Rock blasting quantity take-off: by pre-blasting natural in-situ (undisturbed) volume (bank measure), and itemization linkage with GB/T 50854-2024 earthworks

Rock blasting BOQ quantities are measured in bank measure (pre-blasting natural in-situ (undisturbed) volume), not loose volume; rock that is not naturally dense converts per GB/T 50862-2024 Table A.5.3 (rock loose 1.54, block stone 1.75, sand-stone mix 1.07). Blasted rock in building BOQs is itemized per GB/T 50862-2024 code 090101 series (GB/T 50854-2024 Appendix A, A.4.14), and per A.4.10 both excavation and backfill ignore densification-state conversion — loose/compacted differences are absorbed by all-in unit rates.

Applicable Codes

  • GB/T 50862-2024 · Standard for Measurement of Quantities of Blasting Works App. A(Table A.1.1、第A.5.3条、Table A.5.3)
  • GB/T 50854-2024 · Standard for measurement of building construction and fitting out works App. A(Table A.1.1、第A.4.10条、第A.4.14条)

Topic Positioning

The volume state (bank/loose) used for measuring rock blasting (surface blasting) BOQ quantities, and the itemization and caliber linkage between GB/T 50862-2024 "Standard for measurement of blasting works" and GB/T 50854-2024 "Standard for measurement of building and decoration works".

Core Conclusions

  1. Measurement caliber: bank measure (pre-blasting natural in-situ (undisturbed) volume). GB/T 50862-2024 Appendix A, A.5.3 original: "In Table A.1.1 of this appendix, 'rock volume' shall be computed as the natural in-situ (undisturbed) volume before blasting; rock that is not naturally dense shall be converted per Table A.5.3." Table A.1.1 rock blasting (code 090101) contains general blasting 090101001, pit blasting 090101002, trench blasting 090101003, cutting excavation blasting 090101004, and boulder blasting 090101005, unit of measurement m3, method of measurement "computed by volume per design dimensions" — i.e., the natural in-situ (undisturbed) volume within the design excavation contour.
  2. Conversion factors (Table A.5.3, non-natural-dense rock back to bank): rock — natural in-situ (undisturbed) 1.00 / loose 1.54 / loosely filled 1.31; block stone — 1.00 / 1.75 / 1.43 / stacked 1.67; sand-stone mix — 1.00 / 1.07 / 0.94. Example: measured loose rock 1540 m3 -> bank = 1540 / 1.54 = 1000 m3.
  3. Linkage with GB/T 50854-2024:
  • A.4.14 original: "Rock blasting works shall be itemized with the codes of the current GB/T 50862 'Standard for measurement of blasting works'." So blasted rock in building BOQs uses 090101-series codes, not the 010101 range of 50854;
  • A.4.10 original: "When computing excavation and backfill quantities of earth and rock, conversion between volumes of different densification states shall not be considered." BOQ quantities are uniformly reported in bank measure; loose/compacted differences stay out of the BOQ quantity and are absorbed by all-in unit rates (quota norms resource consumption layer);
  • Non-blasting rock: Table A.1.1 item 010101002 excavation of rock separately, unit of measurement m3, "computed by volume per the cut/fill dimensions between the original topography and the preset elevation", likewise bank caliber;
  • Blasting item description (work item specification) per Table A.1.1 (crushing requirements, geology/topography, rock class, blasting works grade, blasting environment, etc.).
  1. Corroboration (railway system, same caliber): TB/T 10822-2024 "Railway works budget quota manual (China Railway), Volume 1, subgrade", Chapter 1 notes: "excavation and haulage quantities are measured in natural in-situ (undisturbed) volume", with a bank-to-compacted conversion table (rock range about 0.84-0.941, by design speed class) — used for cut-fill balance conversion; BOQ measurement itself remains in bank measure.

Applicable Boundaries

  • Applies to surface blasting works (GB/T 50862-2024 Appendix A, 090101 series) BOQ measurement, and to itemization/caliber of blasting rock items in building and other lists.
  • Conversion factors apply only when measurement data are non-natural-dense (loose/loosely filled/stacked) to get back to bank; the BOQ quantity itself is always reported in bank, without loose conversion.
  • Not applicable to: non-blasting rock excavation (GB/T 50854-2024 010101002); loose/compacted conversions at the quota norms/pricing layer (absorbed by all-in unit rates and norm resource consumption, not shown in BOQ quantities); blasting types outside Appendix A (tunnel, shaft, and other underground blasting have their own rules).
  • Version note: GB 50854-2013 is abolished; the current GB/T 50854-2024 (MOHURD Announcement No. 191 of 2024, effective 2025-09-01); blasting measurement now rests on GB/T 50862-2024.

Further Reading

  • GB/T 50862-2024 Appendix A (surface blasting): Table A.1.1 (rock blasting, code 090101), A.5.3 and Table A.5.3 (rock volume conversion factors).
  • GB/T 50854-2024 Appendix A (earthworks): Table A.1.1 (separate earth/rock, code 010101), A.4.10 (no densification conversion), A.4.14 (blasting per GB/T 50862).
  • For cut-fill balance conversions, see TB/T 10822-2024 "Railway works budget quota manual (China Railway), Volume 1, subgrade", Chapter 1 notes and the bank/compacted conversion table.