Constituent requirements of BOQ item descriptions and the three common defects (vague description / missing measurable parameters / disconnect from the work process), with corrected drafting (GB/T 50500-2024 clauses 2.0.5, 2.0.27, 4.1.7, 4.2.2, 4.2.4; GB/T 50854-2024 clause 4.1.2)

An item description, by definition (GB/T 50500-2024 clause 2.0.5), is 'a textual description stating the nature and requirements of the BOQ item itself ...'; a description written wrongly falls under clause 2.0.27, BOQ errors (including 'mismatched item description'), and enters the price-adjustment channel rather than mere textual polish. The hard yardstick of accurate description is GB/T 50854-2024 clause 4.1.2 - 'item descriptions must be given accurately and comprehensively ... sufficient to satisfy the need to determine the all-in unit rate' - and they must be 'prepared on the basis of the design documents and in combination with the completion and handover requirements' (GB/T 50500-2024 clause 4.2.2); any parameter whose variation would change labour, material and plant consumption or the basis of percentage charges must be stated, while decorative words that do not change the price are useless if stated.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.5条、第2.0.27条、第4.1.4条、第4.1.7条、第4.2.2条、第4.2.4条、第6.1.6条、第6.1.7条、第8.2.1条、第8.9.1条
  • GB/T 50854-2024 · Standard for measurement of building construction and fitting out works 第4.1.2条、App. E Table E.2.1(现浇混凝土构件,code 010502)

Topic positioning

This card explains how to write the 'item description' column of a BOQ acceptably: first, the constituent requirements a compliant description must meet and their normative basis; second, how to identify and rewrite the three most common drafting defects (vague description, missing measurable parameters, disconnect from the work process). It applies to preparing tender BOQs, reviewing BOQs, tender cross-checking, and characterising 'mismatched description' disputes at settlement.

Core conclusions

1. First fix the nature: a wrongly written description = a BOQ error, not a textual flaw

  • Definition of item description (GB/T 50500-2024 clause 2.0.5): 'a textual description stating the nature and requirements of the BOQ item itself, used to explain the BOQ items required to be completed by the design drawings, the technical standards and the tender documents.'
  • Definition of BOQ errors (GB/T 50500-2024 clause 2.0.27): 'the differences existing between the BOQ items listed in the measured-works BOQ and the BOQ items required by the corresponding contract drawings and contract specifications, in itemisation, item description or quantities, including superfluous items, wrong or missing items, mismatched item descriptions, quantity deviations and other cases of the same kind.'
  • Consequence channel: under a unit-rate contract, clause 4.1.4 provides 'the employer shall bear the responsibility for the relevant BOQ errors, and BOQ errors shall be adjusted under Section 8.2 of this standard'; clause 8.2.1 takes as the boundary whether the increase or decrease in quantities exceeds 15% (15% inclusive) of the quantity contained in the contract BOQ for the corresponding item, adjusting the contract price under clause 8.9.1 or clause 8.9.2 respectively. Under a lump-sum contract, clause 4.1.4 provides 'the contractor shall bear the duty to complete and rectify BOQ errors ... which shall not be adjusted under clause 6.1.7 of this standard' (provisional-quantity items excepted).

2. Constituent requirements of an accurate description (normative basis + key original wording)

Requirement Normative basis Key original wording
(1) Essential nature GB/T 50500-2024 clause 2.0.5 'a textual description stating the nature and requirements of the BOQ item itself ...'
(2) Basis requirement GB/T 50500-2024 clause 4.2.2 'BOQ item descriptions shall be prepared on the basis of the design documents and in combination with the completion and handover requirements.'; under a unit-rate contract 'pricing shall follow the requirements of the item descriptions'; under a lump-sum contract 'pricing shall follow the requirements of the contract drawings and the contract specifications'
(3) Item-by-item requirement GB/T 50500-2024 clause 4.1.7 'whether a unit-rate contract or a lump-sum contract is adopted, the item coding, item names, item descriptions, units of measurement and work content of the measured-works BOQ shall be prepared under the national and sector quantity take-off standards and the supplementary BOQ measurement rules'; 'where the preliminaries bill and the bill of provisional sums and other charges in the BOQ cannot describe item descriptions, the work content and the item names may be listed'
(4) Depth requirement GB/T 50854-2024 clause 4.1.2 'item descriptions must be given accurately and comprehensively and shall meet the requirements of standard, concise, accurate and comprehensive description of item descriptions. The content of item descriptions shall follow the provisions of the annexes to this standard, in combination with the actualities of the proposed works, and shall satisfy the need to determine the all-in unit rate.'
(5) Boundary requirement (item description is not work content) GB/T 50854-2024 clause 4.1.2 'the work content of the items in Annexes A to R of this standard lists only the principal contents; unless otherwise provided or noted, it shall be deemed to include the necessary work required to complete the BOQ item'; 'the construction processes corresponding to the work content shall not, except where specially noted, be split out and listed as separate BOQ items'
(6) Element-level detail requirement GB/T 50854-2024 Annex E clause E.2.1 'the BOQ item setting, the content of item descriptions, the units of measurement and the measurement rules for cast-in-place concrete members shall follow the provisions of table E.2.1' (code 010502)
(7) Special matters requirement GB/T 50500-2024 clauses 4.2.4 and 4.1.4 For employer-supplied (free-issue) materials 'the item description shall state that the main material is provided by the employer'; for provisional material prices 'the item description shall state the amount of the provisional material price'; where the tender drawings cannot support accurate itemisation and measurement 'the item description of the corresponding item of the measured-works BOQ shall state provisional quantities, and the provisional quantities shall be given in combination with the tender drawings'

