of the works must follow the method of measurement specified in this code ... whether the project is invested with state or non-state funds, its measurement of the works must comply with this code'; 4.3.1 — 'for preliminary items that list item code, item name, item description (work item specification), unit of measurement, and method of measurement, the BOQ shall be prepared per the provisions of Clause 4.2 for work items'.
- The 2024 edition was approved as a national standard by MOHURD Announcement No. 191 of 2024, numbered GB/T 50854-2024, 'effective from 1 September 2025. The former national standard 'Code for Measurement of Building and Decoration Works' (GB 50854-2013) is repealed simultaneously.' Its nature changed to recommendatory (GB/T), the text no longer contains mandatory provisions of codes, and the name changed from 'Code' to 'Standard'. The revision was based on Jian Ban Biao Han [2018] No. 35 and prepared per the spirit of the 'Construction Cost Reform Work Plan' (Jian Ban Biao [2020] No. 38).
2. Five main revisions stated in the 2024 foreword
- Item descriptions (work item specifications) of some BOQ items revised, deleting content unrelated to design documents;
- Units of measurement and method of measurement of some BOQ items revised;
- Work contents of some BOQ items revised to reflect the principal construction processes;
- BOQ items for demolition works and obsolete construction processes deleted, with some items matching current design and construction processes added;
- Preliminary items method of measurement revised — formwork entered the work-item BOQ for computation, and other preliminary items are priced per item.
3. Preliminary items rule restructuring (the biggest substantive change)
- Under the 2013 edition (Appendix S), preliminary items that listed item code, item name, item description (work item specification), unit of measurement, and method of measurement had to follow the work-item provisions (mandatory 4.3.1) — measured by quantity and separately rate-built-up.
- The 2024 edition moves preliminary items to Appendix R, listing only item code, item name, and work contents, with no more method of measurement — priced per item; 2024 Clause 4.3.1: 'in preparing the BOQ, the preliminary items of Appendix R of this standard shall be determined by the prescribed item code, item name, and work contents.'
- Formwork moved from preliminary items into the work-item BOQ; other preliminary items are priced per item.
4. Appendix R preliminary items work-content boundaries (2024 edition)
- Scaffolding: 'includes all scaffolds erected during the works, per relevant code requirements and to meet construction operational needs.'
- Vertical transport: 'covers only the large vertical-transport machinery used during construction. Vertical transport performed with other hoisting machinery and hand-held tools is included in the corresponding work-item contents.'
- Temporary works and site establishment, mandatory health, safety and environmental (HSE) provisions, environmental protection, and work safety: 'the included scope of the work contents shall be supplemented with reference to the provisions of the provinces, autonomous regions, municipalities directly under the central government, or industry construction authorities.'
- 'Preliminary items for which the employer provides design drawings and requires construction accordingly may be listed by reference to work items with supplementary coding.'
5. Boundary changes with other measurement standards
- 2013 Clause 3.0.6: installation works involving electrical, water supply and drainage, fire protection, etc. -> 'Code for Measurement of General Installation Works' GB 50856; antique-style works -> GB 50855; exterior ground (road) surfaces and exterior water supply/drainage -> 'Code for Measurement of Municipal Works' GB 50857; rock excavation by blasting -> 'Code for Measurement of Blasting Works' GB 50862.
- 2024 Clause 3.0.4: installation works involving electrical, water supply and drainage, HVAC, etc. -> 'Standard for Measurement of General Installation Works' GB/T 50856; antique-style -> GB/T 50855; municipal roads, street lighting, and other municipal works -> GB/T 50857; landscape greening works -> 'Standard for Measurement of Landscape Greening Works' GB/T 50858. The companion standards are uniformly renumbered as GB/T, landscape greening is added to the demarcation, and blasting works (GB 50862) are no longer listed in the boundary description.
Applicable Boundaries
- Applies through the edition transition (around 1 September 2025) when preparing BOQs, choosing measurement bases, and checking the bases of old/new cost documents.
- From 1 September 2025 the 2013 edition is repealed; pricing documents prepared or signed earlier per the 2013 edition follow the contract agreements.
- With 2024 preliminary items priced per item, the cost scope of temporary works and site establishment, mandatory health, safety and environmental (HSE) provisions, environmental protection, and work safety must be supplemented per the provisions of provinces, autonomous regions, municipalities, or industry authorities — large regional differences.
- This card covers only the overall edition differences and the preliminary items framework; the specific methods of measurement of work items (earthwork, concrete, rebar, doors and windows, etc.) are on dedicated cards.
Further Reading
- MOHURD Announcement No. 191 of 2024, 'Announcement of the Ministry of Housing and Urban-Rural Development on Publishing the National Standard 'Standard for Measurement of Building and Decoration Works'', public on the MOHURD portal (www.mohurd.gov.cn).
- GB/T 50854-2024 foreword (revision bases Jian Ban Biao Han [2018] No. 35 and Jian Ban Biao [2020] No. 38), Clause 3.0.4, Clause 4.3.1, Appendix R (preliminary items), and commentary R.2.
- GB 50854-2013 Clauses 1.0.3, 3.0.6, 4.3.1 (mandatory provisions of codes).
- Companion document: GB/T 50500-2024, the China national pricing standard for BOQ (GB/T 50500), implemented simultaneously; the method of measurement takes effect through contract agreement.
Keywords
- GB/T 50854-2024
- GB 50854-2013
- 房屋建筑与装饰工程工程量计算标准
- 工程量计算规范
- 新旧版本对比
- 措施项目按项计算
- 模板工程列入分部分项
- 2024年第191号公告
- mandatory provisions of codes