Engineering Knowledge Cards.

all-in unit rate

39 knowledge cards · sorted by most recently updated

Concept Guide

Concept

In the Chinese bill-of-quantities pricing system, the all-in unit rate (zonghe danjia) is the core pricing unit. It is the sum of labour, materials, construction plant and machinery, enterprise overheads, profit, and a defined allowance for risk, all bundled into a single rate for one measured unit of a work item or a preliminaries item. The mechanism dates from the bill-of-quantities valuation standards introduced from 2003 onwards: the employer supplies the bill of quantities and bears responsibility for its accuracy, while tenderers fill in a rate for each item, producing the priced bill of quantities from which the tender total is aggregated.

Three features define the mechanism. First, quantity and price are separated: quantities are given by the employer, prices are competitively set by tenderers, so quantity risk sits with the employer and price risk with the contractor. Second, the rate is fully bundled: unlike the older quota-based approach, which listed labour, materials, plant, overheads and profit separately, the all-in unit rate merges them, and overheads and profit are no longer shown as separate lines in the bill or compared separately in tender evaluation. Third, the rate is adjustable: contracts commonly provide that where actual quantities deviate from billed quantities beyond an agreed threshold, where material prices fluctuate beyond an agreed risk band, or where a variation changes the item's characteristics, the rate may be adjusted or re-rated.

The all-in unit rate is therefore both a pricing device and a risk-allocation device: a defined band of risk is absorbed into the rate in advance, while risk beyond that band flows back into the contract price through the adjustment mechanism.

FIDIC Mapping

Under FIDIC contracts, the closest functional equivalent is the all-in unit rate entered in the bill of quantities (BOQ). In the Red Book framework, tenderers fill in rates and prices item by item, and the BOQ must be formed so that those rates cover, without duplication or omission, the total work to be carried out and all other obligations of the contractor under the contract. The bundling logic therefore runs in the same direction as the Chinese all-in unit rate.

The differences are substantive. First, the pricing route differs: the Chinese rate is built and reviewed against a national or regional quota system, with a strong regulatory flavour, whereas FIDIC rates and prices are set by the contractor on a self-priced basis, with no contractual quota, and both evaluation and payment follow the contractor's own filled rates. Second, adjustment differs: FIDIC handles re-rating through its variations and adjustments mechanism, under which a new rate is derived first from relevant rates or prices in the BOQ with reasonable adjustments, and only where no relevant rate exists is it derived from reasonable Cost plus profit; Chinese adjustment instead relies more on contractual deviation thresholds and external references such as published information prices and quotas. Third, the risk band differs: the "defined range of risk" inside a Chinese all-in unit rate is usually fixed by local valuation rules or special conditions, while under FIDIC risk allocation is set by the Conditions of Contract and Particular Conditions together, and the contractor must absorb foreseeable risk within its own rates.

Usage warning: in international tender or project documents, a literal word-for-word rendering of the Chinese term should not be used, as it is not the idiom of international BOQ practice. Use all-in unit rate, or rates and prices where the context is the BOQ itself, and state the cost composition where necessary so that the rate is not mistaken for one excluding overheads or profit.

Chinese TermEnglish TermFIDIC TermRelationNotes
综合单价all-in unit rateall-in rate / rates and pricesadjacent功能相近但组价路径不同:中国综合单价依托定额与计价规范组价并含约定风险包干,FIDIC 的 rates and prices 由承包商自主填报、无定额参照,风险分配由合同条件界定。
工程量清单bill of quantities (BOQ)Bill of Quantitiesadjacent两者均为量价分离的载体,但中国清单由招标人提供并承担工程量准确性责任,FIDIC 下 BOQ 的编制与计量程序由序言及合同约定,承包商填报单价时须自行覆盖全部义务。
变更计价valuation of variationsVariations and AdjustmentsadjacentFIDIC 下新单价优先由 BOQ 中相关单价推导并作合理调整,无相关单价时基于合理成本加利润;中国综合单价的调整更多依赖合同约定的偏差幅度与信息价、定额等外部参照。
综合单价调整re-rating of unit ratesnew rate or priceadjacent两者都触发单价重定,但触发条件不同:中国以工程量偏差幅度、材料价格波动幅度和项目特征不符为主要触发点,FIDIC 以变更指示及单价不再合理为主要触发点。

Updated 2026-09-13