3. Three common defects and corrected drafting

Class Typical defective drafting Clause violated Corrected drafting
A Vague description 'quality concrete, complying with the specifications and the design requirements'; 'construct per the drawings'; 'brand grade: quality / name brand' Clause 4.1.2 depth requirement: no strength grade / specification / brand-grade criterion, failing 'satisfy the need to determine the all-in unit rate'; clause 2.0.27 constitutes 'mismatched item description' 'C30 ready-mixed concrete, pumped; beam section 300x600'; 'see structural drawing 12, price against the following: C30 pumped concrete, fair-faced formwork'
B Missing measurable parameters Excavation stating only 'excavate soil' without the soil class or the haul distance; rebar without the diameter and the connection method; waterproofing without the thickness and the number of plies Clause 4.1.2: 'follow the provisions of the annexes to this standard, in combination with the actualities of the proposed works' (parameters required by the annexes must not be omitted); clause 4.1.7: item descriptions shall be prepared under the national and sector quantity take-off standards State all measurable parameters per the annexes (soil class, excavation depth, spoil haul distance, rebar type and diameter, connection method); any parameter whose variation changes labour, material and plant consumption or the basis of percentage charges must be stated
C Disconnect from the work process Writing processes such as 'erecting formwork, curing, moving plant, transporting materials' into the item description as separate items; or descriptions contradicting the actual construction method (pumped concrete in the drawings described as non-pumped); forcing pseudo-descriptions where preliminaries or other items cannot be described Clause 4.1.2 boundary requirement: 'unless otherwise provided or noted, deemed to include the necessary work required to complete the BOQ item'; 'shall not be split out and listed separately'; clause 4.1.7: preliminaries and other items that cannot be described 'may list the work content and the item names' Delete the already-included processes; describe only the physical parameters and delivery requirements that define the item and affect the rate build-up; preliminaries and other items switch to work content + item names; where a description contradicts the process in the drawings, revise per the design documents (clause 4.2.2)
D Omitted special-matter notes Employer-supplied materials without noting the supplier; provisional material prices without the provisional amount; quantities written as fixed despite insufficient drawing depth Clauses 4.2.4 and 4.1.4 special matters requirement Note 'main material provided by the employer'; state the provisional unit price of the material; mark the quantity column 'provisional quantity'

4. The yardstick for judging corrections

'Satisfy the need to determine the all-in unit rate' is the operable hard yardstick: any parameter whose variation would change the labour, material and plant consumption or the basis of percentage charges must enter the item description; purely decorative adjectives with no price effect and no criterion (quality, beautiful, imported and similar expressions without a benchmark) shall not serve as item descriptions. Depth follows the four-word requirement of clause 4.1.2, 'standard, concise, accurate, complete' - neither omitting parameters to the point of preventing rate build-up, nor piling processes and auxiliary work into the description and causing double counting.

Boundaries of application

  • This card addresses item descriptions in the measured-works BOQ; the preliminaries bill and the bill of provisional sums and other charges, where item descriptions cannot be given under clause 4.1.7, list the work content and the item names instead, and the 'must describe' requirement does not apply.
  • The consequences of defective descriptions divide by contract pricing mode (unit-rate contract: on the employer/tenderer, adjusted under Section 8.2; lump-sum contract: in principle completed and rectified by the contractor without adjustment, provisional-quantity items excepted); responsibility is determined under clauses 4.1.4, 6.1.6 and 6.1.7 - this card only resolves 'how to write acceptably'.
  • The specific parameters to be described for each element follow the annexes of the sector quantity take-off standards (for building and decoration works see the BOQ tables of the corresponding elements in GB/T 50854-2024 Annexes A to R); this card does not replace the item-by-item parameter lists of the annexes.
  • Descriptions must accord with the contract drawings and the contract specifications; if a change in the design documents means the description should read otherwise, the design change procedure must be followed first - 'correcting the description' must not be used to bypass a variation.

Further reading

  • GB/T 50500-2024 (national BOQ pricing standard): clause 2.0.5 (item description), clause 2.0.27 (BOQ errors), clause 4.1.4 (error responsibility by contract type and provisional quantities), clause 4.1.7 (basis of BOQ preparation), clause 4.2.2 (descriptions based on the design documents and the completion requirements), clause 4.2.4 (employer-provided materials and provisional material prices), clauses 6.1.6 and 6.1.7 (tender cross-check and lump-sum completion and rectification), clauses 8.2.1 and 8.9.1 (adjustment of the contract price for errors, the 15% boundary, and determination of all-in unit rates).
  • GB/T 50854-2024 (quantity take-off standard for building and decoration works): clause 4.1.2 (item description requirements, the scope included in work content and non-splitting of processes), Annex E clause E.2.1 and table E.2.1 (cast-in-place concrete members, code 010502) and the item-description columns of the BOQ tables of each element.
  • Checking path: first compare, item by item, against the 'item description' column of the corresponding BOQ table in the annexes of the sector standard for missing parameters; then re-check the depth of description by whether a parameter changes the labour/material/plant consumption or the basis of percentage charges; finally determine whether a clause 2.0.27 error is constituted and fix responsibility by contract type.