Reviewing tender bills of quantities: methods and criteria for detecting omissions, errors, and duplications

Check the BOQ against four baselines—tender documents, construction drawings, measurement standards, and the pricing standard: omissions via drawing cross-check + standard appendix tick-off + item description derivation + preliminaries check; errors via codes (twelve digits, no duplicate codes within one project), item descriptions (standard, concise, accurate, complete), units and quantities, and work-content attribution (operations must not be split); duplications via duplicate codes, substantively identical items, split-out operations, and overlaps between work items and preliminaries. Per GB/T 50500-2024 Article 4.1.4: BOQ defects are borne by the employer under unit-rate contracts (adjusted per Section 8.2) and by the contractor under lump-sum contracts (not adjusted per Article 6.1.7).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准
  • GB 50860-2013 构筑物工程工程量计算规范
  • DB37/T 5096-2017 建设工程项目管理咨询规范
  • T/CMEA 53-2024 市政基础设施项目全过程工程咨询指南

Topic Positioning

This card provides a complete checking framework for tender-stage BOQ review: how to systematically detect omissions, errors, and duplications—what to check, how, and by what criteria—plus review procedure, for cost consultants, employers (tenderers), and bidders reviewing BOQs.

Core Conclusions

Check one BOQ against four baselines: tender documents, construction drawings, measurement standards, and the pricing standard (GB/T 50500-2024).

  • Omissions: (1) drawing cross-check—sheet by sheet by discipline; on drawing but not in BOQ = omission; (2) standard appendix check—tick off against the division/sub-division tables of the applicable measurement standard appendix; (3) item description derivation—necessary work mentioned in the item description (bedding, leveling, corrosion protection, waterproofing) must have corresponding BOQ items; (4) preliminaries checked against the envisioned project execution plan (construction methodology and site organization).
  • Errors: (1) item codes must be twelve digits—positions 1-9 per the appendix, 10-12 per actual project; no duplicate codes within one tendered project (GB 50860-2013 Article 4.2.2, mandatory provision of the code); (2) item descriptions must be standard, concise, accurate, and complete, sufficient to determine all-in unit rates (GB/T 50854-2024 Article 4.1.2); (3) units and quantities re-verified per measurement rules; (4) work content should include all necessary work—single operations must not be split into separate items.
  • Duplications: screen duplicate codes across the whole table; substantively identical items (different names but same item description/work content) identified by drawing location; operations already included in work content (vibrating, curing) listed separately are duplicates; overlaps between work items and preliminaries resolved to unique attribution per compilation rules. Procedure suggestion: first internal consistency (unique codes, uniform units, subtotals = totals), then table-vs-drawing (omissions/errors), then table-vs-tender (scope, pricing principles, provisional sums consistent with tender documents).

Applicable Boundaries

Applies to tender-stage BOQ compilation/review; each discipline must use its own measurement standard appendix (buildings: GB/T 50854-2024 Appendices A-R); bill of preliminaries defects are the contractor's responsibility under any contract type; this card is a checking-method framework, not a substitute for verifying local pricing bases.

Further Reading

GB/T 50500-2024 Article 4.1.4 (BOQ defect liability), Article 4.1.7 (compilation rules); GB/T 50854-2024 Article 4.1.2 (item descriptions and work content); GB 50860-2013 Article 4.2.2 (mandatory coding rule); review essentials in DB37/T 5096-2017 Article 6.3.2 and T/CMEA 53-2024 Article 10.2.4.