Market-inquiry pricing when no applicable quota exists: the two-step method (multi-source inquiry → labor/material/machinery pricing) and traceability/audit requirements
A missing quota does not mean missing pricing rules: the all-in unit rate structure (labor/materials/machinery + management fee + profit + statutory fees + taxes) stays unchanged, with labor/material/machinery prices obtained instead from multi-channel market inquiries (online platforms / telephone / site visits / similar-project benchmarks), and consumption referenced from similar quotas with correction, manufacturer technical parameters, or field measurement. Inquiries must be multi-source and benchmarked, consistent with design parameters, and must not directly pick published prices; records are countersigned and a ledger kept; fees still accrue per the fee standards. The priority of price bases is contract agreement > price confirmed by both parties > published price > market inquiry — inquiry-based pricing is the last resort and requires employer / auditor acceptance with traceability (inquiry-verification report, preparation notes, all-in unit rate analysis sheets).
Applicable Codes
- GB/T 51095-2015 建设工程造价咨询规范
- GB/T 50500-2024 建设工程工程量清单计价标准
- DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范
- T/HAEC 013-2025 全过程工程咨询服务标准
- DB37/T 5096-2017 建设工程项目管理咨询规范
- DL/T 5468-2013 输变电工程施工图预算编制导则
Topic Positioning
This card covers "how to price from market inquiries when no quota applies": where the quota lacks an item and new materials/processes have no corresponding item, the all-in unit rate structure is unchanged (labor/materials/machinery + management fee + profit + statutory fees + taxes) — only the labor/material/machinery prices come from market inquiry, and consumption from corrected similar quotas / manufacturer parameters / field measurement. It gives the two-step workflow and the traceability and audit requirements.
Core Conclusions
Two steps: ① Market inquiry — online inquiry platforms, telephone, site visits, and similar-project benchmarks in parallel multi-channels; inquiries must be multi-source and compared, consistent with design parameters and the project positioning; published prices must not be picked directly and serve only as reference; inquiry records are countersigned by all participants, an inquiry ledger is kept and archived, and entries go into the price information base. ② Pricing — labor cost at market labor rates × workdays; material cost mainly from inquiry results (tax-exclusive basis) with published prices as fallback; machinery cost at machine-shift rental prices × consumption; consumption referenced from process-similar quota items with correction, from manufacturer technical parameters for equipment installation, or from field measurement and statistics for new materials/processes; management fee, profit, statutory fees, and taxes still accrue per the fee standards / fee quota at market levels — never report labor/materials/machinery alone. Priority of price bases: contract agreement > price confirmed by both parties > published price > market inquiry — inquiry-based pricing is the last resort and requires acceptance by the employer / auditor, otherwise the settlement may be overturned. Traceability: inquiry-verification report and ledger; preparation notes stating the missing-quota reason and price sources; item-by-item traceable all-in unit rate analysis sheets.
Applicable Boundaries
Applies where budget / BOQ pricing quotas lack an item and no similar item can be applied (new materials, new processes, equipment installation, etc.). Where a quota can be applied or applied with adjustment (including similar-process quotas or cross-industry quotas), market inquiry must not be used directly; for ordinary construction-type gaps prefer a supplementary unit valuation table per the quota compilation principles, and use inquiry pricing for price-oriented scenarios (equipment, specialist works). Note the new GB/T 50500-2024 basis: the all-in unit rate excludes VAT, and statutory fees are no longer listed separately.
Further Reading
GB/T 51095-2015 Clauses 5.3.9 (unit price composition principles) and 5.3.12 (supplementary unit valuation tables); GB/T 50500-2024 Clause 3.2.2 (all-in unit rate composition and risk costs); DBJ/T 15-153-2019 Clauses 7.6.1–7.6.4 (inquiry verification and ledger); T/HAEC 013-2025 Clause 11.4.3 (inquiry-verification organization); DB37/T 5096-2017 Clause 6.5.2 (countersigned market inquiry records); DL/T 5468-2013 Clauses 4.1.4, 4.1.12 (power industry missing-quota handling).