GB/T 50854-2024 foundation earthwork BOQ quantity rules: pit/trench excavation includes working space, excludes sloping; trench-vs-pit division and excavation depth

Per GB/T 50854-2024 Appendix A Table A.2.1, the BOQ quantity of pit/trench excavation = the foundation (including bedding) bottom area per design drawings plus working-space area, multiplied by excavation depth: working-space width enters the BOQ quantity (per Tables A.4.6-1/2 where no design value is given), while the sloping increment does not (sloping is listed in the work content "excavation, sloping (if any)" and is to be allowed for by bidders in the all-in unit rate). Trench = bottom width <= 3 m and bottom length > 3 x bottom width (neither includes working space, A.4.5); excavation depth runs from the preset elevation to the foundation (including bedding) bottom elevation, or to the soil-rock boundary where rock lies below (A.4.7). GB/T 50500-2024 has no "re-measure only beyond some percentage" rule — re-measurable (unit-rate) contracts are re-measured on an item-by-item basis per 7.2.1 (except items priced per lump item); 15% is the boundary for re-rating of unit rates (8.2.1: <= 15% inclusive per 8.9.1, > 15% per 8.9.2).

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准(App. A 土石方工程:Table A.2.1、A.4.5、A.4.6、A.4.7)
  • GB/T 50500-2024 建设工程工程量清单计价标准(第7.2.1、8.2.1、8.9.1、8.9.2条)
  • GB 50854-2013 房屋建筑与装饰工程工程量计算规范(对比参照)

Topic Positioning

This card covers the quantity take-off (measurement) rules for BOQ quantities of foundation earthwork (code 010102) in Appendix A of GB/T 50854-2024 "Standard for measurement of building and decoration works": whether pit/trench excavation quantities include working-space width and sloping increments, the dividing line between trenches and pits, where excavation depth starts, and the "BOQ quantity vs actual constructed quantity difference" treatment basis (re-measurement and the 15% boundary) in linkage with GB/T 50500-2024.

Core Conclusions

  1. BOQ quantity basis (Table A.2.1 pit excavation 010102001): computed by volume as the foundation (including bedding) bottom area per design drawings plus working-space area, multiplied by excavation depth. That is: working-space width enters the BOQ quantity; the sloping increment does not. Table A.2.1 lists the work content as "1. excavation, sloping (if any), retaining-board shoring (if any) 2. loading 3. on-site transport 4. bottom cleaning and edge trimming 5. base tamping 6. base probing" — sloping is a work content item whose quantity increment is to be allowed for by bidders in the all-in unit rate. Key difference from GB 50854-2013: the old version used "bedding bottom area x excavation depth", with neither working space nor sloping entering the BOQ quantity (whether they were merged in was province-specific); the 2024 version explicitly merges working-space area into the BOQ quantity while sloping stays in the work content. When preparing a BOQ under the 2024 version, the old quantity model must not be reused, or a block of working-space quantity will be missed.
  2. Working-space width values (A.4.6): per design requirements; where there are no design requirements, take Tables A.4.6-1 (working-space widths required for foundation construction) and A.4.6-2 (working-space width per side for pipeline trench construction); note: for pipeline structure width, use the foundation outer edge where there is a pipe saddle, or the pipe outer diameter where there is none.
  3. Trench vs pit division (A.4.5): a trench has bottom width <= 3 m and bottom length > 3 x bottom width; beyond that range (bottom width > 3 m, or bottom length <= 3 x bottom width) it is a pit; neither bottom width nor bottom length includes working-space dimensions.
  4. Excavation depth (A.4.7): from the preset elevation to the foundation (including bedding) bottom elevation; where rock lies below, to the soil-rock boundary.
  5. No percentage threshold for "re-measurement": GB/T 50500-2024 has no rule of "re-measure only when the difference exceeds some percentage". Under re-measurable (unit-rate) contracts, per 7.2.1, unit-priced items in the BOQ shall be re-measured on the basis of the actual construction drawings and variation instructions, in accordance with the contracted national and industry measurement standards (items priced per lump item shall not be re-measured or adjusted). 15% is the boundary for re-rating of unit rates: per 8.2.1, quantity changes not exceeding 15% (inclusive) adjust the contract price per 8.9.1 (same construction conditions and same item description: retain the contract unit rate; similar items: adjust by conversion; different items: determine by negotiation), while changes exceeding 15% (exclusive) adjust per 8.9.2 (increased portions reasonably reduce the unit rate in the light of procurement discounts; decreased portions reasonably raise the unit rate).
  6. Dual-track bases: the 2024 BOQ quantity = (bedding bottom area + working-space area) x excavation depth (excluding sloping); quantities under the quota norms (prescribed resource consumption standards) follow the quota-norm rules (usually including sloping, with working space taken per the project execution plan (construction methodology and site organization)). Different bases between BOQ and quota-norm quantities are normal; compute on separate tracks and list items independently.

Applicable Boundaries

  • Applies only to building and decoration works (GB/T 50854-2024 Appendix A); A.4.5/A.4.6/A.4.7 are general supporting bases for Table A.2.1, and the trench/pit division and depth rules apply to all foundation earthwork in this appendix.
  • Industry difference: GB/T 50861-2024 (urban rail transit) does not compute "quantities increased by working space and sloping not explicitly shown in design drawings" — they are included in the work content — the opposite of the building 2024 basis of "working space merged into BOQ quantity"; the two project types' bills of quantities must not be intermixed.
  • This card covers only BOQ quantity bases and division rules; specific values of working-space widths and sloping coefficients (formwork for concrete foundations 400 mm, bedding 150 mm, sloping start for Class I/II soils 1.20 m, etc.) are in the general earthwork excavation computation card.
  • The 15% boundary applies only to re-rating of unit rates caused by errors and omissions in the BOQ and variations under re-measurable (unit-rate) contracts; explicit contract provisions on measurement and pricing prevail. First distinguish the source of the difference: differences between the contract BOQ and the contract drawings are errors and omissions in the BOQ (adjust per 8.2.1); differences between the contract drawings and the actual construction drawings are variations (adjust per 7.4.2 + Section 8.9) — both are re-measured, but the price-adjustment paths differ.

Further Reading

  • GB/T 50854-2024 Appendix A earthwork: Table A.2.1 foundation earthwork (code 010102, including general/pit/trench excavation rules and work content), A.4.5 (trench-pit division), A.4.6 (working-space widths, Tables A.4.6-1 and A.4.6-2), A.4.7 (excavation depth).
  • GB/T 50500-2024 "China national pricing standard for BOQ (GB/T 50500)": 7.2.1 (re-measurement under re-measurable contracts), 8.2.1 (15% boundary for errors and omissions in the BOQ), 8.9.1 (<= 15%: retain/convert/negotiate the unit rate), 8.9.2 (> 15%: re-rating of unit rates).
  • Old-new comparison: GB 50854-2013 Appendix A (bedding bottom area x depth; neither working space nor sloping enters the BOQ quantity); GB 50500-2013 9.4.2 (rigid decrease/increase beyond 15%; the 2024 version changed to flexible, reasonable adjustment).
  • Industry contrast: GB/T 50861-2024 (urban rail transit) A.7.1 — working-space and sloping increments not explicitly shown in the design are not computed, being included in the work content.