Key points for the item description of earthworks BOQ items: how to set soil class and rock class (tables A.4.3-1 and A.4.3-2), the optional dry or wet soil supplement, the geotechnical investigation report as fallback, and the GB/T 50500-2024 compilation requirements for coding, names, descriptions, units and work content plus the itemisation principles
GB/T 50854-2024 A.4.3: soil class and rock class are set per table A.4.3-1 and table A.4.3-2, with dry or wet soil descriptions added where needed; where the class cannot be accurately determined, the description is based on the geotechnical investigation report. Item descriptions, together with coding, item names, units of measurement and work content, must be compiled per the national and industry quantity take-off standards (GB/T 50500-2024 clause 4.1.7); itemisation follows 'clear, unambiguous boundaries, easy to price and pay', with codes preferably ascending (clause 3.1.4); the description entries are governed by the exact wording of tables A.1.1, A.2.1 and A.3.1, and disposal of surplus excavated material is a separate item under table A.3.1, not an incidental entry in the excavation item's description.
Applicable Codes
- GB/T 50854-2024 App. A A.4.3、Table A.4.3-1、Table A.4.3-2、Table A.1.1、Table A.2.1、Table A.3.1
- GB/T 50500-2024 第4.1.7条、第3.1.4条
Topic positioning
How to write the item descriptions of earthworks BOQ items, and at what granularity - this card gives the GB/T 50854-2024 rules for describing soil and rock classes (tables A.4.3-1 and A.4.3-2, dry or wet soil, the geotechnical fallback) and the GB/T 50500-2024 mandatory compilation requirements for item coding, names, descriptions, units of measurement and work content, plus the itemisation principles, for judging 'whether the descriptions are adequate' when preparing and reviewing BOQs.
Core conclusions
1. Rules for describing soil and rock classes (GB/T 50854-2024 A.4.3, verbatim): 'In the item descriptions, soil class and rock class may be set per table A.4.3-1 and table A.4.3-2, with descriptions of dry soil and wet soil added where needed. Where the soil class or rock class cannot be accurately determined, the description may be based on the geotechnical investigation report.' Three implications: (1) class names come from the standard annex tables (table A.4.3-1 soil classification, table A.4.3-2 rock classification) - invented classes are not allowed; (2) dry and wet soil are optional supplements, added when needed, not mandatory entries; (3) where the class cannot be accurately determined, the description is based on the geotechnical report rather than left to the tenderer's judgement on site.
2. Compiling item descriptions is a mandatory requirement (GB/T 50500-2024 clause 4.1.7, verbatim): 'Whether a unit-rate or a lump-sum contract is used, the item coding, item names, item descriptions, units of measurement and work content of the schedule of divisional work items shall be compiled per the national and industry quantity take-off standards and any supplementary BOQ calculation rules; the item coding, item names and work content of the bill of preliminaries shall be compiled per the national and industry quantity take-off standards. When preparing the BOQ, item descriptions shall be given as required; where the bill of preliminaries or the bill of provisional sums and other charges cannot carry item descriptions, work content and item names may be listed instead.' That is: the names and content of description entries come from the annexes of the take-off standards (for earthworks, the item rows of table A.1.1 sole-purpose earthworks, table A.2.1 foundation earthworks and table A.3.1 site levelling and others) and must not be freely added to, dropped or reworded; where preliminaries and other items cannot carry descriptions, work content plus item names substitute. Clause 4.1.7 also allows the BOQ to be ordered by chapters and items in the normal construction sequence, so the contractor can re-check BOQ errors when tendering and pricing, and progress payments and valuation of variations stay easy.
3. Itemisation principles (GB/T 50500-2024 clause 3.1.4, verbatim): 'The BOQ shall be compiled per the item classification, units of measurement and quantity take-off rules of the national and industry take-off standards for the works concerned, on the basis of the design drawings and technical standards, following the principles of unambiguous itemisation, clear boundaries, and ease of pricing and payment; items may be ordered by the normal construction sequence and itemised per the take-off standards, and BOQ codes should run from small to large.' - 'clear, unambiguous boundaries, easy to price and pay' is the overall yardstick for judging descriptions and itemisation; ascending coding is a drafting habit that avoids duplicate and disordered codes.
4. Points on description scope: description entries must match the chosen item row - excavation items are described by soil (rock) class, excavation depth and so on, while disposal of surplus excavated material is resolved as a separate item under table A.3.1 (site levelling and others, code 010103); excavation and spoil disposal are different BOQ items, not handled by an incidental 'spoil haul distance' entry; the concrete description entries must be checked row by row against the 'item description' column of tables A.1.1, A.2.1 and A.3.1, not filled in from memory of the old edition (GB 50854-2013). Missing or inaccurate descriptions are bills of quantities errors; responsibility and price adjustment follow the GB/T 50500-2024 BOQ error rules (employer responsible under unit-rate contracts, contractor under lump-sum contracts, preliminaries always the contractor's).
Boundaries of application
- Applies to preparing and reviewing earthworks (and similar) item descriptions under GB/T 50854-2024; description and line-item bases of local consumption standards and industry quotas follow their own rules.
- Dry and wet soil are optional, added only when the design or the geotechnical report states the moisture state; treating them as mandatory puts the BOQ out of line with the standard.
- Descriptions take the design drawings and the geotechnical report as their factual source; classes must not be guessed from experience; where no geotechnical report exists, state so in the tender documents and agree in the contract how classes are confirmed and adjusted.
- The final list of description entries is governed by the annex tables of the standard; this card gives rules and judgement principles only and does not replace looking up the tables.
Further reading
- GB/T 50854-2024 Annex A: A.4.3 (soil and rock class description rules), table A.4.3-1 (soil classification), table A.4.3-2 (rock classification), and the 'item description' columns of table A.1.1 (sole-purpose earthworks 010101), table A.2.1 (foundation earthworks 010102) and table A.3.1 (site levelling and others 010103).
- GB/T 50500-2024 pricing standard for BOQ of construction works, clause 4.1.7 (compilation requirements for coding, names, descriptions, units, work content) and clause 3.1.4 (BOQ compilation and itemisation principles).
Keywords
- 项目特征描述
- 土类别 岩石类别
- 干土 湿土
- 地勘报告
- 清单列项原则
- 弃土 余方弃置
- 4.1.7 3.1.4