The depth standard for describing item descriptions in the bill of quantities: describe item by item per the appendices, satisfy the needs of fixing the all-in unit rate, and never substitute the quota work content (trades)
The item description is the pricing parameter that fixes the all-in unit rate; the depth floor is 'describe item by item per the item descriptions prescribed in the appendices of the corresponding discipline measurement standard + satisfy the needs of fixing the all-in unit rate' (GB/T 50854-2024 clauses 4.2.4, 4.1.2). Citing a standard drawing collection or drawing number covers only 'the part it can satisfy' - the rest still needs words (GB 50860-2013 clause 4.2.4 commentary). Copying the work content (trades) of the quota / appendices replaces no item description: work content defines the included scope of the offer and the trade boundaries, and trades must not be split into separate items - copying produces no pricing parameters such as material, grade or strength class, and invites trade-splitting double pricing.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.5条、第2.0.27条
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 第4.1.2条、第4.2.4条、App. ETable E.1.1、第E.7.1条
- GB 50860-2013 构筑物工程工程量计算规范 第4.2.4条(强制性条文)及条文说明
- GB/T 50856-2024 通用安装工程工程量计算标准 第4.2.7条
Positioning
The depth requirement for BOQ item descriptions: how much is enough, how it divides work with 'work content', and whether the trade wording of the quota (appendix) work content can replace the description. Basis: GB/T 50500-2024, GB/T 50854-2024, GB 50860-2013 and GB/T 50856-2024 texts and commentaries.
Core conclusions
1. Definition and role (GB/T 50500-2024 term 2.0.5) 'Item description: the wording stating the essential nature and requirements of the BOQ item itself, used to describe the item required by the drawings, the technical standards and the tender documents.' The item description is an indispensable basis for fixing an item's all-in unit rate - the substantive test for whether a sentence belongs in the description column: does it affect the unit rate? If yes it must be written; if no, it should not.
2. Three depth floors (1) Item-by-item correspondence with the appendix, nothing missing - GB/T 50854-2024 clause 4.2.4: 'The item descriptions of the BOQ shall be described per the item descriptions prescribed in Appendices A to Q of this standard, combined with the actual conditions of the proposed works. The descriptions shall reflect the actual works - both the drawn design details and the code-required construction.' As many items as the appendix lists, so many are written; one fewer is incomplete description. (2) Enough to fix the all-in unit rate - not the more detail the better - clause 4.1.2: 'The item descriptions of the BOQ are an indispensable basis for fixing an item's all-in unit rate; in compiling the BOQ they must be described accurately and comprehensively, to the standard of regulated, concise, accurate and complete. The content shall follow the appendix provisions, combined with the actual works, to satisfy the needs of fixing the all-in unit rate.' (3) Citing drawing collections is allowed but removes no wording duty - GB 50860-2013 clause 4.2.4 (mandatory) commentary: '(1) description content follows the appendices, combined with the actual works, to satisfy the needs of fixing the all-in unit rate. (2) Where a standard collection or the construction drawings can fully or partly satisfy the description, the description may cite the collection or drawing number; the unsatisfied part is still described in words.' In practice, writing only 'see drawing A-05' while dropping strength class, waterproofing grade or substrate build-up leaves the description incomplete - the citation is no waiver.
3. The depth gauge comes from the appendices themselves
- GB/T 50854-2024 Table E.1.1 'foundation and floor bedding' (code 010501) lists exactly three: '1. foundation form; 2. thickness; 3. material type, strength requirement, mix ratio'.
- Clause E.7.1 general note for cast-in-place concrete: 'concrete type' may be described as ready-mixed, site-mixed, fair-faced, coloured, waterproof, acid-resistant, rubble or lightweight-aggregate concrete.
- Installation adds a layer - GB/T 50856-2024 clause 4.2.7: 'Where the principal item and the composite content do not correspond, the item description shall state the parameters, specifications and quantities of both.' (Complete sets / distribution boards: write both sides' parameters when they differ.)
4. Copying quota (appendix) work content replaces no item description GB/T 50854-2024 clause 4.1.2: 'The work content in the appendices lists only the principal construction content; auxiliary content certain to occur - plant movement, material transport - is included though unlisted. Unless specially stated, the construction trades corresponding to the work content must not be split into separately listed items.' The functions differ: work content answers 'which trades are to be done' - the included scope and trade boundaries of the offer (unlisted trades not charged separately, auxiliary content necessarily included, trades not split); the item description answers 'what is this thing and to what standard' - the parameter basis for selecting quota line items and building up rates. Copying trade wording like 'fabricate, install, remove, clean, stack': (1) still no priceable parameters - different concrete classes and masonry materials cannot be told apart, bidders can only guess; (2) invites trade splitting and duplicate itemisation, directly against 'trades must not be split'; (3) misfits the appendix, which asks for 'concrete type, strength class' while the copied column carries construction trades.
5. Consequences Descriptions not matching the drawings / contract specification, or missing items, are 'errors and omissions in the BOQ' (GB/T 50500-2024 term 2.0.27: differences between the listed items of the work-item list and those required by the contract drawings and specification - in itemisation, item descriptions or quantities, including extra items, omissions, description mismatch, quantity deviation and the like). Liability and price adjustment follow the contract's pricing method (unit-rate / lump-sum).
Applicable boundaries
- Depth follows the item descriptions of the discipline's own measurement standard: building and decoration GB/T 50854-2024 Appendices A-R; structures GB 50860-2013; general installation GB/T 50856-2024 - never borrow another discipline's tables.
- 'Describe per the appendix item by item' is not copying the appendix verbatim - it must be made concrete to the actual works (drawn details + code-required construction).
- Citing collections or drawing numbers helps only 'the part that satisfies'; parameters not covered still need words.
- This card covers how to write descriptions, not the liability and adjustment after mismatch or omission (unit-rate: clause 8.2; lump-sum: 6.1.7 - another domain).
Further reading
GB/T 50500-2024 terms 2.0.5 and 2.0.27; GB/T 50854-2024 clauses 4.1.2, 4.2.4, Table E.1.1, clause E.7.1; GB 50860-2013 clause 4.2.4 and commentary; GB/T 50856-2024 clause 4.2.7.
Keywords
- item description (work item specification)
- 项目特征描述
- 工作内容
- all-in unit rate
- errors and omissions in the BOQ
- GB/T 50854-2024
- GB/T 50500-2024
- 标准图集引用